Case Note & Summary
The dispute arose from a contract between the State Project Director of Rashtriya Madhyamika Shikshana Abhiyana and M/s BSR Infratech India Ltd. regarding the construction of Adarsha Vidyalayas and Girls' Hostels in Karnataka. The appellant filed a commercial appeal under Section 13(1A) of the Commercial Courts Act, 2015 and Section 37(1)(c) of the Arbitration and Conciliation Act, 1996, challenging the judgment of the learned LXXXIV Additional City Civil and Sessions Judge, Bengaluru, which dismissed the appellant's petition to set aside an arbitral award. The arbitral award, rendered on 10.11.2023, partly allowed BSR's claims, directing the appellant to pay a total of ₹2,50,28,834 along with future interest. The appellant contended that the learned Commercial Court erred in finding no grounds for interference with the arbitral award. The court analyzed the claims made by BSR, particularly focusing on claims for unproductive overhead charges and loss of expected profit. It found that the Arbitral Tribunal had insufficient evidence to support these claims, leading to the conclusion that the award was unsustainable. Consequently, the court set aside the impugned award and allowed the appeal.
Headnote
A) Arbitration - Setting Aside Arbitral Award - Grounds for Interference - Arbitration and Conciliation Act, 1996, Section 34 - The court found that the learned Arbitral Tribunal's award on claims for unproductive overhead charges and loss of expected profit lacked sufficient evidence and justification, leading to the conclusion that the award was unsustainable. Held that the impugned award was set aside due to insufficient basis for the claims (Paras 29-30).
Issue of Consideration
Whether the learned Commercial Court erred in dismissing the petition to set aside the arbitral award.
Final Decision
The appeal was allowed, and the impugned award was set aside due to insufficient evidence supporting the claims for unproductive overhead charges and loss of expected profit.
Law Points
- Arbitration
- Commercial Courts Act
- 2015
- Arbitration and Conciliation Act
- 1996
- setting aside arbitral award
- unproductive overhead charges
- loss of expected profit
- costs


