Case Note & Summary
The petitioner, M.Ramesh, proprietor of M/s A.K.Enterprises, a covered establishment under the Employees' Provident Fund and Miscellaneous Provisions Act, 1952 (EPF Act), was allotted Code No. PY/BOM/46272. Due to non-remittance of provident fund contributions for the period from January 2017 to September 2017, proceedings under Section 7Q of the EPF Act were initiated, and an order under Section 14B was passed on 11.06.2018 imposing damages of Rs.8,22,790/- and interest of Rs.6,45,670/- for delayed remittance. Aggrieved, the petitioner filed an appeal before the Central Government Industrial cum Labour Court (CGIT-cum-Labour Court) in EPF No.134/2018, which was dismissed by order dated 02.05.2019. The petitioner then filed a writ petition under Articles 226 and 227 of the Constitution of India seeking to quash the order of the CGIT-cum-Labour Court and the original orders of the Regional Provident Fund Commissioner. The main contention was that the orders were passed without affording an opportunity of hearing, violating principles of natural justice. The High Court, after hearing both sides, held that the Regional Provident Fund Commissioner must follow natural justice before imposing damages and interest. The court quashed the impugned orders and remanded the matter to the Regional Provident Fund Commissioner for fresh consideration after giving the petitioner an opportunity of hearing. The court directed the petitioner to appear before the authority on a specified date and cooperate in the proceedings.
Headnote
A) Administrative Law - Natural Justice - Right to be Heard - Employees' Provident Fund and Miscellaneous Provisions Act, 1952, Sections 14B and 7Q - The court held that the Regional Provident Fund Commissioner must afford an opportunity of hearing before imposing damages and interest for delayed remittance of provident fund contributions. The order passed without hearing the petitioner was quashed as violative of principles of natural justice. (Paras 1-3) B) Labour Law - Provident Fund - Damages for Delayed Remittance - Section 14B, Employees' Provident Fund and Miscellaneous Provisions Act, 1952 - The court held that the authority under Section 14B must consider the explanation of the employer and pass a reasoned order. The impugned order was set aside and the matter remanded for fresh consideration after hearing the petitioner. (Paras 2-3) C) Labour Law - Provident Fund - Interest on Delayed Payment - Section 7Q, Employees' Provident Fund and Miscellaneous Provisions Act, 1952 - The court held that interest under Section 7Q is compensatory and not penal, but the authority must still follow principles of natural justice before levying interest. The order was quashed and remanded. (Paras 2-3)
Issue of Consideration
Whether the order passed under Sections 14B and 7Q of the EPF Act imposing damages and interest without affording an opportunity of hearing to the petitioner is sustainable in law.
Final Decision
The High Court allowed the writ petition, quashed the order dated 02.05.2019 passed by the CGIT-cum-Labour Court in EPF No.134/2018 and the orders dated 11.06.2018 passed by the Regional Provident Fund Commissioner under Sections 14B and 7Q of the EPF Act. The matter was remanded to the Regional Provident Fund Commissioner for fresh consideration after affording an opportunity of hearing to the petitioner. The petitioner was directed to appear before the authority on 20.09.2021.
Law Points
- Natural justice
- right to be heard
- Section 14B
- Section 7Q
- Employees' Provident Fund and Miscellaneous Provisions Act
- 1952
- damages for delayed remittance
- interest on delayed payment
- waiver of pre-deposit