High Court of Karnataka Quashes Termination Notices Issued by Electricity Supply Companies to Sugar Mills Under Power Purchase Agreements for Bagasse-Based Cogeneration Plants. Court Declares PPAs Valid Until Expiry on 01.01.2022 and Directs Parties to Continue Performance.

High Court: Karnataka High Court Bench: BENGALURU In Favour of Accused
  • 63
Judgement Image
Font size:
Print

Case Note & Summary

The judgment concerns a batch of writ petitions filed by sugar mills (Shree Renuka Sugars Limited, Sri Chamundeshwari Sugar Limited, and others) challenging termination notices issued by electricity supply companies (BESCOM, HESCOM, GESCOM, MESCOM, CESC) and the Karnataka Electricity Regulatory Commission (KERC). The petitioners had entered into Power Purchase Agreements (PPAs) dated 02.01.2017 for the supply of electricity generated from bagasse-based cogeneration plants. The PPAs were for a period of five years, expiring on 01.01.2022. The respondents issued termination notices on 06.03.2021 and other dates, alleging that the petitioners had violated the Deviation Settlement Mechanism Regulations, 2018 and the Karnataka Electricity Grid Code, 2015 by not adhering to scheduling and despatch procedures. The petitioners contended that the termination was arbitrary, without prior notice or opportunity of hearing, and contrary to the terms of the PPA. They sought quashing of the termination notices and a declaration that the PPAs were valid till their expiry. The court examined the contractual provisions, the regulatory framework, and the principles of natural justice. It held that the termination notices were illegal as they were issued without following the contractual termination clause, which required a notice period and opportunity to remedy breaches. The court also noted that the respondents had not specified the exact breaches or provided any opportunity for the petitioners to respond. The court quashed the termination notices and declared the PPAs valid until their natural expiry on 01.01.2022. The court directed the parties to continue performance under the PPAs until expiry and to settle any disputes regarding deviation charges through the appropriate forum. The judgment emphasizes that state instrumentalities must act fairly and in accordance with contractual terms and principles of natural justice.

Headnote

A) Electricity Law - Power Purchase Agreement - Validity and Termination - Sections 86, 62, 63 of the Electricity Act, 2003 - The court examined whether PPAs for bagasse-based cogeneration plants could be terminated by electricity supply companies on grounds of alleged non-compliance with Deviation Settlement Mechanism Regulations and Grid Code. Held that the termination notices were arbitrary and illegal as they were issued without affording opportunity of hearing and without considering the contractual terms. The PPAs were declared valid until their expiry on 01.01.2022. (Paras 1-30)

B) Contract Law - Termination of Contract - Natural Justice - Section 56 of Indian Contract Act, 1872 - The court held that termination of a contract by a state instrumentality without giving prior notice or opportunity of hearing violates principles of natural justice. The termination notices were quashed as they were non-speaking and did not specify the alleged breaches. (Paras 15-25)

C) Constitutional Law - Writ Jurisdiction - Article 226 of Constitution of India - The court held that writ petitions are maintainable against state instrumentalities for contractual disputes where the action is arbitrary and violative of Article 14. The existence of alternative remedy does not bar writ jurisdiction when the impugned action is without jurisdiction or in violation of natural justice. (Paras 10-12)

Subscribe to unlock Headnote Subscribe Now

Issue of Consideration

Whether the Power Purchase Agreements (PPAs) dated 02.01.2017 executed between the petitioner sugar mills and the respondent electricity supply companies are valid and subsisting, and whether the termination notices issued by the respondents are arbitrary and illegal.

Subscribe to unlock Issue of Consideration Subscribe Now

Final Decision

The court quashed the termination notices dated 06.03.2021 and others, and declared that the Power Purchase Agreements dated 02.01.2017 are valid and subsisting till their expiry on 01.01.2022. The court directed the parties to continue performance under the PPAs until expiry and to settle any disputes regarding deviation charges through the appropriate forum.

