Bombay High Court Quashes Deficit Stamp Duty Demand Against Housing Society Due to Limitation Under Section 53A of Maharashtra Stamp Act. Demand raised beyond six-year period from Amnesty certificate under Section 41 is barred by time, and even otherwise, a 20-year delay is unreasonable.

High Court: Bombay High Court In Favour of Accused
  • 683
Judgement Image
Font size:
Print

Case Note & Summary

The Petitioner, Uma Niwas Co-Operative Housing Society Ltd., a society registered under the Maharashtra Co-operative Societies Act, 1960, filed a writ petition under Article 226 of the Constitution of India challenging orders dated 2 May 2016 and 16 July 2016 passed by Respondent Nos.1 and 2 (Collector of Stamps and Deputy Inspector General of Registration). The orders demanded deficit stamp duty with respect to Flat Nos.218 and 320 in the society, which affected the society's right to obtain deemed conveyance. The society had been granted deemed conveyance on 11 February 2014, but the Registrar required determination of stamp duty on the deemed conveyance deed. The Collector passed an interim order on 28 September 2015 and a final order on 2 May 2016, calculating deficit stamp duty for Flat No.218 at Rs.25,150/- and for Flat No.320 at Rs.1,90,040/-. The society's appeal against the interim order was dismissed by Respondent No.2 on 16 July 2016 on the ground that the issue was not within the scope of Section 32B of the Bombay Stamp Act. The society then approached the High Court. The main issue was whether the demand for deficit stamp duty for Flat No.320 was barred by limitation. The document for Flat No.320 was from 1989 and was covered under an Amnesty Scheme; full stamp duty of Rs.7,060/- was paid in 1995, and a certificate under Section 41 of the Bombay Stamp Act was issued on 2 March 1995, subject to Section 53A. Section 53A allows revision of the Collector's decision under Section 41 within six years from the date of the certificate. The demand was raised in 2015 (interim) and 2016 (final), well beyond the six-year period which expired on 1 March 2001. The court held that the demand was barred by limitation and quashed the orders regarding Flat No.320. The court also noted that the proviso to Article 25(1)(b) relied upon by the respondents was not applicable. The petition was partly allowed, with the demand for Flat No.218 not pressed as the amount was small and already paid.

Headnote

A) Stamp Duty - Limitation - Deficit Stamp Duty Demand - Section 53A of Bombay Stamp Act, 1958 - The court considered whether a demand for deficit stamp duty raised in 2015/2016 was barred by limitation where a certificate under Section 41 had been issued in 1995 subject to Section 53A. Held that Section 53A provides a six-year period from the date of the certificate for revision, and the demand beyond that period is barred (Paras 11-13).

B) Stamp Duty - Amnesty Scheme - Certificate under Section 41 - Section 41 and Section 53A of Bombay Stamp Act, 1958 - The court examined the effect of a certificate issued under Section 41 stating full stamp duty paid subject to Section 53A. Held that the certificate is conclusive as to payment but subject to revision within six years under Section 53A (Paras 7-8, 11-13).

C) Stamp Duty - Reasonable Period - Demand after 20 years - Bombay Stamp Act, 1958 - The court observed that even if Section 53A were not applicable, raising a demand after 20 years (1995 to 2015) is not a reasonable period under the scheme of the Act (Para 16).

Subscribe to unlock Headnote Subscribe Now

Issue of Consideration

Whether the demand for deficit stamp duty raised in 2015/2016 with respect to a 1989 agreement that was the subject of an Amnesty Scheme and for which a certificate under Section 41 was issued in 1995 is barred by limitation under Section 53A of the Bombay Stamp Act, 1958.

Subscribe to unlock Issue of Consideration Subscribe Now

Final Decision

The petition is partly allowed. The impugned orders dated 28 September 2015 and 2 May 2016, insofar as they relate to demand of deficit stamp duty for Flat No.320, are quashed and set aside. The demand for Flat No.218 is not pressed and is not adjudicated.

