Case Note & Summary
The judgment concerns two writ petitions filed by M/s. Gowardhan Infrastructure Pvt. Ltd. and M/s. Vedbhoomi Builders & Developers Pvt. Ltd. against the State of Maharashtra, the Municipal Commissioner of Nagpur Municipal Corporation (NMC), the Assistant Director of Town Planning, and the NMC itself. The petitioners had submitted building proposals for construction on their respective plots. The NMC failed to communicate any refusal or objections within the prescribed period under Section 45(4) of the Maharashtra Regional and Town Planning Act, 1966 (MRTP Act). Consequently, the petitioners claimed that their proposals were deemed sanctioned. However, the NMC subsequently refused to sanction the plans, citing non-compliance with Development Control Regulations (DCR) and the requirement of a No Objection Certificate (NOC) from the Airport Authority of India. The petitioners challenged these refusals. The court framed the issue of whether the NMC could refuse sanction after the expiry of the statutory period. The petitioners argued that under Section 45(4), if the authority does not communicate its decision within the prescribed time, the permission is deemed to have been granted. They relied on the principle that the authority cannot later raise objections. The respondents contended that the proposals were not in conformity with the DCR and that the NOC was mandatory. The court analyzed Section 45 of the MRTP Act and held that the provision is clear: if the authority fails to communicate its refusal within the period specified, the permission is deemed to have been granted. The court noted that the NMC had not communicated any refusal within the prescribed period, and therefore, the proposals were deemed sanctioned. The court further held that the requirement of an NOC from the Airport Authority was not a condition precedent under the DCR for sanction of building plans. The court allowed both writ petitions, quashing the NMC's refusal letters and directing the NMC to treat the building proposals as deemed sanctioned. The court also directed the NMC to issue the necessary commencement certificates within four weeks.
Headnote
A) Town Planning - Deemed Sanction - Section 45(4) of Maharashtra Regional and Town Planning Act, 1966 - Once a building proposal is submitted and the Municipal Corporation fails to communicate its refusal within the prescribed period, the proposal is deemed to have been sanctioned - The Corporation cannot later refuse permission on grounds not communicated earlier - Held that the petitioners were entitled to a deemed sanction and the Corporation's subsequent refusal was invalid (Paras 10-15). B) Development Control Regulations - Interpretation - Regulation 4(7) of the Development Control Regulations for Nagpur Municipal Corporation, 2000 - The requirement of obtaining a No Objection Certificate from the Airport Authority of India is not a condition precedent for sanction of building plans under Section 45 of the MRTP Act - The Corporation cannot insist on such NOC at the stage of sanction if not required by the regulations - Held that the Corporation's insistence on NOC was without authority (Paras 16-20). C) Administrative Law - Estoppel - If the Municipal Corporation fails to object within the statutory period, it is estopped from raising objections later - The principle of deemed sanction under Section 45(4) is based on the need for expeditious disposal of building proposals - Held that the Corporation's conduct in not communicating objections within time resulted in a deemed sanction (Paras 12-14).
Issue of Consideration
Whether the Nagpur Municipal Corporation could refuse to sanction building plans after the period specified under Section 45(4) of the Maharashtra Regional and Town Planning Act, 1966 had expired, and whether the petitioners were entitled to a deemed sanction.
Final Decision
Both writ petitions are allowed. The impugned letters of refusal issued by the Nagpur Municipal Corporation are quashed and set aside. The respondents are directed to treat the building proposals as deemed sanctioned under Section 45(4) of the MRTP Act and to issue the necessary commencement certificates within four weeks from the date of the order.
Law Points
- Deemed sanction under Section 45(4) of MRTP Act
- 1966
- Estoppel by conduct
- Duty to communicate objections within prescribed period
- Interpretation of Development Control Regulations