Law Points

  • Power Purchase Agreement
  • Termination
  • Validity
  • Contractual Obligations
  • Electricity Act
  • 2003
  • Section 86
  • Section 62
  • Section 63
  • Renewable Energy
  • Cogeneration
  • Bagasse
  • Sugar Mills
  • Karnataka Electricity Regulatory Commission
  • Tariff
  • Competitive Bidding
  • Deviation Settlement Mechanism
  • Grid Code
  • Force Majeure
  • Frustration of Contract
  • Section 56 of Indian Contract Act
  • 1872
  • Writ Jurisdiction
  • Article 226
  • Article 227
  • Alternative Remedy
  • Disputed Questions of Fact
  • Contractual Disputes
  • Public Law Remedy
  • Private Law Rights
  • State Instrumentality
  • Arbitrariness
  • Unfair Trade Practice
  • Promissory Estoppel
  • Legitimate Expectation
  • Natural Justice
  • Hearing
  • Termination Notice
  • Show Cause Notice
  • Opportunity of Hearing
  • Reasoned Order
  • Speaking Order
  • Non-Compliance with Contractual Terms
  • Breach of Contract
  • Repudiation
  • Anticipatory Breach
  • Damages
  • Specific Performance
  • Injunction
  • Interim Order
  • Status Quo
  • Extension of PPA
  • Fresh Agreement
  • Negotiation
  • Good Faith
  • Mutual Agreement
  • Regulatory Framework
  • KERC Regulations
  • Deviation Settlement Mechanism Regulations
  • 2018
  • Karnataka Electricity Grid Code
  • 2015
  • Forecasting and Scheduling
  • Availability Based Tariff
  • UI Charges
  • DSM Charges
  • Payment Default
  • Letter of Credit
  • Bank Guarantee
  • Security Deposit
  • Performance Guarantee
  • Liquidated Damages
  • Penalty
  • Compensation
  • Interest
  • Late Payment Surcharge
  • Rebate
  • Prompt Payment Discount
  • Billing
  • Metering
  • Energy Accounting
  • Audit
  • Inspection
  • Testing
  • Commissioning
  • Synchronization
  • Evacuation
  • Interconnection
  • Transmission
  • Distribution
  • Open Access
  • Third Party Sale
  • Captive Consumption
  • Group Captive
  • Wheeling Charges
  • Cross Subsidy Surcharge
  • Additional Surcharge
  • Banking
  • Net Metering
  • Gross Metering
  • Feed-in Tariff
  • Renewable Purchase Obligation
  • Renewable Energy Certificate
  • Carbon Credit
  • Clean Development Mechanism
  • Environmental Benefits
  • Sustainable Development
  • Public Interest
  • Consumer Interest
  • Tariff Rationalization
  • Cost Reflectivity
  • Efficiency
  • Economy
  • Competition
  • Non-Discrimination
  • Transparency
  • Accountability
  • Good Governance
  • Rule of Law
  • Separation of Powers
  • Judicial Review
  • Doctrine of Proportionality
  • Doctrine of Reasonableness
  • Doctrine of Legitimate Expectation
  • Doctrine of Promissory Estoppel
  • Doctrine of Frustration
  • Doctrine of Force Majeure
  • Doctrine of Unjust Enrichment
  • Doctrine of Restitution
  • Doctrine of Election
  • Doctrine of Waiver
  • Doctrine of Estoppel
  • Doctrine of Acquiescence
  • Doctrine of Laches
  • Doctrine of Limitation
  • Doctrine of Res Judicata
  • Doctrine of Merger
  • Doctrine of Stare Decisis
  • Doctrine of Precedent
  • Ratio Decidendi
  • Obiter Dicta
  • Per Incuriam
  • Sub Silentio
  • Ex Facie
  • Prima Facie
  • Inter Alia
  • Inter Se
  • Suo Motu
  • De Novo
  • De Hors
  • De Jure
  • De Facto
  • Ipso Facto
  • Ipso Jure
  • Jus Tertii
  • Locus Standi
  • Cause of Action
  • Subject Matter Jurisdiction
  • Territorial Jurisdiction
  • Pecuniary Jurisdiction
  • Appellate Jurisdiction
  • Original Jurisdiction
  • Extraordinary Jurisdiction
  • Inherent Jurisdiction
  • Plenary Jurisdiction
  • Limited Jurisdiction
  • Exclusive Jurisdiction
  • Concurrent Jurisdiction
  • Alternate Dispute Resolution
  • Arbitration
  • Mediation
  • Conciliation
  • Lok Adalat
  • Settlement
  • Compromise
  • Consent Terms
  • Decree
  • Order
  • Judgment
  • Verdict
  • Finding
  • Observation
  • Direction
  • Declaration
  • Mandamus
  • Prohibition
  • Certiorari
  • Quo Warranto
  • Habeas Corpus
  • Writ of
  • Constitutional Remedy
  • Statutory Remedy
  • Common Law Remedy
  • Equitable Remedy
  • Specific Relief
  • Restitution
  • Account of Profits
  • Delivery up
  • Declaration of Rights
  • Stay
  • Interim Relief
  • Ad Interim Relief
  • Ex Parte Ad Interim Relief
  • Notice of Motion
  • Caveat
  • Affidavit
  • Counter Affidavit
  • Rejoinder
  • Sur Rejoinder
  • Written Submissions
  • Oral Arguments
  • Judgment Reserved
  • Judgment Pronounced
  • Operative Portion
  • Final Order
  • Consent Order
Subscribe to unlock Law Points Subscribe Now

Case Details

2021 LawText (KAR) (07) 3

Writ Petition No.6043/2021 (GM-KEB) c/w Writ Petition No.9633/2021, Writ Petition No.9863/2021, Writ Petition No.10349/2021, Writ Petition No.10452/2021, Writ Petition No.11837/2021

2021-07-20

M. Nagaprasanna

Sri Manmohan P.N., Sri Shridhar Prabhu, Smt. M.C. Nagashree, Sri S. Sriranga, Sri B.N. Prakash

Shree Renuka Sugars Limited, Sri Chamundeshwari Sugar Limited, and others

State of Karnataka, Bangalore Electricity Supply Company Limited (BESCOM), Hubli Electricity Supply Company Limited (HESCOM), Gulbarga Electricity Supply Company Limited (GESCOM), Mangalore Electricity Supply Company Ltd (MESCOM), Chamundeshwari Electricity Supply Corporation Ltd (CESC), Power Company of Karnataka Ltd, Karnataka Electricity Regulatory Commission

Subscribe to unlock Case Details (Citation, Judge, Date & more) Subscribe Now

Nature of Litigation

Writ petitions challenging termination of Power Purchase Agreements by electricity supply companies.

Remedy Sought

Quashing of termination notices and declaration that PPAs are valid till 01.01.2022.

Filing Reason

Respondents issued termination notices alleging violation of DSM Regulations and Grid Code without affording opportunity of hearing.

Issues

Whether the termination notices issued by the respondents are arbitrary and illegal. Whether the PPAs are valid and subsisting till their expiry on 01.01.2022. Whether the writ petitions are maintainable in contractual disputes.

Submissions/Arguments

Petitioners argued that termination notices were issued without prior notice or opportunity of hearing, violating principles of natural justice. Petitioners contended that the alleged breaches were not specified and the termination was contrary to the PPA terms. Respondents argued that the petitioners had violated DSM Regulations and Grid Code, justifying termination. Respondents also contended that the writ petitions were not maintainable as there were disputed questions of fact.

Ratio Decidendi

Termination of a contract by a state instrumentality without affording opportunity of hearing and without specifying breaches is arbitrary and violative of Article 14. The existence of an alternative remedy does not bar writ jurisdiction when the impugned action is without jurisdiction or in violation of natural justice. PPAs must be performed in accordance with their terms until expiry.

Judgment Excerpts

The termination notices are quashed. The Power Purchase Agreements dated 02.01.2017 are declared valid and subsisting till their expiry on 01.01.2022. The respondents are directed to continue to perform their obligations under the PPAs until the expiry of the said agreements.

Procedural History

The writ petitions were filed in 2021 challenging termination notices issued in March 2021. The court heard the matter and reserved judgment, pronouncing it on 20.07.2021.

Acts & Sections

  • Electricity Act, 2003: 86, 62, 63
  • Indian Contract Act, 1872: 56
  • Constitution of India: 226, 227
Subscribe to unlock full Legal Analysis Subscribe Now
Related Judgement
High Court Bombay High Court Allows Appeal in Adoption and Hindu Women's Property Rights Case — Widow's Adoption in 1953 Does Not Extinguish Her Limited Estate Under Hindu Women's Rights to Property Act, 1937. The court held that the widow's adoption of a son...
Related Judgement
Supreme Court Supreme Court Quashes Compulsory Retirement Order of IRS Officer Due to Bias and Malice. Compulsory retirement under Rule 56(j) of Fundamental Rules, 1922, set aside as it was punitive, violated natural justice due to biased committee members, and di...