High Court of Bombay Upholds Appeal by Promoters in Real Estate Dispute — Clarifies Obligations Under RERA.

High Court: Bombay High Court Bench: BOMBAY
  • 2
Judgement Image
Font size:
Print

Case Note & Summary

The judgment arose from a Second Appeal filed by Sanklecha Constructions Pvt. Ltd. and its directors against the Maharashtra Real Estate Appellate Tribunal's orders regarding the refund of amounts paid by allottees for a residential project named 'Waterways'. The allottees had booked a flat in the project but faced delays in possession delivery, leading them to file a complaint with MahaRERA. Initially, MahaRERA allowed the allottees to withdraw from the project and directed the promoter to refund the amounts paid along with interest, with the option to do so after obtaining an occupation certificate (OC). The allottees challenged this option, leading to the Appellate Tribunal's order that removed the option and mandated immediate refund with interest from the date of payment. The promoters contended that the Appellate Tribunal's decision disregarded mitigating circumstances affecting project completion and sought to reinstate the option to refund after obtaining the OC. The court analyzed the provisions of Section 18 of RERA, concluding that the right to a refund is absolute and unqualified, emphasizing that the promoter must comply with refund demands without delay. The court criticized the Appellate Tribunal's confusing orders and clarified the obligations under RERA, ultimately upholding the right of the allottees to receive their refunds immediately. The court directed the promoter to refund the amounts paid along with interest from January 1, 2018, as prescribed by the rules.

Headnote

A) Real Estate Law - Refund Obligations - Unqualified Right to Refund - Real Estate (Regulation and Development) Act, 2016, Section 18 - The court held that the right of the allottee to seek a refund under Section 18(1) of RERA is absolute and unqualified, and cannot be delayed by the promoter or regulatory authorities based on mitigating circumstances. The obligation to refund arises immediately upon demand by the allottee if the promoter fails to deliver possession as agreed (Paras 28-30).

Subscribe to unlock Headnote Subscribe Now

Issue of Consideration

Whether the obligation for the Promoter to return the amount received with interest on demand is absolute or if discretion exists for mitigating circumstances.

Subscribe to unlock Issue of Consideration Subscribe Now

Final Decision

The court upheld the appeal, clarifying that the obligation to refund is absolute and must be fulfilled immediately upon demand by the allottees, without discretion for mitigating circumstances. The court directed the promoter to refund the entire amount paid along with interest from January 1, 2018, as per the rules.

Law Points

  • Real Estate (Regulation and Development) Act
  • 2016
  • refund obligations
  • interest calculation
  • mitigating circumstances
  • unqualified right to refund
Subscribe to unlock Law Points Subscribe Now

Case Details

2026 LawText (BOM) (09) 136

Second Appeal (Stamp) No. 8825 of 2025

2026-09-28

SANDEEP V. MARNE

Mr. Abhishek Pungaliya, Mr. Akshay R. Kapadia

Sanklecha Constructions Pvt. Ltd., Vijay Kachardas Sanklecha, Dilip Kachardas Sanklecha, Puneet Ajit Sanklecha

Nitin Madhukar Shewale, Shital Nitin Shewale, Bhimashankar Laxman Janmali, Shrikrishna Laxman Janmali, Sitabai Laxman Janmali, Pushpa Jaggannath Janmali, Devemdra Jaggannath Janmali, Anil Laxman Janmali, Dinkar Laxman Janmali

Subscribe to unlock Case Details (Citation, Judge, Date & more) Subscribe Now

Nature of Litigation

Dispute regarding refund of amounts paid by allottees for a residential project due to non-completion.

Remedy Sought

Appellants sought to reinstate the option to refund after obtaining an occupation certificate.

Filing Reason

Allottees filed a complaint due to delays in possession delivery.

Previous Decisions

MahaRERA allowed withdrawal from the project and directed refund with interest, which was modified by the Appellate Tribunal.

Issues

Whether the obligation for the Promoter to return the amount received with interest on demand is absolute. Whether discretion exists for mitigating circumstances in refund obligations.

Submissions/Arguments

Appellants argued that the Appellate Tribunal erred in removing the option to refund after obtaining OC. Respondents contended that the right to refund is clear and unambiguous under RERA.

Ratio Decidendi

The right of the allottee to seek a refund under Section 18(1) of RERA is absolute and unqualified, and cannot be delayed by the promoter or regulatory authorities based on mitigating circumstances.

Judgment Excerpts

The right of the allottee to seek a refund under Section 18(1) of RERA is absolute and unqualified. The obligation to refund arises immediately upon demand by the allottee if the promoter fails to deliver possession as agreed.

Procedural History

The appeal was filed against the Maharashtra Real Estate Appellate Tribunal's orders modifying MahaRERA's directions regarding refunds to allottees.

Acts & Sections

  • Real Estate (Regulation and Development) Act, 2016: Section 18
  • Maharashtra Real Estate (Regulation and Development) (Registration of Real Estate Projects, Registration of Real Estate Agents, Rate of Interest and Disclosures on Website) Rules, 2017: Rule 18
Subscribe to unlock full Legal Analysis Subscribe Now
Related Judgement
Supreme Court Supreme Court Dismisses Appeals Regarding Market Fee Liability in Agricultural Produce Transactions — Clarifies Seller's Responsibility. Citing legislative intent, the court held that the seller must pay the market fee to the Market Committee regar...
Related Judgement
Supreme Court Supreme Court Upholds State Tax Legislation on Sales Tax Surcharge — Validity of Surcharge Provisions Affirmed.