Case Note & Summary
The present matters comprised two cross arbitration petitions filed under Section 9 of the Arbitration and Conciliation Act, 1996 before the Bombay High Court, Ordinary Original Civil Jurisdiction. The first petition, ARBPL/25010/2026, was filed by Om Vitthal Co-operative Housing Society Limited, a society registered under the Maharashtra Co-operative Societies Act, 1960, against Trilogy Infra Private Limited, the developer. The second petition, CARBPL/23586/2026, was filed by the developer against the Society. The dispute concerned a Development Agreement dated 25 November 2023 and a Power of Attorney dated 11 December 2023 for redevelopment of a property described as Final Plot No.275, Sub Plot No.30, Town Planning Scheme No.III, with building 'Vithal Apartments', Borivali (West), Mumbai. The Society had previously appointed M/s. JKD Enterprises as developer on 31 January 2015, terminated that arrangement on 23 January 2023 due to defaults, and after Court Receiver proceedings, restored possession to the Society. Thereafter, the Society conducted a tender process between 13 June 2023 and 11 December 2023 and selected the respondent developer. The Society alleged that the developer failed to obtain necessary approvals, failed to execute Permanent Alternate Accommodation Agreements, failed to pay monthly rent and rehabilitation compensation from January 2026 onwards, and did not carry out meaningful redevelopment work. After issuing a cure notice, the Society terminated the Development Agreement, Power of Attorney and all connected documents by notice dated 18 May 2026, and informed authorities and the public. The Society apprehended creation of third-party rights and filed for interim protection. The developer disputed the termination and sought stay of the termination notice and restraint against dispossession. The learned counsel for the Society argued that the developer was obligated to complete redevelopment within 18 months, with an additional grace period of 6 months, and to obtain an Occupation Certificate, referring to Clause 8.3 of the Development Agreement. The text of the judgment provided ends at paragraph 9, before the court's analysis and final order; therefore, the court's decision, reasoning, and final relief are not available in the given excerpt.
Issue of Consideration
Whether the Co-operative Housing Society is entitled to interim relief under Section 9 of the Arbitration and Conciliation Act, 1996, including a declaration that the Development Agreement stands terminated and an injunction restraining the developer from interfering with possession and redevelopment; and whether the developer is entitled to a stay of the termination notice and an injunction restraining the Society from dispossessing it.
Case Details
2026 LawText (BOM) (08) 91
ARBPL/25010/2026 with CARBPL/23586/2026
Amogh Singh, Krutisha Pandey, Nirav Karia, Bhavin Bhatia, Mutahhar Khan, Khalid Kazi, Vikrant Parshurami
Om Vitthal Co-operative Housing Society Limited (Petitioner in ARBPL/25010/2026) and Trilogy Infra Private Limited (Petitioner in CARBPL/23586/2026)
Trilogy Infra Private Limited (Respondent in ARBPL/25010/2026) and Om Vitthal Co-operative Housing Society Limited (Respondent in CARBPL/23586/2026)
Subscribe to unlock Case Details (Citation, Judge, Date & more)
Subscribe Now
Nature of Litigation
Cross arbitration petitions under Section 9 of the Arbitration and Conciliation Act, 1996 seeking interim measures in a dispute over termination of a redevelopment agreement between a co-operative housing society and a developer.
Remedy Sought
Society sought declaration that Development Agreement terminated, injunction to prevent developer from disturbing possession and interfering with right to redevelop; developer sought stay of termination notice and injunction restraining Society from acting on termination notice and from dispossessing developer.
Filing Reason
Society alleged developer breached Development Agreement by failing to obtain approvals, execute permanent alternate accommodation agreements, pay rent from January 2026, and complete redevelopment; developer disputed termination and claimed rights under the agreement.
Previous Decisions
Earlier development arrangement with M/s. JKD Enterprises terminated on 23 January 2023; consent terms executed before High Court; possession restored to Society through Court Receiver; subsequent tender process led to appointment of current developer. No prior judicial decision in these specific petitions is mentioned in the provided text.
Issues
Whether the Society is entitled to interim relief under Section 9 of the Arbitration and Conciliation Act, 1996, including a declaration that the Development Agreement stands terminated and an injunction restraining the developer from interfering with possession and redevelopment.
Whether the developer is entitled to a stay of the termination notice and an injunction restraining the Society from dispossessing the developer.
Submissions/Arguments
Society contended that developer failed to perform obligations under the Development Agreement, defaulted in payment of monthly rent and rehabilitation compensation from January 2026, did not cure breaches after cure notice, and that termination on 18 May 2026 was valid.
Developer, in its petition, sought stay of the termination notice and restraint against dispossession, thereby disputing the termination.
Learned counsel for the Society argued that developer was required to complete redevelopment within 18 months plus 6 months grace period, to obtain Occupation Certificate, and referred to Clause 8.3 of the Development Agreement.
Judgment Excerpts
Arbitration Petition (L) No.25010 of 2026 is filed by a Co-operative Housing Society against the developer.
The Society terminated the Development Agreement, Power of Attorney and all other documents connected with the development arrangement by a notice dated 18 May 2026.
Mr. Singh, learned Advocate appearing for the Petitioner Society, submitted that under the Development Agreement entered into between the Society and the developer, the developer was required to complete the redevelopment of the Society within a period of 18 months, with an additional grace period of 6 months.
Procedural History
On 31 January 2015, Society appointed M/s. JKD Enterprises as developer; terminated that arrangement on 23 January 2023; consent terms executed; possession taken through Court Receiver and restored to Society. Between 13 June 2023 and 11 December 2023, Society conducted fresh tender process and appointed Trilogy Infra Private Limited; executed Development Agreement on 25 November 2023 and Power of Attorney on 11 December 2023. Society issued cure notice calling upon developer to cure breaches; developer did not cure. Between 2 May 2026 and 18 May 2026, developer invoked arbitration and sought restraint. Society terminated development documents by notice dated 18 May 2026, informed authorities and issued public notices from 22 May 2026 onwards. Society filed ARBPL/25010/2026 under Section 9; developer filed CARBPL/23586/2026 seeking stay of termination. No final order available in provided text.
Acts & Sections
- Arbitration and Conciliation Act, 1996: Section 9
- Maharashtra Co-operative Societies Act, 1960: