Bombay High Court Allows Appointment of Arbitrator and Grants Interim Relief in Construction Contract Dispute. The court held that the arbitration clause covered the disputes and that the petitioner made out a prima facie case for interim protection under Section 9 of the Arbitration and Conciliation Act, 1996.

High Court: Bombay High Court Bench: BOMBAY
  • 7
Judgement Image
Font size:
Print

Case Note & Summary

The petitioner, Generic Engineering Construction and Projects Ltd., filed Commercial Arbitration Application No. 675 of 2025 under Section 11 of the Arbitration and Conciliation Act, 1996, seeking appointment of an arbitrator for disputes arising out of a Work Order dated 25 January 2023 and Agreement dated 6 February 2023 with the respondent, Maharashtra Maritime Board (MMB), for construction of an office building at Bandra Kurla Complex, Mumbai. The estimated work value was Rs.68,18,50,446/- with a 24-month completion period ending February 2025. Disputes arose regarding site handover, delayed removal of previous contractor's material, delayed drawings/approvals, statutory approvals, and a stop work notice. The respondent issued a show cause notice on 28 July 2025 alleging breaches. The petitioner also filed Commercial Arbitration Petition No. 1070 of 2025 under Section 9 for interim measures to restrain encashment of bank guarantees and termination of the contract. The court examined the arbitration agreement and found it valid. On the Section 9 application, the court held that the petitioner had a prima facie case and balance of convenience favored granting interim relief to prevent irreparable loss. The court appointed a sole arbitrator and granted interim protection subject to the petitioner depositing a sum or furnishing security. The decision was pronounced on 27 April 2026.

Headnote

A) Arbitration Law - Appointment of Arbitrator - Section 11 of the Arbitration and Conciliation Act, 1996 - Existence of Arbitration Agreement - The court examined whether there was a valid arbitration agreement between the parties and whether the disputes fell within its scope. Held that the arbitration clause in the Agreement dated 6 February 2023 covered the disputes raised by the petitioner, and the court appointed a sole arbitrator to adjudicate the disputes (Paras 1-10).

B) Arbitration Law - Interim Measures - Section 9 of the Arbitration and Conciliation Act, 1996 - Prima Facie Case and Balance of Convenience - The court considered the petitioner's application for interim relief to prevent the respondent from encashing bank guarantees and to restrain termination of the contract. Held that the petitioner made out a prima facie case and balance of convenience was in its favor, and granted interim protection subject to conditions (Paras 11-20).

Subscribe to unlock Headnote Subscribe Now

Issue of Consideration

Whether an arbitrator should be appointed under Section 11 of the Arbitration and Conciliation Act, 1996, and whether interim measures under Section 9 of the Act should be granted pending arbitration.

Subscribe to unlock Issue of Consideration Subscribe Now

Final Decision

The court allowed Commercial Arbitration Application No. 675 of 2025 and appointed a sole arbitrator to adjudicate the disputes. The court also allowed Commercial Arbitration Petition No. 1070 of 2025 and granted interim relief subject to the petitioner depositing a sum or furnishing security as directed.

Law Points

  • Section 11 of the Arbitration and Conciliation Act
  • 1996
  • Section 9 of the Arbitration and Conciliation Act
  • Existence of arbitration agreement
  • Prima facie case
  • Balance of convenience
  • Irreparable loss
Subscribe to unlock Law Points Subscribe Now

Case Details

2026 LawText (BOM) (04) 89

Commercial Arbitration Petition No. 1070 of 2025 with Commercial Arbitration Application No. 675 of 2025

2026-04-27

Sandeep V. Marne

Mr. Rohaan Cama with Mr. Chetan Shah, Ms. Farnaaz Karbhari, Mr. Rahul Jain and Mr. Sharan Shetty i/b HSA Advocates, for the Petitioner/Applicant; Dr. Birendra Saraf, Senior Advocate with Mr. Jay Sanklecha, Mr. Harshvardhan Nankani, Mr. Ishwar Nankani, Mr. Huzefa Khokhawala and Mr. Kartik Gupta i/b Nankani & Associates, for the Respondent.

Generic Engineering Construction and Projects Ltd.

Maharashtra Maritime Board

Subscribe to unlock Case Details (Citation, Judge, Date & more) Subscribe Now

Nature of Litigation

Commercial arbitration petition for appointment of arbitrator and interim measures.

Remedy Sought

Appointment of arbitrator under Section 11 of the Arbitration and Conciliation Act, 1996, and interim relief under Section 9 of the Act to restrain encashment of bank guarantees and termination of contract.

Filing Reason

Disputes arose between the parties regarding site handover, delayed approvals, and show cause notice for alleged breaches.

Issues

Whether an arbitrator should be appointed under Section 11 of the Arbitration and Conciliation Act, 1996? Whether interim measures under Section 9 of the Act should be granted?

Submissions/Arguments

Petitioner argued that disputes arose due to respondent's delays and breaches, and sought appointment of arbitrator and interim protection. Respondent opposed the applications, contending that the disputes were not arbitrable or that the petitioner had not made out a case for interim relief.

Ratio Decidendi

The court held that the arbitration agreement existed and covered the disputes, and that the petitioner had a prima facie case and balance of convenience in its favor for interim relief.

Judgment Excerpts

Commercial Arbitration Application No. 675 of 2025 is filed under Section 11 of the Arbitration and Conciliation Act, 1996 seeking appointment of Arbitrator for adjudication of disputes and differences between the parties. Commercial Arbitration Petition No.1070 of 2025 is filed under Section 9 of the Arbitration Act for seeking interim measures.

Procedural History

The petitioner filed Commercial Arbitration Application No. 675 of 2025 under Section 11 and Commercial Arbitration Petition No. 1070 of 2025 under Section 9 of the Arbitration and Conciliation Act, 1996. The court reserved judgment on 10 April 2026 and pronounced it on 27 April 2026.

Acts & Sections

  • Arbitration and Conciliation Act, 1996: Section 11, Section 9
Subscribe to unlock full Legal Analysis Subscribe Now
Related Judgement
Supreme Court Supreme Court Allows State's Appeal in Ceiling Act Case — Customary Divorce Not Proven, Civil Suit Barred. High Court Erred in Interfering with Concurrent Findings and Ignoring Bar of Jurisdiction Under Section 46 of Madhya Pradesh Ceiling on Agric...
Related Judgement
High Court Bombay High Court Allows Appointment of Arbitrator and Grants Interim Relief in Construction Contract Dispute. The court held that the arbitration clause covered the disputes and that the petitioner made out a prima facie case for interim protection ...