The National Company Law Appellate Tribunal addressed an application concerning the extension of time for curing defects in a Memo of Appeal filed by the Appellant, Sumit Sharma, against the Registrar of Companies, Kolkata. The Appellant had e-filed the Memo of Appeal on 21st July 2026, but upon scrutiny on 17th August 2026, the Office identified certain defects and notified the Appellant on the same day. The Appellant subsequently re-filed the Appeal on 25th August 2026. During the hearing, the learned counsel for the Appellant presented arguments regarding the necessity of condoning the delay. The Tribunal considered the submissions and the reasons provided in the Interlocutory Application, determining them to be sufficient. Consequently, the Tribunal condoned the delay of one day in re-filing the Memo of Appeal and ordered that the case be listed for admission under the fresh case heading. The Interlocutory Application was thus disposed of.
Headnote
A) Company Law - Condonation of Delay - Delay in Re-filing Memo of Appeal - Companies Act, 2013 - The Appellant sought to extend the time for curing defects in the Memo of Appeal, which was initially filed electronically. The Tribunal found the reasons provided in the Interlocutory Application sufficient to condone the delay of one day in re-filing the Memo of Appeal and directed the case to be listed for admission. Held that the delay was condoned (Paras Not mentioned).
Issue of Consideration
Whether the delay in re-filing the Memo of Appeal should be condoned.
Final Decision
The Tribunal condoned the delay of one day in re-filing the Memo of Appeal and directed that the case be listed for admission under the fresh case heading.
Law Points
- Condonation of delay
- e-filing procedures