National Company Law Appellate Tribunal Dismisses Appeal Against NCLT Order on Insolvency. The Tribunal upheld the NCLT's dismissal of the operational creditor's petition, emphasizing the existence of a prior dispute regarding payments.

Tribunals: National Company Law Appellate Tribunal Bench: NEW DELHI
  • 0
Judgement Image
Font size:
Print

Case Note & Summary

The case involved an appeal by Hotel Horizon Private Limited against an order of the National Company Law Tribunal (NCLT) that dismissed its petition under Section 9 of the Insolvency and Bankruptcy Code, 2016, for recovery of dues amounting to Rs. 2.62 crore from Tea4Health Private Limited. The appellant contended that the delay in refiling the appeal was due to the impact of the Covid-19 pandemic on its operations and staffing, which hindered timely document submission. The Tribunal condoned the delay of 133 days in refiling the appeal, acknowledging the ex-parte nature of the proceedings against the respondent. The NCLT had previously found that the corporate debtor had paid most dues until February 2019 and that a prior dispute existed regarding payments due after the initiation of the Corporate Insolvency Resolution Process (CIRP) against the operational creditor. The Tribunal upheld the NCLT's dismissal of the petition, stating that the operational creditor's claims were subject to adjudication due to the ongoing disputes. The appeal was ultimately dismissed, reinforcing the NCLT's findings regarding the operational creditor's claims and the existence of a prior dispute.

Headnote

A) Insolvency Law - Condonation of Delay - Delay in Refilling Appeal - Section 61 of the Insolvency and Bankruptcy Code, 2016 - The appellant sought to condone a delay of 133 days in refiling the appeal due to the pandemic's impact on business operations and staffing issues. The Tribunal allowed the application for condonation of delay considering the circumstances and the ex-parte nature of the proceedings against the respondent. Held that the delay was not due to deliberate inaction (Paras 2-8).

B) Insolvency Law - Operational Creditor's Petition - Section 9 of the Insolvency and Bankruptcy Code, 2016 - The NCLT dismissed the operational creditor's petition for recovery of dues, finding that the corporate debtor had cleared most dues until February 2019 and that a prior dispute existed regarding payments post-CIRP initiation. The Tribunal upheld the NCLT's decision, emphasizing the need for adjudication on the disputed amounts (Paras 10-14).

Subscribe to unlock Headnote Subscribe Now

Issue of Consideration

Whether the delay in refiling the appeal should be condoned and whether the NCLT's dismissal of the operational creditor's petition was justified.

Subscribe to unlock Issue of Consideration Subscribe Now

Final Decision

The Tribunal allowed the application for condonation of delay of 133 days in refiling the appeal and upheld the NCLT's dismissal of the operational creditor's petition, emphasizing the existence of a prior dispute regarding payments.

Law Points

  • Insolvency and Bankruptcy
  • Corporate Insolvency Resolution Process
  • Condonation of Delay
  • Operational Creditor Rights
Subscribe to unlock Law Points Subscribe Now

Case Details

2026 LawText (NCLAT) (05) 68

Company Appeal (AT) (Ins) No. 1443 of 2023

2026-05-06

Justice Mohd. Faiz Alam Khan

Mr. Vaijant Paliwal, Mr. Nikhil Mathur, Ms. Shruti Poddar

Hotel Horizon Private Limited

Tea4Health Private Limited

Subscribe to unlock Case Details (Citation, Judge, Date & more) Subscribe Now

Nature of Litigation

Appeal against the dismissal of a petition under the Insolvency and Bankruptcy Code.

Remedy Sought

Condonation of delay in refiling the appeal and reversal of NCLT's dismissal of the petition.

Filing Reason

Delay due to pandemic impact on business operations.

Previous Decisions

NCLT dismissed the operational creditor's petition for recovery of dues.

Issues

Whether the delay in refiling the appeal should be condoned. Whether the NCLT's dismissal of the operational creditor's petition was justified.

Submissions/Arguments

The appellant argued that the delay was due to the pandemic and staffing issues. The respondent did not appear, leading to ex-parte proceedings.

Ratio Decidendi

The Tribunal emphasized the necessity of adjudication on disputed amounts and upheld the NCLT's findings regarding the operational creditor's claims.

Judgment Excerpts

The delay occurred in refiling is not due to any deliberate act of the appellant and may kindly be condoned. The petition bearing CP (IB) 1285/MB - IV/2020 filed by Hotel Horizon Private Limited, the Operational Creditor/Applicant, under section 9 of Insolvency & Bankruptcy Code, 2016 (I&B Code) seeking initiation of Corporate Insolvency Resolution Process (CIRP) against Tea4Health Private Limited, Corporate Debtor, is hereby Rejected. We find that dues till February 2019 have mostly been cleared by the Corporate Debtor and only amount charged on account of GST on such dues is withheld.

Procedural History

The appeal was filed on 02.05.2023, with a delay of 133 days in refiling due to pandemic-related issues. The NCLT dismissed the operational creditor's petition on 31.03.2023, leading to the current appeal.

Acts & Sections

  • Insolvency and Bankruptcy Code, 2016: Section 9, Section 61
Subscribe to unlock full Legal Analysis Subscribe Now
Related Judgement
High Court Gujarat High Court Allows Petition for Benefit of Government Resolution Dated 17.10.1988 in Service Matter — Petitioner Entitled to Pay Revision and Arrears as Per Precedents. The Court held that the petitioner, working in the same post and organiz...
Related Judgement
High Court Bombay High Court Upholds Lease Rent Revision Based on Ready Reckoner Rates for Housing Societies in Bandra. Court holds that linkage of lease rent to land value is not per se prohibited and the Government Resolutions of 2006, 2012, and 2018 are cons...