Case Note & Summary
The dispute arose from a long-standing contractual relationship between the appellant and the respondent concerning flooring and cladding works at Vashi Railway Station. The respondent, National Building Construction Corporation Limited, awarded a sub-contract to the appellant, M/s Sharma Enterprises, in 1991 for a total of Rs.9,50,73,603.20, with a completion deadline of January 10, 1993. Due to delays in civil works by the primary contractor, the appellant could only complete limited work by the inauguration date in May 1992. The contract was terminated by the respondent in September 1992, leading the appellant to invoke arbitration. The learned Arbitrator ruled in favor of the appellant in 2016, awarding various claims but also including interest. The respondent challenged this award under Section 34 of the Arbitration and Conciliation Act, 1996, leading to a High Court ruling that upheld the substantive claims but set aside the interest award based on Clause 26 of the Special Conditions of Contract. The appellant's subsequent appeal to the Supreme Court contested this interpretation of the clause. The court analyzed the contractual language and relevant statutory provisions, ultimately agreeing with the High Court's interpretation that the clause constituted a bar against awarding interest. The appeal was dismissed, affirming the lower court's decision while maintaining the substantive claims and post-award interest.
Headnote
A) Arbitration Law - Interest Awards - Contractual Bar on Interest - Arbitration and Conciliation Act, 1996, Section 31(7)(a) - The court examined whether the contractual clause prohibited the award of pre-reference and pendente lite interest. It held that the phrase 'or otherwise' in Clause 26 of the SCC constituted a comprehensive bar against interest, aligning with precedents interpreting similar clauses. Thus, the High Court's decision to set aside the interest award was upheld (Paras 18-22).
Issue of Consideration
Whether Clause 26 of the Special Conditions of Contract operates as a contractual bar under Section 31(7)(a) of the Arbitration and Conciliation Act, 1996, preventing the Arbitral Tribunal from awarding pre-reference and pendente lite interest.
Final Decision
The Supreme Court dismissed the appeal, affirming the High Court's decision to set aside the arbitral award regarding interest while maintaining the substantive claims and post-award interest.
Law Points
- Arbitration
- Interest
- Contractual Prohibition
- Section 31(7)(a) Arbitration and Conciliation Act
- 1996
- Clause Interpretation



