Case Note & Summary
The case involved the State of Bihar and another party against Girija Prasad Sharma and another. On 12.5.2009, the court noted that none appeared on behalf of the parties. The court granted time until 23.6.2009 for the parties to carry out the order of the learned Lawazima Board dated 3.3.2009. This compliance was subject to the deposit of costs amounting to Rs.1000/- with the Secretary of the High Court Legal Services Committee, Patna, within the same period. The court indicated that failure to comply would lead to the rejection of the application without further reference to the Bench. The decision emphasized the importance of adhering to court orders and the consequences of non-compliance.
Headnote
A) Administrative Law - Compliance with Court Orders - Time Granted for Compliance - Not applicable - The court granted time until 23.6.2009 for the parties to comply with the order of the learned Lawazima Board dated 3.3.2009, subject to the deposit of costs. Failure to comply would result in rejection of the application without further reference to the Bench. Held that compliance is essential for the continuation of the application (Paras 5).
Issue of Consideration
Whether the parties complied with the order of the learned Lawazima Board and the implications of non-compliance.
Final Decision
The court granted time until 23.6.2009 for compliance with the order of the learned Lawazima Board, subject to the deposit of costs. Failure to comply would result in rejection of the application.
Law Points
- Compliance with court orders
- Legal costs
- Legal services committee procedures