Supreme Court Dismisses Bank's Appeal in Consumer Dispute Over Cheque Clearing Deficiency. Bank held liable for deficiency in service under Consumer Protection Act, 1986 due to negligence in presenting cheques within validity period, with compensation awarded for loss caused by expired cheques.

The Supreme Court of India heard two civil appeals filed by Canara Bank against a judgment of the National Consumer Disputes Redressal Commission. The...

© Image Copyrights Juris Services & Technology

Bombay High Court Allows Retired Employees' Writ Petition for Pensionary Benefits Under Maharashtra Civil Services (Pension) Rules, 1982. Held that aided non-government educational institutions are bound to adopt government pension scheme for employees who retired after the cut-off date.

The petitioners, thirteen retired employees of Dr. Punjabrao Deshmukh Polytechnic, Amravati (respondent No.4), which is run by Shivaji Education Socie...

© Image Copyrights Juris Services & Technology

Bombay High Court Dismisses Writ Petition Challenging Land Acquisition for Resettlement Project Due to Unexplained Delay of 12 Years. Petitioners' challenge to 2006 order of Divisional Commissioner fails as they failed to demonstrate diligence after personal hearing in 2005.

The petitioners, four individuals who are grandchildren of the original landowner Babasaheb Khadirsaheb Pirjade, filed a writ petition in 2018 challen...

© Image Copyrights Juris Services & Technology

Bombay High Court Dismisses Petitioner's Claim for Additional Alternate Land After 49-Year Delay. Writ petition seeking allotment of 80R land under Nazare Project rejected as grossly delayed and lacking explanation for laches.

The petitioner, Nana Narayan Bhalerao (since deceased, through his legal heir Jalindar Nana Bhalerao), filed a writ petition under Article 226 of the ...

© Image Copyrights Juris Services & Technology

Bombay High Court Dismisses Petitioner's Claim for Shortfall Land Due to Delay and Laches. Claim for balance land under Maharashtra Project Affected Persons Rehabilitation Act, 1999 rejected as application made 37 years after acquisition award and 20 years after enactment without explanation.

The petitioner, legal heir of Tatoba Rama Chavan, filed a writ petition under Article 226 of the Constitution of India seeking a direction to the resp...

© Image Copyrights Juris Services & Technology

Supreme Court Allows Appointment of Arbitrator in Defence Contract Dispute Over Encashment of Warranty Bond. The court held that the claims were not barred by limitation as bilateral discussions continued until 2019, and the arbitration clause covered the dispute.

The petitioner, a Swiss company engaged in arms manufacturing, entered into a contract with the Ministry of Defence, Government of India, for supply o...

© Image Copyrights Juris Services & Technology

Bombay High Court Dismisses Appeal in Share Dispute — No Grounds for Interference Under Section 37 of Arbitration and Conciliation Act, 1996. Court Held That the Arbitral Tribunal's Findings on Non-Delivery of Shares and Limitation Were Not Perverse or Contrary to Law.

The appellant, M/s Satish K. Narang & Co., an investor, filed an appeal under Section 37 of the Arbitration and Conciliation Act, 1996, against the ju...

© Image Copyrights Juris Services & Technology

Bombay High Court Quashes Labour Court Award in Stale Industrial Dispute Case — Delay of 12 Years in Reference Held Fatal. Reinstatement Order Set Aside as Labour Court Erred in Shifting Burden of Proof on Employer Under Industrial Disputes Act, 1947.

The petitioner, the Executive Engineer of the Public Works Department, Wardha, challenged an Award dated 7.3.2006 passed by the Labour Court, Wardha i...