The dispute arose from a judgment by the High Court of Delhi which declared that the acquisition of certain land had lapsed under Section 24(2) of the Right to Fair Compensation and Transparency in Land Acquisition, Rehabilitation and Resettlement Act, 2013. The Delhi Development Authority appealed this decision, arguing that possession of the land had already been taken. The High Court's ruling relied on the precedent set by Pune Municipal Corporation v. Harakchand Misirimal Solanki, which was later overruled by the Supreme Court in Indore Development Authority v. Manoharlal. The Supreme Court clarified that under Section 24(2), if possession has been taken, the non-payment of compensation does not lead to a lapse of acquisition proceedings. The court emphasized that the lapse of acquisition occurs only when both possession and compensation have not been addressed for five years prior to the commencement of the 2013 Act. Consequently, the Supreme Court quashed the High Court's order and dismissed the original writ petition, affirming that the acquisition remained valid. The decision underscored the importance of distinguishing between the conditions that lead to the lapse of land acquisition proceedings and the obligations of authorities regarding compensation and possession.
Headnote
A) Land Acquisition - Lapse of Proceedings - Conditions for Lapse - Right to Fair Compensation and Transparency in Land Acquisition, Rehabilitation and Resettlement Act, 2013, Section 24(2) - The court held that if possession has been taken, non-payment of compensation does not result in lapse of acquisition proceedings. The decision in Pune Municipal Corporation was overruled, clarifying that lapse occurs only when both possession and compensation are absent for five years prior to the 2013 Act. (Paras 3-4).
Issue of Consideration
Whether the acquisition of land lapsed under Section 24(2) of the Right to Fair Compensation and Transparency in Land Acquisition, Rehabilitation and Resettlement Act, 2013 due to non-payment of compensation.
Final Decision
The Supreme Court quashed the High Court's order and dismissed the original writ petition, affirming that the acquisition remained valid as possession had been taken.
Law Points
- Land acquisition
- lapse of proceedings
- compensation
- possession
- Right to Fair Compensation and Transparency in Land Acquisition
- Rehabilitation and Resettlement Act
- 2013