Bombay High Court Dismisses Developer's Section 9 Petition as Misuse of Process in Redevelopment Dispute with Non-Member Occupant. Court holds that a developer cannot seek interim relief against a non-signatory occupant under Section 9 of the Arbitration and Conciliation Act, 1996, where the occupant has independent rights and is not bound by the arbitration agreement.

High Court: Bombay High Court In Favour of Accused
  • 796
Judgement Image
Font size:
Print

Case Note & Summary

The petitioner, Gulshan Townplanners LLP, a developer, filed a petition under Section 9 of the Arbitration and Conciliation Act, 1996 seeking interim relief against the respondent, Baiju Mahendra Doshi, who was an occupant of three flats in the B-Wing of a building owned by the Gulshan Co-operative Housing Society Limited. The petitioner had entered into a Redevelopment Agreement (RDA) and a Supplementary Agreement (SA) with the society for redevelopment of the entire property. However, the respondent was not a member of the society and had not signed the RDA or SA. The respondent claimed independent ownership of the three flats in B-Wing and the land beneath them, based on sale agreements from 1993. The society had obtained a deemed conveyance of the entire land in 2020, which the respondent challenged in a pending writ petition. The petitioner sought reliefs including a direction to the respondent to vacate the flats and hand over possession, and an injunction restraining the respondent from interfering with redevelopment. The court examined the facts and found that the respondent was not a party to the arbitration agreement contained in the RDA. The court held that Section 9 of the Arbitration Act cannot be used to seek relief against a third party who is not bound by the arbitration agreement. The court noted that the respondent had independent rights and was contesting the society's ownership. The court also observed that the petitioner had other remedies available, such as filing a suit or seeking relief in the pending writ petition. The court dismissed the petition, holding that it was a misuse of the provisions of Section 9. The court did not award costs but made it clear that the petition was an abuse of process.

Headnote

A) Arbitration Law - Section 9 of the Arbitration and Conciliation Act, 1996 - Maintainability against third party - The court held that a petition under Section 9 is not maintainable against a respondent who is not a party to the arbitration agreement and who claims independent rights over the property. The court found that the petitioner's attempt to seek relief against the non-member occupant was a misuse of the provisions of Section 9. (Paras 1, 10-12)

B) Arbitration Law - Interim Relief - Scope of Section 9 - The court clarified that Section 9 is intended to protect the subject matter of the arbitration agreement and cannot be used to obtain relief against a person who is not bound by the arbitration agreement. The court emphasized that the existence of a valid arbitration agreement between the parties is a prerequisite for granting relief under Section 9. (Paras 10-12)

C) Property Law - Redevelopment - Rights of non-member occupant - The court noted that the respondent, who was not a member of the society and had not signed the redevelopment agreement, had independent rights over the B-Wing flats and the land beneath them. The court held that such a person cannot be compelled to participate in redevelopment through a Section 9 petition. (Paras 2, 4-7, 10-12)

Subscribe to unlock Headnote Subscribe Now

Issue of Consideration

Whether a petition under Section 9 of the Arbitration and Conciliation Act, 1996 is maintainable against a respondent who is not a party to the arbitration agreement and who claims independent rights over the property, and whether the court can grant interim relief against such a third party.

Subscribe to unlock Issue of Consideration Subscribe Now

Final Decision

The court dismissed the petition, holding that it is not maintainable against Respondent No.2 as he is not a party to the arbitration agreement. The court found that the petition was a misuse of the provisions of Section 9 of the Arbitration and Conciliation Act, 1996. No order as to costs.

Law Points

  • Section 9 of the Arbitration and Conciliation Act
  • 1996 cannot be used to seek relief against a third party who is not a party to the arbitration agreement
  • especially when the third party has independent rights and the dispute is not arbitrable against them
  • Interim relief under Section 9 is meant to protect the subject matter of the arbitration agreement and cannot be used to circumvent legal proceedings or coerce a non-party
  • A developer cannot use Section 9 to obtain possession or injunctive relief against an occupant who is not a member of the society and has not signed the redevelopment agreement
  • The court must examine the existence of a valid arbitration agreement between the parties before granting relief under Section 9
  • and if the respondent is not a party to the agreement
  • no relief can be granted.
Subscribe to unlock Law Points Subscribe Now

Case Details

2024 LawText (BOM) (09) 2729

Commercial Arbitration Petition (L) No.34078 of 2023

2024-09-30

Arif S. Doctor, J.

