Case Note & Summary
These first appeals were filed under Section 54 of the Land Acquisition Act, 1894 and Section 96 of the Code of Civil Procedure, 1908 challenging the judgment and award dated 13.01.2017 passed by the Principal Senior Civil Judge, Modasa in Land Acquisition References. The land in question, situated in village Fantadhirpur, Taluka Bayad, District Sabarkantha (now Aravalli), was acquired by the State for construction of a link water canal. A Section 4 notification was published on 05.08.2008 and a Section 6 notification on 30.07.2009. The Special Land Acquisition Officer passed an award on 30.04.2010 determining the market value at Rs.10 per square meter. The landowners sought enhancement under Section 18 of the Act, and the Reference Court relying on an earlier decision for village Desaipura fixed the market value at Rs.110.70 per square meter, awarding additional compensation of Rs.100.70. The appellants contended that the Reference Court erred in relying on the earlier Desaipura decision, as a subsequent decision for the same village (LAR Nos. 1 of 2021 to 12 of 2021) had determined the market value at Rs.422 per square meter. They pointed out that the Section 4 notification in those cases was published on 04.12.2008, only four months after the notification in the present case, and that the State had accepted the later decision. The learned advocate for the appellants also cited a decision of this Court in First Appeal No. 30 of 2026 and allied matters, where compensation was similarly enhanced. The State, through the learned AGP, accepted the decision in LAR Nos. 1 of 2021 to 12 of 2021 and requested an appropriate order. The Court noted that a map produced showed a common boundary between the two villages, which was not disputed by the State. Given the minimal time gap between the notifications, the similarity of purpose, and the State's acceptance of the higher compensation for the adjoining village, the Court held that the market value for the land in Fantadhirpur should also be Rs.422 per square meter. The appeals were allowed and disposed of, with a direction that the difference in compensation be paid to the claimants within eight weeks along with all permissible benefits. However, it was clarified that the claimants would not be entitled to interest for the delayed period, as stated at the time of condonation of delay.
Headnote
A) Land Acquisition - Determination of Market Value - Parity with Adjacent Village - Land Acquisition Act, 1894, Sections 4, 18, 54 - When the acquired land shares a common boundary with land in an adjoining village, and the Section 4 notification dates are proximate (four months apart), the market value should be determined consistently with the compensation awarded for the adjoining village, particularly where the State has accepted the higher compensation in the adjoining village. Held, the appeals are allowed and compensation enhanced to Rs.422 per square meter, with direction to pay the difference within eight weeks along with all permissible benefits, but no interest for the delay period as per earlier order. (Paras 5-8)
Issue of Consideration
Whether the land owners are entitled to enhanced compensation at par with the compensation awarded for lands in adjoining village with similar characteristics and acquired under close proximity of time?
Final Decision
Appeals allowed; market value of acquired land fixed at Rs.422 per square meter; difference in compensation to be paid within eight weeks from date of order with all permissible benefits; claimants not entitled to interest for the delayed period as per earlier condonation order.
Law Points
- Market value determined on parity with adjoining village
- similar notification dates
- State acceptance
- Section 4 and 6 of Land Acquisition Act
- 1894




