Case Note & Summary
This case arose from a petition under Section 9 of the Arbitration and Conciliation Act, 1996 filed by Limited Liability Company 'LTB', the owner and operator of 138 T-11 ISO tank containers, seeking interim measures against Shri Vaibhavi Logistics (Respondent No.1), its Indian agent, and three depot operators (Respondent Nos.2 to 4) who were in physical possession of the containers. The petitioner had appointed Respondent No.1 as its agent in India under an Agency Agreement dated 4th March 2021, which contained an arbitration clause. Two other agreements existed between the parties: a Master Tank Container Lease Agreement dated 20th November 2023 and an Agency Agreement dated 8th December 2020, each with its own arbitration clause. The petitioner restricted the present petition to reliefs under the 4th March Agreement, seeking unconditional release of all 138 tanks from the depots. According to the petition, after arriving in India, the 138 tanks were handed over to Respondent No.1 under the 4th March Agreement, and Respondent No.1 placed them with Respondent Nos.2, 3, and 4. Exhibit 'EE' listed 131 tanks with Respondent No.2, 5 with Respondent No.3, and 2 with Respondent No.4, though Respondent No.4's reply mentioned four tanks. Respondent No.1 initially stated no objection to returning the tanks but then claimed a lien over them until separate dues under other agreements were paid. Respondent No.1 also argued that the petition was not maintainable because it originally included reliefs under all three agreements and could not be cured by dropping claims. Respondent No.4 raised objections regarding territorial jurisdiction, lack of arbitration agreement, and bailee status, while Respondent No.2 admitted holding 132 tanks but claimed outstanding dues of Rs.17,23,493 and a lien under a Memorandum of Understanding dated 16th July 2026. The court framed three legal issues: (i) whether a party could exercise a cross-contractual lien without express contractual provision; (ii) whether a petitioner could withdraw part of a composite petition under Order XXIII Rule 1(3)(b) CPC and seek liberty to file separate proceedings; and (iii) whether relief could be granted against non-signatory depots in possession of the subject matter despite territorial objections. The petitioner argued that separate arbitration clauses prevented respondent no.1 from mixing claims and that withdrawal of part claim was permissible on 'sufficient grounds' as held in Sarguja Transport Service and other decisions. The respondents maintained their stands on maintainability, lien, and jurisdiction. The judgment excerpt provided does not include the court's final analysis or operative order, so the ultimate decision and ratio decidendi could not be extracted. The case was reserved on 21 August 2026 and pronounced on 27 August 2026.
Headnote
A) Arbitration - Interim Measures - Cross-Contractual Lien - Arbitration and Conciliation Act, 1996, Section 9 - The court examined whether a party could retain goods handed over under one contract to secure a claim arising under another contract without an express contractual provision allowing cross-contract recovery. The petitioner argued that respondent no.1 could not exercise a lien over 138 tank containers for dues allegedly arising under separate agreements because the three agreements had distinct arbitration clauses. The court framed the issue and heard submissions; no final determination was extracted from the available text (Paras 7-9). B) Civil Procedure - Withdrawal of Part of Claim - Code of Civil Procedure, 1908, Order XXIII Rule 1(3)(b) - The court considered whether a petitioner in a composite Section 9 petition could elect not to press reliefs under other agreements and seek liberty to pursue them separately. The petitioner relied on Sarguja Transport Service v. State Transport Appellate Tribunal, Atul Krushna Roy v. Raukishore Mohanty, and Sambanda Naicker v. Ranganayaki Ammal to contend that 'other sufficient grounds' permitted such withdrawal. The court noted the respondent's objection to maintainability but no final ruling was extracted (Paras 7-8). C) Arbitration - Territorial Jurisdiction and Non-Signatory Possession - Arbitration and Conciliation Act, 1996, Section 9; Letters Patent (Bombay), Clause XII - The court examined whether interim relief could be granted against respondent nos.2 to 4, who were not parties to the arbitration agreement but possessed the tank containers and claimed through respondent no.1, despite territorial objections raised by respondent no.4 that the containers were in Uttarakhand and no leave under Clause XII was obtained. The court framed the issue and considered the stands of the parties; no final decision was extracted (Paras 7, 5-6).
Issue of Consideration
1. Whether a party can exercise a lien or retain goods handed over under one contract to secure a claim arising under another contract absent express contractual provision permitting cross-contract recovery. 2. Whether in a composite petition containing claims under several agreements with different arbitration clauses, the petitioner can choose not to press some reliefs and seek liberty to pursue them separately under Order XXIII Rule 1(3)(b) CPC. 3. Whether the court can grant relief against respondent nos.2 to 4 who possess the subject matter and claim through respondent no.1 despite respondent nos.3 and 4 being outside territorial jurisdiction and absent direct arbitration agreements.
Law Points
- Section 9 Arbitration and Conciliation Act
- 1996 interim measures
- Order XXIII Rule 1(3)(b) CPC withdrawal of part claim with liberty
- cross-contractual lien requires express contractual provision
- party claiming through arbitration respondent may be subject to interim relief if possessing subject matter
- territorial jurisdiction under Clause XII Letters Patent



