High Court Closes Contempt Petition Against Power Corporation Officials After Undertaking to Pay Amount Due. Contempt petition filed for disobedience of court order dated 13.12.2023 was closed upon recording that the Board had sanctioned payment and would credit the amount by the next day.

High Court: Madras High Court Bench: Principal
  • 6
Judgement Image
Font size:
Print

Case Note & Summary

The contempt petition was filed by M/s. OM Textiles against three officials of TANGEDCO alleging disobedience of the order dated 13.12.2023 in W.P.No. 34473 of 2023. The petitioner had obtained an order in a writ petition, and the respondents failed to comply, leading to the contempt petition. At the hearing, the respondents' counsel stated that the Board had sanctioned payment on 25.02.2025 and that the amount would be credited to the petitioner's bank account by the end of business on 06.03.2025. The court recorded this undertaking and closed the contempt petition. No costs were awarded. No legal issues were discussed; the matter was resolved by the undertaking. The decision effectively put an end to the contempt proceedings without a finding of contempt.

Headnote

A) Contempt of Court - Disobedience of Order - Compliance Undertaking - Contempt of Courts Act, 1971, Section Not mentioned - The contempt petition was filed alleging disobedience of the order dated 13.12.2023 in W.P.No. 34473 of 2023. Respondents' counsel stated that the Board had sanctioned payment on 25.02.2025 and the amount would be credited by 06.03.2025. The court recorded this undertaking and closed the contempt petition without costs. (Paras 1-2)

Subscribe to unlock Headnote Subscribe Now

Issue of Consideration

CONT P No. 3768 of 2024

Subscribe to unlock Issue of Consideration Subscribe Now

Final Decision

Contempt petition closed. No costs.

Case Details

2025 LawText (MAD) (03) 12

CONT P No. 3768 of 2024

2025-03-05

Dr. Justice Anita Sumanth

2025:MHC:624

M/s. M.Saravanakumar for petitioner; Mr. D.R.Arun Kumar for respondents

M/s. OM Textiles

1. Thiru. Rajeshlakhoni, I.A.S., Chairman, Tamil Nadu Generation And Distribution Corporation Limited; 2. R.K.Vinothan, Chief Engineer, Non Conventional Energy Sources, Tamil Nadu Generation And Distribution Corporation Limited; 3. D.Rajendran, Director Generation, Tangedco

Subscribe to unlock Case Details (Citation, Judge, Date & more) Subscribe Now

Nature of Litigation

Contempt petition for disobedience of court order dated 13.12.2023 in W.P.No. 34473 of 2023

Remedy Sought

Punishment of respondents for contempt of court

Filing Reason

Disobedience of the order of this Honble Court dated 13.12.2023

Previous Decisions

Order dated 13.12.2023 in W.P.No. 34473 of 2023

Submissions/Arguments

The respondents' counsel stated that sanction had been accorded by the Board on 25.02.2025 and the amount in question would be credited to the petitioner's bank account by end of business on 06.03.2025.

Judgment Excerpts

sanction has been accorded by the Board on 25.02.2025 and the amount in question would be credited to the bank account of petitioner, positively by end of business tomorrow i.e. 06.03.2025 This is recorded. Recording the same, this contempt petition is closed. No costs.

Procedural History

The petitioner filed W.P.No. 34473 of 2023, which was allowed on 13.12.2023. Alleging disobedience, the present contempt petition was filed. The court recorded the undertaking and closed the petition on 05.03.2025.

Acts & Sections

  • Contempt of Courts Act, 1971:
Subscribe to unlock full Legal Analysis Subscribe Now
Related Judgement
High Court High Court Closes Contempt Petition Against Power Corporation Officials After Undertaking to Pay Amount Due. Contempt petition filed for disobedience of court order dated 13.12.2023 was closed upon recording that the Board had sanctioned payment and ...
Related Judgement
High Court Bombay High Court Quashes Criminal Proceedings in Central Excise Case Due to Inordinate Delay and Lack of Sanction. Prosecution for Alleged Removal of Scrap Resistors Without Payment of Duty Fails as Complaint Filed After 4 Years and Sanction Under S...