Case Note & Summary
The case involved an appeal against the judgment and order of the High Court of Madhya Pradesh regarding the recovery of liquidated damages by the M.P. Road Development Authority from the appellant, a Class 'A' contractor. The appellant was awarded a contract for the construction and maintenance of rural roads under the Pradhan Mantri Gram Sadak Yojna, with a completion date set for October 21, 2009. However, the contract was terminated due to slow progress of work, and the authority sought to recover liquidated damages. The appellant challenged the recovery proceedings, arguing that the matter was sub judice before the Arbitral Tribunal. The High Court dismissed the petitions, leading to the appeal before the Supreme Court. The Supreme Court analyzed the relevant clauses of the contract and the provisions of the Madhya Pradesh Madhyastham Adhikaran Adhiniyam, 1983, concluding that the respondents could not initiate recovery proceedings while the dispute was pending adjudication. The court emphasized the principle that a party cannot be an arbiter in its own cause and quashed the High Court's judgments, allowing the appeal and directing that the Arbitral Tribunal should decide the pending reference independently. No costs were awarded.
Headnote
A) Arbitration - Recovery Proceedings - Initiation of recovery proceedings for liquidated damages pending arbitration - Madhya Pradesh Madhyastham Adhikaran Adhiniyam, 1983, Section 7 - The court held that the respondents were not justified in initiating recovery proceedings for liquidated damages while the matter was pending adjudication before the Arbitral Tribunal, emphasizing that a party cannot be an arbiter in its own cause (Paras 15-17).
Issue of Consideration
Whether the respondents were justified in initiating recovery proceedings for liquidated damages while the matter was pending adjudication before the Arbitral Tribunal.
Final Decision
The Supreme Court allowed the appeal, quashed the judgments of the High Court dated 26th February, 2018 and 7th September, 2018, and clarified that the observations made were solely for the purpose of disposal of the appeals, leaving the Arbitral Tribunal to decide the pending reference independently.
Law Points
- Liquidated damages
- arbitration
- recovery proceedings
- adjudication
- contract termination