2024:BHC-OS:14977

Mr. Shanay Shah a/w Smit K. Nagda for the Petitioner, Mr. Mayur Khandeparkar a/w Pankaj S. Pandey for Respondent No.1 (Society), Mr. Simil Purohit, Senior Advocate a/w Arshil Shah i/by Parisha Shah a/w Smita Durve, Rasesh Shah, Tanmay Gujarathi, Vishal Pattabiraman and Rutwij Bapat for Respondent No.2

Gulshan Townplanners LLP

Gulshan Co-operative Housing Society Limited and Baiju Mahendra Doshi

Subscribe to unlock Case Details (Citation, Judge, Date & more) Subscribe Now

Nature of Litigation

Petition under Section 9 of the Arbitration and Conciliation Act, 1996 seeking interim relief in relation to a redevelopment agreement.

Remedy Sought

The petitioner sought a direction to Respondent No.2 to vacate the three flats in B-Wing and hand over possession, and an injunction restraining Respondent No.2 from interfering with the redevelopment.

Filing Reason

The petitioner claimed that Respondent No.2 was obstructing the redevelopment of the property despite the society having entered into a redevelopment agreement with the petitioner.

Previous Decisions

The Competent Authority granted a deemed conveyance in favour of the Society on 7th September 2020, which was challenged by Respondent No.2 in a pending writ petition. No interim order was passed in that petition.

Issues

Whether a petition under Section 9 of the Arbitration and Conciliation Act, 1996 is maintainable against a respondent who is not a party to the arbitration agreement? Whether the court can grant interim relief under Section 9 against a third party who claims independent rights over the property?

Submissions/Arguments

Petitioner argued that the Society is the rightful owner of the entire property due to the deemed conveyance, and that Respondent No.2, being a non-member, cannot obstruct redevelopment approved by the majority. Petitioner relied on judgments allowing Section 9 relief against third parties. Respondent No.2 argued that he is not a party to the arbitration agreement, has independent ownership rights over the B-Wing flats, and that the petition is an abuse of process. He contended that the petitioner has no arbitrable dispute against him.

Ratio Decidendi

A petition under Section 9 of the Arbitration and Conciliation Act, 1996 is not maintainable against a person who is not a party to the arbitration agreement. The court cannot grant interim relief against a third party who claims independent rights over the property and is not bound by the arbitration agreement. The existence of a valid arbitration agreement between the parties is a prerequisite for granting relief under Section 9.

Judgment Excerpts

While at first blush the captioned Petition would appear to be the usual Petition filed under Section 9 of the Arbitration & Conciliation Act, 1996... the facts of the present case would make plain that it is infact anything but so. Infact, in my view, as the facts of the present case would make clear, the present Petition is nothing but a sheer attempt to misuse of the provisions of Section 9 of the Arbitration Act. Admittedly, Respondent No. 2 is neither a member of the Society nor has Respondent No. 2 signed the RDA.

Procedural History

The petitioner filed a petition under Section 9 of the Arbitration and Conciliation Act, 1996 on an unspecified date. The court reserved judgment on 10th September 2024 and pronounced it on 30th September 2024.

Acts & Sections

  • Arbitration and Conciliation Act, 1996: Section 9
  • Maharashtra Cooperative Societies Act, 1960:
  • Limited Liability Partnership Act, 2007:
Subscribe to unlock full Legal Analysis Subscribe Now
Related Judgement
High Court Bombay High Court Dismisses Developer's Section 9 Petition as Misuse of Process in Redevelopment Dispute with Non-Member Occupant. Court holds that a developer cannot seek interim relief against a non-signatory occupant under Section 9 of the Arbitra...
Related Judgement
High Court High Court of Karnataka Allows Withdrawal of Petition Challenging Circular on School Reopening Guidelines. Petitioners sought mandamus against framing of guidelines under impugned circular dated 11.6.2020, but withdrew the petition at preliminary hea...