The High Court of Judicature at Bombay dealt with two writ petitions concerning the liability of an incoming developer for financial obligations incurred by an erstwhile developer in a real estate redevelopment project. The petitioner, H. Rishabraj Developers, challenged an order from the Maharashtra Real Estate Regulatory Authority (MahaRERA) that directed both the petitioner and the erstwhile developer to pay interest on a principal amount of Rs. 37 lakhs owed to flat purchasers. The petitioner contended that it was not a party to the original order requiring payment and argued that MahaRERA lacked the authority to review its own orders. The court noted that the petitioner had executed a development agreement with the trust that owned the property and had completed the redevelopment. The court found that the liability for the financial obligations of the erstwhile developer could be transferred to the new developer, particularly regarding interest payments. The court also addressed the review powers of MahaRERA, concluding that it had the jurisdiction to review its orders based on subsequent events, such as the default of the erstwhile developer. The court ultimately upheld the order of MahaRERA, affirming the new developer's liability for interest payments while rejecting claims for compensation due to lack of evidence. The decision emphasized the importance of ensuring that allottees are not left without recourse due to the defaults of developers. The court dismissed the petitions challenging the orders of MahaRERA and the attachment of the petitioner's bank accounts under the Maharashtra Land Revenue Code.
Headnote
A) Real Estate Law - Liability of Incoming Developer - Financial Obligations - Real Estate (Regulation and Development) Act, 2016, Sections 15, 18 - The court examined the liability of the new developer for the financial obligations of the erstwhile developer towards flat purchasers, holding that the new developer could be held liable for interest on amounts paid by allottees. (Paras 1-5). B) Review Powers of MahaRERA - Jurisdiction to Review Orders - Real Estate (Regulation and Development) Act, 2016 - The court addressed the issue of whether MahaRERA has the power to review its own orders, concluding that such power exists under the regulations, and the review was justified based on subsequent events. (Paras 7-19).
Issue of Consideration
Whether the incoming developer is liable for the financial obligations incurred by the erstwhile developer towards purchasers of flats in a redevelopment project.
Final Decision
The court upheld the order of MahaRERA, affirming the new developer's liability for interest payments on the principal amount owed to allottees and dismissed the petitions challenging the orders.
Law Points
- Liability of incoming developer
- Review powers of MahaRERA
- Interest on principal amount
- RERA Act