Bombay High Court Dismisses Section 9 Petition for Injunction in Arbitration Dispute Over Development Agreement. Court holds that disputes regarding termination of a development agreement are arbitrable and that interim relief under Section 9 cannot be granted when the agreement itself provides for termination and the petitioner has an adequate remedy under the arbitration clause.

High Court: Bombay High Court Bench: BOMBAY
  • 170
Judgement Image
Font size:
Print

Case Note & Summary

The petitioner, B.E. Billimoria & Company Limited, filed a petition under Section 9 of the Arbitration and Conciliation Act, 1996 seeking an injunction against the respondents, Mahindra Bebanco Developers Ltd. and Mahindra Lifespace Developers Ltd., from taking steps pursuant to letters dated 5th January 2017 and 13th January 2017 and from breaching a development agreement dated 28th September 2011. The petitioner also sought status quo with respect to the agreement and an injunction against the second respondent from creating third party rights or allotting contracts for construction on the site. The dispute arose out of a development agreement where the petitioner was to develop a property. The respondents issued termination letters alleging breach of the agreement by the petitioner. The petitioner contended that the termination was wrongful and that the disputes were arbitrable. The court examined the terms of the agreement and the correspondence between the parties. It held that the disputes were indeed arbitrable and that the petitioner had an adequate remedy under the arbitration clause. The court found that the petitioner failed to establish a prima facie case for grant of interim relief, as the agreement itself provided for termination upon breach. The balance of convenience was not in favor of the petitioner, and no irreparable loss was shown. The court dismissed the petition, leaving the parties to pursue arbitration.

Headnote

A) Arbitration - Interim Measures - Section 9 of the Arbitration and Conciliation Act, 1996 - Injunction against termination of agreement - The petitioner sought to restrain the respondent from terminating a development agreement and from creating third party rights. The court held that the disputes were arbitrable and that the petitioner failed to make out a prima facie case for grant of interim relief as the agreement itself provided for termination and the petitioner had an adequate remedy under the arbitration clause. (Paras 1-10)

B) Contract Law - Termination of Agreement - Breach of Contract - The court examined the terms of the development agreement and found that the respondent had the right to terminate the agreement upon breach. The petitioner's allegations of breach were disputed and required evidence, which could not be decided in a Section 9 proceeding. (Paras 11-20)

C) Specific Performance - Injunction - The court held that an injunction to prevent termination of a contract is in the nature of specific performance, which is a discretionary remedy. The petitioner did not demonstrate that damages would be an inadequate remedy. (Paras 21-25)

Subscribe to unlock Headnote Subscribe Now

Issue of Consideration

Whether the petitioner is entitled to an interim injunction under Section 9 of the Arbitration and Conciliation Act, 1996 restraining the respondents from terminating the development agreement and from creating third party rights pending arbitration.

Subscribe to unlock Issue of Consideration Subscribe Now

Final Decision

The petition is dismissed. The parties are left to pursue their remedies in arbitration.

Law Points

  • Section 9 of the Arbitration and Conciliation Act
  • 1996
  • interim measures
  • prima facie case
  • balance of convenience
  • irreparable loss
  • termination of contract
  • arbitrability of disputes
  • specific performance
  • injunction against termination
Subscribe to unlock Law Points Subscribe Now

Case Details

2017 LawText (BOM) (05) 21

Commercial Arbitration Petition (LDG.) No.29 of 2017

2017-05-02

R.D. Dhanuka, J.

Mr. Janak Dwarkadas, Senior Counsel with Mr. Zal Andhyarujina, Mr. Kunal Dwarkadas, Mr. Amit Vyas and Mr. Rohan Mathur i/b Vertices Partners for the Petitioner. Mr. Pravin Samdhani, Senior Counsel with Ms. Disha Kunder i/b Lodha Legal for the Respondent No.1. Mr. Simil Purohit with Mr. Dhaval Mehta, Mr. Manish Vora, Mr. Swapnil Khatri and Mr. Akash Lodha i/b Wadia Ghandy & Co. for the Respondent No.2.

B.E. Billimoria & Company Limited

Mahindra Bebanco Developers Ltd. and Mahindra Lifespace Developers Ltd.

Subscribe to unlock Case Details (Citation, Judge, Date & more) Subscribe Now

Nature of Litigation

Commercial arbitration petition under Section 9 of the Arbitration and Conciliation Act, 1996 seeking interim relief pending arbitration.

Remedy Sought

Injunction against respondent no.1 from taking steps pursuant to termination letters dated 5th January 2017 and 13th January 2017, status quo with respect to the agreement dated 28th September 2011, and injunction against respondent no.2 from creating third party rights or allotting contracts on the site.

Filing Reason

Alleged wrongful termination of a development agreement by the respondents.

Issues

Whether the petitioner is entitled to an interim injunction under Section 9 of the Arbitration and Conciliation Act, 1996 restraining the respondents from terminating the development agreement and from creating third party rights pending arbitration.

Submissions/Arguments

Petitioner argued that the termination was wrongful and that the disputes were arbitrable, and sought interim protection to preserve the subject matter of the arbitration. Respondents contended that the petitioner had breached the agreement and that the termination was valid, and that the petitioner had an adequate remedy under the arbitration clause.

Ratio Decidendi

In a Section 9 petition, the court must consider whether the petitioner has made out a prima facie case, balance of convenience, and irreparable loss. Where the agreement itself provides for termination upon breach and the petitioner has an adequate remedy under the arbitration clause, interim relief cannot be granted.

Judgment Excerpts

By this petition filed under section 9 of the Arbitration & Conciliation Act, 1996, the petitioner seeks an injunction against the respondent no.1 from taking any steps pursuant to their letters dated 5th January, 2017 and 13th January, 2017 and from in any manner breaching the agreement dated 28th September, 2011.

Procedural History

The petition was filed under Section 9 of the Arbitration and Conciliation Act, 1996. It was reserved on 19th April 2017 and pronounced on 2nd May 2017.

Acts & Sections

  • Arbitration and Conciliation Act, 1996: Section 9
Subscribe to unlock full Legal Analysis Subscribe Now
Related Judgement
High Court Gujarat High Court Allows Revision Application in NI Act Case Following Amicable Settlement Between Parties. Conviction under Section 138 of Negotiable Instruments Act, 1881 quashed as complainant accepted reduced settlement amount and had no objecti...
Related Judgement
High Court Bombay High Court Sets Aside Competent Authority's Apportionment Order in National Highways Act Compensation Dispute Due to Lack of Jurisdiction. Competent Authority Failed to Refer Rival Claimants' Apportionment Dispute to Principal Civil Court Unde...