Bombay High Court Partially Upholds Arbitral Award in Railway Contract Dispute — Interest Rate Reduced from 18% to 9%. The court held that the arbitrator's award did not violate public policy but reduced the interest rate as excessive under Section 34 of the Arbitration and Conciliation Act, 1996.

The petitioner, Union of India, challenged an arbitral award dated 8 October 2010 under Section 34 of the Arbitration and Conciliation Act, 1996. The ...

© Image Copyrights Juris Services & Technology

Bombay High Court Dismisses Appeal for Recovery of Fishing Rights Compensation Due to Lack of Evidence of Loss. Agreement for fishing rights at sluice gates did not confer exclusive rights, and plaintiff failed to prove actual loss from alleged breach.

The appellant, originally Orlando Dias and later his widow Maria Fausta Dias, filed a first appeal against the judgment and decree dated 29/10/2005 of...

© Image Copyrights Juris Services & Technology

Bombay High Court Dismisses Petition Challenging Arbitral Award in Specific Performance Dispute. Court upholds arbitrator's discretion to deny specific performance and award damages instead, finding no grounds for interference under Section 34 of the Arbitration and Conciliation Act, 1996.

The petitioner, Rolta India Ltd., challenged an arbitral award dated 8th December, 2010 under Section 34 of the Arbitration and Conciliation Act, 1996...

© Image Copyrights Juris Services & Technology

Bombay High Court Dismisses Appeal Against Rejection of Time-Barred Counterclaim in Arbitration. Limitation for Counterclaim Runs from Date of Termination of Contract, Not from Subsequent Correspondence.

The appeal arose from an order dated 1 October 2012 passed by a learned Single Judge under Section 34 of the Arbitration and Conciliation Act, 1996, d...

© Image Copyrights Juris Services & Technology

High Court of Bombay at Goa Dismisses Appeal Against Arbitral Award in Construction Contract Dispute. Court holds that arbitrators are not bound to give reasons for each item of claim and that the award is not liable to be set aside for non-speaking nature under the Arbitration Act, 1940.

The appellant, Board of Trustees of Port of Mormugao, a body corporate under the Major Port Trusts Act, 1963, entered into a contract dated 12/10/1985...

© Image Copyrights Juris Services & Technology

Bombay High Court Allows Appeal in Part in Flat Purchase Dispute — Earnest Money Refund with Daily Fine and Compound Interest Upheld but Reduced. Clause 4 of Agreement for Construction and Sale Held to Be a Valid Forfeiture Clause, Not a Penalty, Under Section 74 of the Indian Contract Act, 1872.

The plaintiff, Dr. Jagdish J.N. Counte, entered into a written agreement dated 13.4.96 with the defendant, M/s. Carl Estate Private Limited, for the p...