The appeal arose from a dispute concerning the constitution of the Committee of Creditors (CoC) in a corporate insolvency resolution process. The Appellant, Ashok Tiwari, contended that the CoC was improperly constituted by the Resolution Professional (RP) and had taken decisions, including the replacement of the RP, without awaiting the outcome of an application challenging the CoC's constitution, which was pending before the Adjudicating Authority. The Appellant sought a similar interim order as granted in a related appeal, Comp. App. (AT) (Ins) No. 704 of 2025, which allowed the newly appointed RP to proceed but required leave from the Tribunal before issuing form G. The Respondents did not dispute the facts regarding the interim order in the previous appeal. The Tribunal acknowledged the pending application and the Appellant's grievances regarding the CoC's decisions. It concluded that the appeal should be disposed of with a request to the Adjudicating Authority to expedite the pending application and allowed the newly appointed RP to proceed with the resolution process, subject to obtaining leave before issuing form G. The Tribunal excluded the period from 21.07.2025 until the date of the order from the calculation of the Corporate Insolvency Resolution Process (CIRP) period, and no costs were awarded.
Headnote
A) Insolvency Law - Committee of Creditors - Constitution Challenge - Insolvency and Bankruptcy Code, 2016, Section Not mentioned - The Appellant challenged the constitution of the Committee of Creditors (CoC) by filing an application which is pending before the Adjudicating Authority. The Tribunal directed that the CoC should not take further decisions until the application is resolved, ensuring the Appellant's grievances are addressed (Paras 1-4).
Issue of Consideration
Whether the appeal regarding the constitution of the Committee of Creditors should be disposed of while an application challenging the constitution is pending before the Adjudicating Authority.
Final Decision
The Tribunal disposed of the appeal, requesting the Adjudicating Authority to expedite the pending application and allowing the newly appointed RP to proceed with the resolution process, subject to obtaining leave before issuing form G. The period from 21.07.2025 until the date of the order was excluded from the calculation of the CIRP period.
Law Points
- Constitution of Committee of Creditors
- Interim Orders
- Resolution Process
- Adjudicating Authority
- Corporate Insolvency Resolution Process