The case involved L.R. Builders Pvt. Ltd. as the appellant against P.P. Jewellers Pvt. Ltd. and another respondent. The appeal was initially listed on 02.04.2026 but was relisted for 10.04.2026 due to procedural issues regarding the filing of replies. On 10.04.2026, it was noted that the reply had not been filed as formal notice was not issued, leading to the withdrawal of an application. During the arguments, the appellant's counsel indicated the intention to withdraw the appeal and pursue contentions before the NCLT in related cases. Consequently, the Tribunal dismissed the appeal as withdrawn, allowing both parties to present their arguments before the NCLT without examining the merits of the case. All pending applications were also disposed of.
Headnote
A) Company Law - Withdrawal of Appeal - Dismissal of Appeal as Withdrawn - Company Appeal (AT) No. 116 of 2026 - The appellant expressed intent to withdraw the appeal and raise all rights and contentions before the NCLT in related matters. The Tribunal dismissed the appeal as withdrawn, emphasizing that it had not examined the matter on merit (Paras 4-5).
Issue of Consideration
Whether the appeal should be withdrawn and the parties directed to present their contentions before the NCLT.
Final Decision
The appeal was dismissed as withdrawn, allowing both parties to present their contentions before the NCLT. The Tribunal did not examine the matter on merit.
Law Points
- Withdrawal of appeal
- Jurisdiction of NCLT