NATIONAL COMPANY LAW APPELLATE TRIBUNAL Upholds Appellant's Claim for Electricity Charges During CIRP — Dismissal for Non-Prosecution Reversed.

Tribunals: National Company Law Appellate Tribunal Bench: New Delhi
  • 1
Judgement Image
Font size:
Print

Case Note & Summary

The dispute arose between a statutory distribution licensee and a corporate debtor undergoing Corporate Insolvency Resolution Process (CIRP). The Appellant, Eastern Power Distribution Company of Andhra Pradesh Limited, was aggrieved by an order of the National Company Law Tribunal (NCLT) dismissing its application for recovery of electricity charges during the moratorium period. The Corporate Debtor, Impex Metal & Ferro Alloys Limited, was placed under CIRP due to default in payments. The Appellant contended that electricity supply is an essential service protected under the Insolvency and Bankruptcy Code, 2016 (I&B Code), and thus it was entitled to recover the dues. The NCLT had previously acknowledged the Appellant's right to claim CIRP costs for electricity supplied during the moratorium. However, the Appellant's application was dismissed for non-prosecution due to the absence of its counsel. The Appellant filed a restoration application, arguing that the dismissal was due to the negligence of its previous counsel, who failed to appear in court. The Tribunal analyzed the circumstances surrounding the counsel's absence and the ethical obligations under the Bar Council of India Rules. It concluded that the Appellant should not be penalized for the counsel's deliberate inaction and that the restoration application should be considered on its merits. The Tribunal ultimately reversed the dismissal and allowed the Appellant to pursue its claim for electricity charges during the CIRP period.

Headnote

A) Insolvency Law - Moratorium on Essential Services - Recovery of Electricity Charges - Insolvency and Bankruptcy Code, 2016, Section 14 - The Appellant, a distribution licensee, sought recovery of electricity charges during the moratorium period imposed under CIRP. The Tribunal held that electricity is an essential service and the Appellant is entitled to recover the charges as CIRP costs (Paras 3-11).

B) Legal Representation - Counsel's Negligence - Restoration of Application - NCLT Rules, Rule 48 - The Tribunal considered the implications of counsel's absence leading to dismissal for non-prosecution. It was held that the Appellant should not suffer due to the deliberate inaction of the counsel, and the application for restoration was warranted (Paras 20-26).

Subscribe to unlock Headnote Subscribe Now

Issue of Consideration

Whether the dismissal of the application for want of prosecution due to counsel's absence can be reversed and whether the appellant is entitled to recover electricity charges during the moratorium period.

Subscribe to unlock Issue of Consideration Subscribe Now

Final Decision

The Tribunal allowed the restoration application, quashed the dismissal order of 08.11.2023, and directed that the application I.A. No. 1061 of 2021 be considered on its own merits.

Law Points

  • Electricity Act
  • 2003
  • Insolvency and Bankruptcy Code
  • 2016
  • moratorium
  • essential services
  • CIRP costs
  • counsel's negligence
Subscribe to unlock Law Points Subscribe Now

Case Details

2026 LawText (NCLAT) (09) 164

Company Appeal (AT) (Insolvency) No. 347 of 2026

2026-09-25

Justice Sharad Kumar Sharma

Mr. Joy Saha, Sr. Advocate, Mr. Sidhartha Sharma, Mr. Rishav Dutt, Mr. Aman Kataruka, Mr. Shaunak Mitra, Mr. Riyanshu Agarwal

EASTERN POWER DISTRIBUTION COMPANY OF ANDHRA PRADESH LIMITED

DAULAT RESOLUTION SERVICES PVT. LTD.

Subscribe to unlock Case Details (Citation, Judge, Date & more) Subscribe Now

Nature of Litigation

Dispute regarding recovery of electricity charges during CIRP.

Remedy Sought

Appellant sought recovery of Rs. 20,72,84,722 as CIRP costs.

Filing Reason

The Appellant filed for restoration after dismissal of its application for non-prosecution.

Previous Decisions

NCLT had previously acknowledged the Appellant's right to claim CIRP costs for electricity supplied.

Issues

Entitlement to recover electricity charges during moratorium Effect of counsel's absence on application for restoration

Submissions/Arguments

Appellant argued that electricity is an essential service and should be recoverable during CIRP. Respondent contended that the restoration application was barred by time and the absence of counsel was deliberate.

Ratio Decidendi

The Tribunal held that a litigant should not suffer due to the negligence or deliberate inaction of their counsel, and that essential services like electricity are recoverable during the moratorium period under the I&B Code.

Judgment Excerpts

Electricity is an essential service and the Appellant is entitled to recover the charges as CIRP costs. The Appellant should not suffer due to the deliberate inaction of the counsel.

Procedural History

The Appellant's application for recovery of electricity charges was dismissed for non-prosecution on 08.11.2023. The Appellant filed a restoration application on 25.07.2024, which was considered by the Tribunal.

Acts & Sections

  • Electricity Act, 2003: Section 2(15)
  • Insolvency and Bankruptcy Code, 2016: Section 14
Subscribe to unlock full Legal Analysis Subscribe Now
Related Judgement
High Court High Court of Karnataka Enhances Compensation for Amputation Victim in Motor Accident Claim — Below Knee Amputation of Left Leg Results in Increased Award from ₹5,98,300 to ₹15,00,000. The Court held that loss of earning capacity should be asse...
Related Judgement
High Court Bombay High Court Allows Arbitration Petition and Interim Application in Share Dispute — Appointment of Arbitrator and Injunction Granted. Court holds that disputes regarding share transfer and oppression are arbitrable and appoints arbitrator unde...