Case Note & Summary
The dispute arose from the reservation of land owned by a partnership firm under the Maharashtra Regional and Town Planning Act, 1966. The appellant, a partnership firm, owned land in Morshi, Maharashtra, which was reserved for a shopping center and garden in the final development plan published on 11.07.2005. The appellant served notices under Section 127 of the Act to the municipality, seeking dereservation after the lapse of ten years. The High Court dismissed the writ petition, stating that the second notice was premature and that the necessary procedures for acquisition were not satisfied. The appellant contended that the second notice was received after the stipulated period and that the municipality had not taken adequate steps for acquisition. The respondents argued that the notice was indeed premature as it was served before the completion of ten years from the final development plan's enforcement. The Supreme Court analyzed the provisions of Section 127, noting that the municipality had not taken sufficient steps towards acquisition within the required timeframe. The court concluded that the reservation had lapsed, allowing the appellant to develop the land. The court also expunged adverse remarks made by the High Court against the appellant's advocate. The appeal was allowed, directing the State Government to notify the lapsing of the reservation in the Official Gazette within four months.
Headnote
A) Land Acquisition - Lapsing of Reservation - Conditions for Lapsing - Maharashtra Regional and Town Planning Act, 1966, Section 127 - The court held that the reservation of the appellant's land lapsed as the municipality failed to take necessary steps for acquisition within the stipulated period after the notice was served. The court emphasized that the statutory requirements under Section 127(1) were satisfied, allowing the appellant to develop the land (Paras 18-21).
Issue of Consideration
Whether the reservation of the appellant's land lapsed under Section 127 of the Maharashtra Regional and Town Planning Act, 1966.
Final Decision
The Supreme Court allowed the appeal, holding that the reservation of the appellant's land had lapsed and directed the State Government to notify the lapsing in the Official Gazette within four months.
Law Points
- Maharashtra Regional and Town Planning Act
- 1966
- Section 127
- land acquisition
- reservation lapsing
- procedural compliance