Case Note & Summary
The case arises from a dispute between OPG Power Generation Private Limited (OPG) and its holding company Gita Power and Infrastructure Private Limited (Gita Power) on one side, and Enexio Power Cooling Solutions India Private Limited (Enexio) on the other, concerning a contract for design, supply, erection, and commissioning of an air-cooled condenser unit for a thermal power plant. The contract was awarded through a tender floated by OPG, but purchase orders were initially issued by Gita Power on 4 March 2013, later confirmed by OPG in July 2013. The total billed amount was Rs. 46,71,04,493, but only Rs. 39,59,19,629 was paid, leaving a balance of Rs. 6,75,15,631. OPG claimed deductions for liquidated damages (Rs. 3,30,00,000), customs duty (Rs. 5,94,06,693), and other costs, totaling Rs. 9,53,19,708, resulting in a net amount allegedly payable by Enexio. After failed settlement attempts, Enexio invoked arbitration under ICC Rules. The Arbitral Tribunal awarded Enexio Rs. 6,11,75,470 as outstanding principal, along with interest and costs, holding OPG and Gita Power jointly and severally liable. The tribunal rejected OPG's counterclaims for liquidated damages and customs duty. OPG and Gita Power challenged the award under Section 34 of the Arbitration and Conciliation Act, 1996 before a Single Judge of the Madras High Court, who set aside the award on grounds of patent illegality. Enexio appealed under Section 37, and a Division Bench restored the award. The Supreme Court, in the present appeals, considered whether the Division Bench correctly exercised its jurisdiction. The Supreme Court held that the Single Judge had exceeded its limited scope of review by re-appreciating evidence and substituting its own view. The court emphasized that an arbitral award can be set aside only if it is patently illegal or against public policy, and mere erroneous findings of fact do not warrant interference. The court upheld the Division Bench's restoration of the award, affirming the joint and several liability of the holding company, the interpretation of tax clauses, and the rejection of liquidated damages. The appeals were dismissed.
Headnote
A) Arbitration Law - Section 37 of Arbitration and Conciliation Act, 1996 - Appeal against order setting aside arbitral award - The Division Bench allowed the appeal and restored the arbitral award, holding that the Single Judge exceeded its jurisdiction by re-appreciating evidence and interfering with findings of fact. The Supreme Court affirmed, emphasizing the limited scope of interference under Section 37. (Paras 1-150) B) Company Law - Joint and Several Liability - Single Economic Enterprise - The Arbitral Tribunal held that Gita Power (holding company) and OPG (subsidiary) were jointly and severally liable as they acted as a single economic enterprise. The Supreme Court upheld this finding, noting that Gita Power actively participated in negotiations and placed purchase orders. (Paras 13, 150) C) Contract Law - Tax Reimbursement - Interpretation of Clause 6 of Purchase Orders - The Arbitral Tribunal interpreted Clause 6 to require reimbursement of all taxes including CVD and SAD, which are equivalent to excise duty. The Supreme Court upheld this interpretation as plausible and not patently illegal. (Paras 4-5, 150) D) Contract Law - Liquidated Damages - Delay in Performance - The Arbitral Tribunal rejected the claim for liquidated damages as the delay was not solely attributable to the contractor and no loss was proved. The Supreme Court upheld this finding as a reasonable view of evidence. (Paras 6, 150) E) Arbitration Law - Interest - Section 31(7)(b) of Arbitration and Conciliation Act, 1996 - The Arbitral Tribunal awarded interest at 10% per annum on the principal amount from the due date. The Supreme Court upheld this as within the tribunal's discretion. (Paras 12, 150)
Issue of Consideration
Whether the Division Bench of the High Court erred in setting aside the Single Judge's order and restoring the arbitral award, particularly regarding the joint and several liability of the holding company and the interpretation of tax and liquidated damages clauses.
Final Decision
The Supreme Court dismissed the appeals, upholding the Division Bench's judgment restoring the arbitral award. The court held that the Single Judge exceeded its jurisdiction under Section 34 by re-appreciating evidence, and the Division Bench rightly restored the award.
Law Points
- Joint and several liability of holding company and subsidiary
- Single economic enterprise doctrine
- Scope of Section 37 of Arbitration and Conciliation Act
- 1996
- Interpretation of tax reimbursement clauses
- Liquidated damages for delay
- Customs duty liability
- Interest on unpaid principal




