National Company Law Appellate Tribunal Upholds Resolution Plan Approval in Insolvency Case — Fairness of CIRP Process Questioned.

Tribunals: National Company Law Appellate Tribunal Bench: NEW DELHI
  • 19
Judgement Image
Font size:
Print

Case Note & Summary

The case involved two appeals against an order from the National Company Law Tribunal regarding the Corporate Insolvency Resolution Process (CIRP) of Aldiam Motors Pvt. Ltd. The appeals were filed by the Resolution Professional and the Successful Resolution Applicant after the Adjudicating Authority rejected the approval of a Resolution Plan and restored the CIRP to an earlier stage. The Corporate Debtor had defaulted on loans from IDBI Bank, leading to the initiation of CIRP. The Adjudicating Authority found that the CIRP was marred by irregularities, particularly concerning the valuation of assets and the transparency of the process. It noted that the Successful Resolution Applicant had an informational advantage, which affected the integrity of the resolution process. The Authority concluded that the Resolution Plan submitted by Claro Energy was non-compliant and upheld the decision to reject the Plan approval application. The appeals challenged the findings of the Adjudicating Authority, arguing that the CIRP was conducted fairly and that the Resolution Plan was compliant with the Code. The court ultimately upheld the Adjudicating Authority's decision, emphasizing the need for transparency and fairness in the CIRP process.

Headnote

A) Insolvency Law - Corporate Insolvency Resolution Process - Fairness and Transparency - Insolvency and Bankruptcy Code, 2016, Section 29A - The Adjudicating Authority found that the CIRP was affected by material irregularities, impacting the fairness and integrity of the process, leading to the rejection of the Resolution Plan. Held that the CIRP must be conducted transparently to ensure all applicants have equal access to information (Paras 30-32).

B) Insolvency Law - Eligibility of Resolution Applicant - Compliance with Section 29A - The Adjudicating Authority concluded that the Successful Resolution Applicant was not ineligible under Section 29A, despite concerns raised about informational advantages. Held that statutory disqualification was not attracted (Paras 31-32).

C) Insolvency Law - Resolution Plan Approval - Compliance with Section 30(2) - The Adjudicating Authority ruled that the Resolution Plan submitted by Claro Energy was non-compliant, justifying the rejection of the Plan approval application. Held that compliance with the Code's requirements is essential for approval (Paras 32-33).

Subscribe to unlock Headnote Subscribe Now

Issue of Consideration

Whether the CIRP was conducted in a fair and transparent manner and if the Resolution Plan submitted by the Successful Resolution Applicant complied with the requirements of the Insolvency and Bankruptcy Code.

Subscribe to unlock Issue of Consideration Subscribe Now

Final Decision

The National Company Law Appellate Tribunal allowed both appeals, reviving the Plan approval application filed by the RP for fresh consideration and closing the applications filed by Claro Energy.

Law Points

  • Insolvency resolution
  • CIRP process
  • eligibility under Section 29A
  • compliance of Resolution Plan
  • transparency in CIRP
  • valuation of assets
Subscribe to unlock Law Points Subscribe Now

Case Details

2026 LawText (NCLAT) (05) 40

Company Appeal (AT) (Ins.) Nos. 512 & 513 of 2026

2026-03-12

Ashok Bhushan

Mr. Krishnendu Datta, Mr. Abhijeet Sinha, Mr. Anand Varma, Mr. Sandeep Bajaj, Ms. Honey Satpal, Mr. Mayank Biyani, Mr. Akash Agarwalla, Nipun Singhvi, Mr. Aman

Manohar Lal Vij, Meghdoot Leisure LLP

Khushvinder Singhal & Ors.

Subscribe to unlock Case Details (Citation, Judge, Date & more) Subscribe Now

Nature of Litigation

Appeal against the order of the National Company Law Tribunal regarding the approval of a Resolution Plan in insolvency proceedings.

Remedy Sought

The appellants sought to overturn the rejection of the Resolution Plan and restore the approval granted by the Committee of Creditors.

Filing Reason

The Adjudicating Authority rejected the Resolution Plan citing material irregularities in the CIRP process.

Previous Decisions

The Adjudicating Authority had previously admitted the Section 7 application and appointed an Interim Resolution Professional.

Issues

Whether the CIRP was conducted in a fair and transparent manner. Whether the Resolution Plan submitted by the Successful Resolution Applicant complied with the requirements of the Insolvency and Bankruptcy Code.

Submissions/Arguments

The RP argued that the Adjudicating Authority erred in rejecting the Plan approval application, which was approved by 100% of the CoC. Claro Energy contended that the CIRP was not conducted transparently and raised concerns about the possession of assets.

Ratio Decidendi

The decision emphasized the importance of conducting the Corporate Insolvency Resolution Process in a fair and transparent manner, ensuring that all resolution applicants have equal access to information and that the Resolution Plans comply with the requirements of the Insolvency and Bankruptcy Code.

Judgment Excerpts

The CIRP process was affected by material irregularity, which have a direct bearing on fairness and integrity of the resolution process. The Adjudicating Authority concluded that the Successful Resolution Applicant was not ineligible under Section 29A. The Resolution Plan submitted by Claro Energy was non-compliant, justifying the rejection of the Plan approval application.

Procedural History

The appeals were filed against the order of the National Company Law Tribunal which rejected the Resolution Plan and restored the CIRP to an earlier stage. The CIRP was initiated following a default on loans by the Corporate Debtor.

Acts & Sections

  • Insolvency and Bankruptcy Code, 2016: Section 29A, Section 30(2)
  • SARFAESI Act, 2002: Section 13(2)
Subscribe to unlock full Legal Analysis Subscribe Now
Related Judgement
Supreme Court Supreme Court Sets Aside High Court Order Allowing Withdrawal of Suit with Leave to File Fresh Suit. The High Court failed to properly assess the grounds for withdrawal under Order XXIII Rule 1(3) of the Code of Civil Procedure, 1908, leading to an e...
Related Judgement
Supreme Court Supreme Court Dismisses Appeal in Rash Driving Case Resulting in Death. Court Emphasizes Deterrent Sentencing for Professional Drivers to Curb Road Accidents.