Bombay High Court Quashes Ban Order Against Contractor in ONGC Project Delay Dispute — Violation of Natural Justice. Internal Enquiry Report Not Shared With Contractor Before Imposing Business Ban, Rendering Order Arbitrary and Unreasonable.
8 Aug 2016The petitioner, Sarku Engineering Services SDN BHD, a Malaysian company, challenged an order dated 4 January 2016 issued by respondent No.2, Oil and N...