Bombay High Court Allows Appeal in Arbitration Dispute, Restoring Arbitral Award in Favor of Contractor. The Court held that payment accepted under protest does not amount to accord and satisfaction, and an exclusion clause cannot bar claims for damages caused by the employer's own breach under the Arbitration and Conciliation Act, 1996.

High Court: Bombay High Court Bench: BOMBAY In Favour of Accused
  • 14
Judgement Image
Font size:
Print

Case Note & Summary

The case arises from a construction contract between Vilayati Ram Mittal (P) Ltd. (the claimant/appellant) and the Reserve Bank of India (RBI/respondent) for building quarters and a community hall at Kharghar, Navi Mumbai. The contract was signed on 14 September 1993, with a completion period of 18 months. Disputes arose regarding delays and extra work, leading the claimant to invoke arbitration. The arbitrator passed an award in favor of the claimant for certain amounts. RBI challenged the award under Section 34 of the Arbitration and Conciliation Act, 1996 before a Single Judge of the Bombay High Court, who set aside the award on two grounds: (1) that there was accord and satisfaction as the claimant had accepted payment towards full and final settlement, and (2) that Clause 18 of the Agreement barred any claim for damages. The claimant appealed. The Division Bench reversed the Single Judge's order, holding that the acceptance of payment under protest did not constitute accord and satisfaction, and that Clause 18 could not be invoked to deny damages caused by the employer's own breach. The Court emphasized the limited scope of interference with arbitral awards under Section 34 and restored the award.

Headnote

A) Arbitration - Accord and Satisfaction - Payment under protest - The issue was whether acceptance of a payment under protest amounts to accord and satisfaction. The Court held that where a party accepts payment under protest or without prejudice, it does not constitute a full and final settlement of the claim. The arbitrator's finding that there was no accord and satisfaction was plausible and not perverse. (Paras 10-15)

B) Contract Law - Exclusion Clause - Clause 18 of Agreement - The issue was whether Clause 18, which disentitles the contractor from claiming compensation for loss suffered, bars claims for damages caused by the employer's breach. The Court held that such a clause cannot be interpreted to exclude liability for the employer's own breach, as it would be against public policy and the principle that a party cannot take advantage of its own wrong. (Paras 16-20)

C) Arbitration - Scope of Interference - Section 34 of the Arbitration and Conciliation Act, 1996 - The issue was the extent to which a court can interfere with an arbitral award. The Court held that interference is limited to grounds specified in Section 34, and the court cannot reappreciate evidence or substitute its own view if the arbitrator's view is plausible. (Paras 21-25)

Subscribe to unlock Headnote Subscribe Now

Issue of Consideration

Whether the learned Single Judge was justified in setting aside the arbitral award on the grounds of accord and satisfaction and the applicability of Clause 18 of the Agreement to bar the claim for damages.

Subscribe to unlock Issue of Consideration Subscribe Now

Final Decision

The appeal is allowed. The judgment of the learned Single Judge dated 30th August, 2004 is set aside. The arbitral award is restored.

Law Points

  • Accord and satisfaction requires clear and unequivocal acceptance of payment in full settlement
  • Payment under protest does not constitute accord and satisfaction
  • Clause 18 of a contract cannot be invoked to deny damages caused by the employer's own breach
  • Arbitral award can be set aside only on grounds under Section 34 of the Arbitration and Conciliation Act
  • 1996
  • Interference with arbitral award is limited when the view of the arbitrator is plausible
Subscribe to unlock Law Points Subscribe Now

Case Details

2017:BHC-OS:12039-DB

Arbitration Appeal No. 125 of 2005 in Arbitration Petition No. 28 of 2003

2017-09-20

Naresh H. Patil, Smt. Bharati H. Dangre

2017:BHC-OS:12039-DB

Mr. Sarosh Bharucha a/with N.C. Parekh and Sunil Vyas i/by Mansukhlal Hiralal & Co. for the Appellant, Mr. Phiroz Palkhiwala a/with Debojit Banerjee i/by Udwadia & Udeshi for the Respondent

Vilayati Ram Mittal (P) Ltd.

Reserve Bank of India

Subscribe to unlock Case Details (Citation, Judge, Date & more) Subscribe Now

Nature of Litigation

Appeal against order of Single Judge setting aside arbitral award in a construction contract dispute.

Remedy Sought

The appellant sought restoration of the arbitral award in its favor.

Filing Reason

The Single Judge set aside the arbitral award on grounds of accord and satisfaction and Clause 18 of the Agreement barring damages.

Previous Decisions

The learned Single Judge set aside the arbitral award dated 30th August, 2004.

Issues

Whether acceptance of payment under protest constitutes accord and satisfaction. Whether Clause 18 of the Agreement bars the claim for damages caused by the employer's breach. Whether the Single Judge exceeded the scope of interference under Section 34 of the Arbitration and Conciliation Act, 1996.

Submissions/Arguments

Appellant argued that payment was accepted under protest and there was no accord and satisfaction. Appellant argued that Clause 18 cannot be invoked to deny damages caused by the employer's own breach. Respondent argued that the claimant accepted payment in full and final settlement and Clause 18 bars any claim for compensation.

Ratio Decidendi

Acceptance of payment under protest does not constitute accord and satisfaction. An exclusion clause in a contract cannot be interpreted to bar claims for damages caused by the employer's own breach. The court's interference with an arbitral award under Section 34 of the Arbitration and Conciliation Act, 1996 is limited and cannot substitute its own view if the arbitrator's view is plausible.

Judgment Excerpts

The present appeal challenges the judgment dated 30th August, 2004 delivered by the learned Single Judge thereby setting aside the Award mainly on two counts, namely that there was accord and satisfaction in between the parties as the amount was accepted towards full and final settlement by the claimant without any demur and secondly rejecting the claim for no damages in view of Clause 18 of the Agreement between the parties which dis-entitle the contractor from claiming any compensation for any loss suffered. The Court held that acceptance of payment under protest does not constitute accord and satisfaction.

Procedural History

The claimant filed a claim before the arbitrator, who passed an award in its favor. RBI challenged the award under Section 34 of the Arbitration and Conciliation Act, 1996 before a Single Judge of the Bombay High Court, who set aside the award. The claimant appealed to the Division Bench, which allowed the appeal and restored the award.

Acts & Sections

  • Arbitration and Conciliation Act, 1996: Section 34
  • Reserve Bank of India Act, 1934:
Subscribe to unlock full Legal Analysis Subscribe Now
Related Judgement
High Court Bombay High Court Upholds Conviction for Rape of Five-Year-Old Girl Motivated by Political Vendetta — Life Imprisonment Maintained Under Section 376 IPC. The court held that the sole testimony of a child victim, if credible, can form the basis of c...
Related Judgement
High Court Bombay High Court Allows Petitioner in Employees' Provident Funds Act Coverage Dispute — Expert Services Notification Interpreted Narrowly. Software Consultancy Services Not Covered Under Notification Dated 17th May 1971 Issued Under Section 1(3)(b...