Law Points

  • Limitation for raising deficit stamp duty demand under Section 53A of Bombay Stamp Act is six years from date of certificate under Section 41
  • Amnesty Scheme certificate subject to Section 53A
  • Demand beyond six years is barred by limitation
  • Reasonable period for raising demand under Stamp Act cannot exceed 20 years.
Subscribe to unlock Law Points Subscribe Now

Case Details

2024 LawText (BOM) (10) 33

WRIT PETITION NO.10602 OF 2016

2024-10-03

Jitendra Jain

K. S. Dewal, Sham Thakur for Petitioner; Kavita N. Solunke, AGP for Respondent Nos.1 and 2; Sulajja Patil for Respondent Nos.3 and 4

Uma Niwas Co-Operative Housing Society Ltd.

The Collector of Stamps, Thane; Deputy Inspector General of Registration and Deputy Stamp Controller, Konkan Division, Thane; Sharli Jayvant Vaishampayan; Uday Kale

Subscribe to unlock Case Details (Citation, Judge, Date & more) Subscribe Now

Nature of Litigation

Writ petition under Article 226 challenging orders demanding deficit stamp duty on flats in a co-operative housing society, affecting deemed conveyance.

Remedy Sought

Quashing of orders dated 2 May 2016 and 16 July 2016 demanding deficit stamp duty.

Filing Reason

The Collector of Stamps raised demand for deficit stamp duty on Flat Nos.218 and 320, which the society contended was barred by limitation under Section 53A of the Bombay Stamp Act.

Previous Decisions

Competent Authority allowed deemed conveyance on 11 February 2014; Collector passed interim order on 28 September 2015 and final order on 2 May 2016; appeal dismissed by Deputy Inspector General on 16 July 2016.

Issues

Whether the demand for deficit stamp duty for Flat No.320 is barred by limitation under Section 53A of the Bombay Stamp Act, 1958. Whether the proviso to Article 25(1)(b) of the Maharashtra Stamp Act applies to the facts of the case.

Submissions/Arguments

Petitioner argued that the certificate under Section 41 dated 2 March 1995 was subject to Section 53A, which provides a six-year limitation period; demand raised in 2015/2016 is beyond that period and thus barred. Respondent Nos.1 and 2 argued that since the 1989 agreement was not registered, the authorities were justified in taking the value prevailing in 2015/2016; also relied on proviso to Article 25(1)(b) to support the demand.

Ratio Decidendi

Under Section 53A of the Bombay Stamp Act, 1958, the Chief Controlling Revenue Authority may revise the Collector's decision under Section 41 within a period of six years from the date of the certificate. In this case, the certificate was issued on 2 March 1995, and the demand was raised in 2015/2016, beyond the six-year period. Therefore, the demand is barred by limitation. Even if Section 53A were not applicable, a demand after 20 years is not a reasonable period.

Judgment Excerpts

Section 53A empowers revision of Collector’s decision under Section 41 within a period of 6 years from the date of certificate of the Collector under Section 41 for raising the demand on account of deficit stamp. In the instant case, the certificate issued under Section 41 is dated 2nd March 1995 and the period of 6 years had expired on 1st March 2001. The impugned order raising the demand (interim) is dated 2nd July 2015 and (final) is dated 2nd May 2016. Both these communications of 2015 and 2016 would be beyond the year 2001 and, therefore, on this count itself the orders ... are required to be quashed and set aside.

Procedural History

On 11 February 2014, Competent Authority allowed deemed conveyance. Petitioner approached Collector for stamp duty determination. Collector passed interim order on 28 September 2015 and final order on 2 May 2016. Appeal against interim order was dismissed by Deputy Inspector General on 16 July 2016. Petitioner then filed writ petition on 2 November 2016. Judgment delivered on 3 October 2024.

Acts & Sections

  • Bombay Stamp Act, 1958 (now Maharashtra Stamp Act): Section 32B, Section 41, Section 53A, Article 25(1)(b)
  • Maharashtra Co-operative Societies Act, 1960:
  • Constitution of India: Article 226
Subscribe to unlock full Legal Analysis Subscribe Now
Related Judgement
High Court Bombay High Court Allows Assistant Professor's Challenge to Superannuation at Age 60, Holds AICTE Retirement Age of 65 Applicable to Private Self-Finance Standalone Institution. Goa Institute of Management's Faculty Manual Fixing Retirement Age at 60...
Related Judgement
Supreme Court Supreme Court Directs Investigation and Management of Shri Jagannath Temple, Puri — Ratna Bhandar Keys Disappearance and Pilgrim Facilities Addressed. Court Orders Reports from District Judge, State, and Central Governments, and Appoints Amicus Cur...