Bombay High Court Dismisses Amendment Application in Arbitration Challenge Due to Delay and Lack of Diligence. Petitioner Failed to Explain 17-Month Delay in Seeking to Add New Ground Under Section 34 of Arbitration and Conciliation Act, 1996.

High Court: Bombay High Court Bench: BOMBAY
  • 3
Judgement Image
Font size:
Print

Case Note & Summary

The Petitioner, Zee Sports Limited (now Zee Digital Convergence Ltd.), filed a Chamber Summons seeking amendment to its Arbitration Petition under Section 34 of the Arbitration and Conciliation Act, 1996, to incorporate a new ground challenging the arbitral award dated 3 August 2015. The dispute arose from a Heads of Agreement dated 17 January 2005 for a joint venture, leading to arbitration where the Respondent, Nimbus Media Pte. Ltd., was awarded USD 1 million with interest. The Arbitration Petition was filed on 27 October 2015. After several adjournments, on 17 January 2017, the Petitioner orally sought to amend. The Chamber Summons was filed thereafter. The court noted that the Petitioner had been aware of the ground (limitation) from the beginning, as it was raised before the arbitrator. The amendment was sought after 17 months without any explanation for the delay. The court held that amendment is not a matter of right and must be refused if there is lack of diligence or mala fides. The Respondent would be prejudiced as the amendment would require re-adjudication of facts. The court dismissed the Chamber Summons with costs of Rs. 25,000.

Headnote

A) Civil Procedure - Amendment of Pleadings - Delay and Laches - Code of Civil Procedure, 1908, Order VI Rule 17 - The court held that amendment cannot be claimed as a matter of right and must be refused if there is lack of diligence or the application is not bona fide. The Petitioner sought to amend after 17 months without explaining the delay, and the amendment would cause prejudice to the Respondent. (Paras 4-7)

B) Arbitration - Challenge to Award - New Ground - Arbitration and Conciliation Act, 1996, Section 34 - The court refused to allow incorporation of a new ground challenging the award on limitation, as the Petitioner had ample opportunity to raise it earlier and failed to show due diligence. The amendment would also require re-adjudication of facts already decided. (Paras 5-7)

Subscribe to unlock Headnote Subscribe Now

Issue of Consideration

Whether the Petitioner should be permitted to amend the Arbitration Petition to incorporate a new ground challenging the arbitral award, given the delay and lack of diligence.

Subscribe to unlock Issue of Consideration Subscribe Now

Final Decision

Chamber Summons dismissed with costs of Rs. 25,000 to be paid to the Respondent.

Law Points

  • Amendment of pleadings
  • Arbitration Act
  • Section 34
  • delay and laches
  • diligence
  • prejudice
Subscribe to unlock Law Points Subscribe Now

Case Details

2017 LawText (BOM) (01) 9

Chamber Summons (Lodg.) No. 114 of 2017 in Arbitration Petition No. 1698 of 2015

2017-01-31

N.M. Jamdar

Dr. Birendra Saraf a/w. Mr. Rohan Savant, Monisha Bhangale and Warisha Parkar i/b. ALMT Legal for the Applicant - Petitioner; Mr. Sanjay Jain a/w. Mr. Hemant Prabhulkar, Ms. Yogesh Bhoge, Ms. Smita Bhosale i/b. Jurisperitus Mumbai for the Respondent

Zee Sports Limited (now Zee Digital Convergence Ltd.)

Nimbus Media Pte. Ltd.

Subscribe to unlock Case Details (Citation, Judge, Date & more) Subscribe Now

Nature of Litigation

Application for amendment of Arbitration Petition under Section 34 of the Arbitration and Conciliation Act, 1996, to incorporate a new ground challenging the arbitral award.

Remedy Sought

Petitioner sought amendment to incorporate a ground challenging the award on limitation.

Filing Reason

Petitioner wanted to add a new ground after 17 months of filing the Arbitration Petition.

Previous Decisions

Arbitral award dated 3 August 2015 allowed Respondent's claim of USD 1 million with interest. Arbitration Petition filed on 27 October 2015.

Issues

Whether the Petitioner should be permitted to amend the Arbitration Petition to incorporate a new ground challenging the arbitral award, given the delay and lack of diligence.

Submissions/Arguments

Petitioner argued that the amendment was necessary to challenge the award on limitation, which was a legal ground. Respondent opposed, stating that the Petitioner was aware of the ground from the beginning and the application was delayed and lacked bona fides.

Ratio Decidendi

Amendment of pleadings is not a matter of right and must be refused if there is lack of diligence or the application is not bona fide. The Petitioner failed to explain the 17-month delay and the amendment would cause prejudice to the Respondent.

Judgment Excerpts

By this Chamber Summons, the Petitioner has sought an amendment to the Arbitration Petition to incorporate a ground to challenge the Award dated 3 August 2015 rendered by the learned Arbitrator. The amendment cannot be claimed as a matter of right and under all circumstances. The power to grant amendment is with the Court to do justice. However, the Court will not allow amendment if there is lack of diligence on the part of the Applicant. In the present case, the Applicant has not explained the delay of 17 months in seeking the amendment. The ground which the Applicant now wants to incorporate was very much available to the Applicant at the time of filing of the Petition.

Procedural History

Parties entered into Heads of Agreement on 17 January 2005. Dispute arose, leading to arbitration. Respondent filed Application No. 42 of 2010 under Section 11 of the Arbitration and Conciliation Act, 1996. Learned Judge appointed sole arbitrator on 24 January 2011. Arbitrator passed award on 3 August 2015. Petitioner filed Arbitration Petition on 27 October 2015. After several adjournments, on 17 January 2017, Petitioner orally sought to amend. Chamber Summons filed thereafter. Heard on 31 January 2017 and dismissed.

Acts & Sections

  • Arbitration and Conciliation Act, 1996: Section 11, Section 34
  • Code of Civil Procedure, 1908: Order VI Rule 17
Subscribe to unlock full Legal Analysis Subscribe Now
Related Judgement
High Court Bombay High Court Dismisses Amendment Application in Arbitration Challenge Due to Delay and Lack of Diligence. Petitioner Failed to Explain 17-Month Delay in Seeking to Add New Ground Under Section 34 of Arbitration and Conciliation Act, 1996.
Related Judgement
High Court Bombay High Court Allows Appeal in Motor Accident Claim — Insurance Company Agrees to Pay Rs.10,000 as Interest. Parties settle interest dispute amicably in appeal against Tribunal order that omitted interest on compensation.