Supreme Court Allows Appellant to Complete Housing Project Under IBC Framework — Upholds Settlement Terms. The court emphasized the importance of homebuyers' interests and the promoter's undertaking regarding project completion.

In Favour of Accused
  • 1
Judgement Image
Font size:
Print

Case Note & Summary

The appeal arose from an order of the National Company Law Appellate Tribunal (NCLAT) rejecting a modification application filed by the appellant, who was the Suspended Director of the Corporate Debtor, Soni Infratech Private Limited. The appellant sought to complete a housing project after a homebuyer, respondent No.2, cancelled their booking and initiated Corporate Insolvency Resolution Process (CIRP) under Section 7 of the Insolvency and Bankruptcy Code, 2016 (IBC). The NCLT admitted the application and appointed an Interim Resolution Professional (IRP). The appellant's subsequent appeals to the NCLAT included requests for settlement terms to cover all homebuyers, which were initially met with resistance. However, after several meetings and submissions, including a Revised Proposed Settlement Plan, the NCLAT ultimately rejected the appellant's modification application, leading to the present appeal. The appellant argued that a settlement had been reached with most stakeholders and that the project was nearly complete. The NCLAT's failure to consider the minutes of a crucial meeting held on October 23, 2021, where most issues were resolved, was highlighted. The court found that the promoter had made significant commitments to complete the project without escalating costs and had arranged necessary funding. The court emphasized the importance of the homebuyers' interests and the promoter's undertaking to complete the project. Consequently, the Supreme Court allowed the appeal, quashing the NCLAT's order and permitting the appellant to proceed with the project under the agreed terms, while also mandating quarterly progress reports to the NCLAT.

Headnote

A) Insolvency Law - Corporate Insolvency Resolution Process - Settlement Terms - Section 12A of the Insolvency and Bankruptcy Code, 2016 - The court allowed the appellant to complete the housing project based on the settlement terms agreed upon with stakeholders, emphasizing the importance of homebuyers' interests and the undertaking provided by the promoter regarding project completion timelines and costs. Held that the interests of homebuyers were paramount and the proposed settlement was in their favor (Paras 21-24).

Subscribe to unlock Headnote Subscribe Now

Issue of Consideration

Whether the appellant should be permitted to complete the housing project despite the ongoing Corporate Insolvency Resolution Process.

Subscribe to unlock Issue of Consideration Subscribe Now

Final Decision

The Supreme Court allowed the appeal, quashed the NCLAT's order dated 22nd November 2021, and permitted the appellant to complete the housing project as per the settlement terms. The court mandated quarterly progress reports to the NCLAT and set a date for the first status report.

Law Points

  • Insolvency and Bankruptcy Code
  • 2016
  • Corporate Insolvency Resolution Process
  • settlement terms
  • homebuyers' interests
Subscribe to unlock Law Points Subscribe Now

Case Details

2022 LawText (SC) (04) 236

Civil Appeal No. 7534 of 2021

2022-04-27

L. Nageswara Rao, B.R. Gavai

Shri Shyam Divan, Shri D.N. Goburdhun, Shri Abhigya Kushwah

Anand Murti

Soni Infratech Private Limited & Anr.

Subscribe to unlock Case Details (Citation, Judge, Date & more) Subscribe Now

Nature of Litigation

Appeal against NCLAT's order rejecting modification application in CIRP proceedings.

Remedy Sought

Appellant sought permission to complete the housing project.

Filing Reason

NCLAT rejected the modification application regarding settlement terms.

Previous Decisions

NCLT admitted the CIRP application and NCLAT issued interim orders affecting the CIRP.

Issues

Whether the appellant should be allowed to complete the housing project despite the ongoing CIRP. Whether the settlement terms proposed by the appellant were sufficient to protect the interests of all homebuyers.

Submissions/Arguments

Appellant argued that a settlement was reached with stakeholders and the project was nearly complete. Respondents contended that the appellant's proposed settlement was not bona fide and aimed at delaying the project.

Ratio Decidendi

The court emphasized the importance of homebuyers' interests and the promoter's commitment to complete the project without escalating costs, allowing the appellant to proceed under the agreed settlement terms.

Judgment Excerpts

The appeal is allowed. The impugned order dated 22nd November, 2021 passed by the National Company Law Appellate Tribunal is quashed and set aside.

Procedural History

The appellant filed a modification application after the NCLAT's interim orders and subsequent rejection of the application led to the present appeal.

Acts & Sections

  • Insolvency and Bankruptcy Code, 2016: Section 7, Section 12A
Subscribe to unlock full Legal Analysis Subscribe Now
Related Judgement
High Court Bombay High Court Allows Petitioners Challenging Enquiry Under Section 88 of Maharashtra Cooperative Societies Act Against Contractors and Suppliers. Enquiry Under Section 88 Cannot Be Conducted Against Persons Who Are Not Members, Past Members, or O...
Related Judgement
Supreme Court Supreme Court Dismisses Writ Petitions Challenging Seniority Lists Under Central Secretariat Service Rules Due to Lack of Evidence of Injustice. Petitioners Failed to Challenge the Validity of the Rules Governing Seniority and Promotion.