Case Note & Summary
The petitioner, B.E. Billimoria & Company Limited, filed a petition under Section 9 of the Arbitration and Conciliation Act, 1996 seeking an injunction against the respondents, Mahindra Bebanco Developers Ltd. and Mahindra Lifespace Developers Ltd., from taking steps pursuant to letters dated 5th January 2017 and 13th January 2017 and from breaching a development agreement dated 28th September 2011. The petitioner also sought status quo with respect to the agreement and an injunction against the second respondent from creating third party rights or allotting contracts for construction on the site. The dispute arose out of a development agreement where the petitioner was to develop a property. The respondents issued termination letters alleging breach of the agreement by the petitioner. The petitioner contended that the termination was wrongful and that the disputes were arbitrable. The court examined the terms of the agreement and the correspondence between the parties. It held that the disputes were indeed arbitrable and that the petitioner had an adequate remedy under the arbitration clause. The court found that the petitioner failed to establish a prima facie case for grant of interim relief, as the agreement itself provided for termination upon breach. The balance of convenience was not in favor of the petitioner, and no irreparable loss was shown. The court dismissed the petition, leaving the parties to pursue arbitration.
Headnote
A) Arbitration - Interim Measures - Section 9 of the Arbitration and Conciliation Act, 1996 - Injunction against termination of agreement - The petitioner sought to restrain the respondent from terminating a development agreement and from creating third party rights. The court held that the disputes were arbitrable and that the petitioner failed to make out a prima facie case for grant of interim relief as the agreement itself provided for termination and the petitioner had an adequate remedy under the arbitration clause. (Paras 1-10) B) Contract Law - Termination of Agreement - Breach of Contract - The court examined the terms of the development agreement and found that the respondent had the right to terminate the agreement upon breach. The petitioner's allegations of breach were disputed and required evidence, which could not be decided in a Section 9 proceeding. (Paras 11-20) C) Specific Performance - Injunction - The court held that an injunction to prevent termination of a contract is in the nature of specific performance, which is a discretionary remedy. The petitioner did not demonstrate that damages would be an inadequate remedy. (Paras 21-25)
Issue of Consideration
Whether the petitioner is entitled to an interim injunction under Section 9 of the Arbitration and Conciliation Act, 1996 restraining the respondents from terminating the development agreement and from creating third party rights pending arbitration.
Final Decision
The petition is dismissed. The parties are left to pursue their remedies in arbitration.
Law Points
- Section 9 of the Arbitration and Conciliation Act
- 1996
- interim measures
- prima facie case
- balance of convenience
- irreparable loss
- termination of contract
- arbitrability of disputes
- specific performance
- injunction against termination



