Bombay High Court Adjudicates Writ Petition Against MMRDA's Demand for Additional Premium on Alleged Construction Delay. Court Examines Whether Demand is Arbitrary and Violative of Article 14 Given Delays Attributed to the Authority.

High Court: Bombay High Court Bench: BOMBAY
  • 3
Judgement Image
Font size:
Print

Case Note & Summary

The present writ petition was filed by Shree Naman Hotels Pvt. Ltd., a subsidiary of Shree Naman Developers Ltd., against the Mumbai Metropolitan Region Development Authority (MMRDA) and its Metropolitan Commissioner, challenging a demand notice dated 12 September 2017 for payment of additional premium with interest on account of alleged delay in completion of construction of a star category hotel at Bandra-Kurla Complex. MMRDA, a statutory authority under the MMRDA Act, 1974, had floated a tender in February 2005 for an 80-year lease of two combined plots for construction of a hotel with a maximum built-up area of 18,600 sq. mtrs. The bid of the petitioner’s parent company was accepted in February 2006, and after payment of the entire lease premium of Rs.204.60 crores, a lease deed was executed on 9 June 2006. The lease deed provided that construction be completed within four years, i.e., by 9 June 2010, failing which the Metropolitan Commissioner could grant extension upon payment of additional premium. The leasehold rights were subsequently assigned to the petitioner with MMRDA’s approval in August 2006. The petitioner encountered several statutory hurdles: a September 2006 notification required Environmental Impact Assessment clearance, which was obtained on 2 March 2007; excavation permission was granted on 8 March 2007; height clearance from the Civil Aviation Ministry was obtained with restrictions in March 2008; and various commencement certificates were issued between October 2007 and July 2010. The petitioner also sought and obtained permission to utilise additional built-up area against premium, which resulted in construction of two extra floors, but no time limit was stipulated for this additional work. Construction was completed on 14 June 2011, certified by MMRDA on 17 June 2011. MMRDA issued a conditional occupation certificate on 11 October 2011, imposing free usage of suites and conference facilities and requiring payment of additional premium before commencing operations. The petitioner had earlier, on 12 October 2011, been served a demand for additional premium of Rs.25.42 crores for delay beyond the stipulated four-year period. Despite representations for waiver being rejected in January 2012, the petitioner paid a part of the demanded amount under protest but was compelled to give an undertaking not to operate the hotel until full payment. Further demands were made in September 2014 and April 2015, culminating in the impugned demand notice of 12 September 2017. The petitioner contended that the delay was primarily attributable to MMRDA’s own processing time for approvals and unforeseen regulatory changes, and that the demand for the basic built-up area was contrary to the lease deed’s terms, and was arbitrary, illegal, and violative of Article 14 of the Constitution. The matter was heard by a Division Bench of the Bombay High Court, but the excerpt provided does not contain the court’s final decision.

Headnote

A) Constitutional Law - Article 14 - Arbitrary Demand for Additional Premium - Constitution of India, 1950, Article 14 - The petitioner challenged MMRDA's demand for additional premium for delay in construction of a hotel, contending that the delay was caused by MMRDA's own delays in granting statutory approvals and unforeseen regulatory requirements, making the demand arbitrary and discriminatory - The court examined whether the demand violated the right to equality under the Constitution. (Paras 3, 9, 11-14, 21)

Subscribe to unlock Headnote Subscribe Now

Issue of Consideration

Whether the demand for additional premium by MMRDA for delay in completion of construction was contrary to the terms of the lease deed and arbitrary, thus violating Article 14 of the Constitution.

Subscribe to unlock Issue of Consideration Subscribe Now

Law Points

  • lease deed interpretation
  • time for completion
  • extension of time
  • additional premium
  • delay due to authority
  • Article 14
  • arbitrary demand
  • writ jurisdiction
Subscribe to unlock Law Points Subscribe Now

Case Details

2026 LawText (BOM) (04) 49

Writ Petition No. 3209 of 2017

2026-04-08

Shree Chandra Shekhar, CJ, Suman Shyam, J

Petitioner: Mr. Vikram Nankani, Senior Advocate with Mr. Vaibhav Krishna & Mr. Tahir Pande i/b Juris Consillis; Respondents: Mr. Pravin Samdani, Senior Advocate with Mr. Nishant Chotani, Mr. Nivit Srivastava, Ms. Sneha Patil, Ms. Aditi Sinha, Mr. Hrishikesh Joshi & Ms. Isha Vyas i/b Maniar Srivastava Associates

Shree Naman Hotels Pvt. Ltd.

Mumbai Metropolitan Region Development Authority and The Metropolitan Commissioner

Subscribe to unlock Case Details (Citation, Judge, Date & more) Subscribe Now

Nature of Litigation

Writ petition under Article 226 of the Constitution challenging a demand notice for additional premium on account of alleged delay in construction.

Remedy Sought

Quashing of the demand notice dated 12 September 2017 and a declaration that the demand for additional premium for the basic built-up area is contrary to the lease deed and unconstitutional.

Filing Reason

The petitioner contended that the demand was arbitrary, illegal, discriminatory, and violative of Article 14 of the Constitution as the delay was due to MMRDA's own processing delays and unforeseen regulatory changes.

Previous Decisions

The respondent authority rejected the petitioner's representation against the demand on 3 January 2012; no prior judicial proceeding mentioned.

Issues

Whether the demand for additional premium by MMRDA for delay in completion of construction was contrary to the terms of the lease deed and thus arbitrary and illegal. Whether the demand violated Article 14 of the Constitution of India.

Submissions/Arguments

The petitioner argued that the delay was caused by MMRDA's own delays in granting approvals and unforeseen regulatory requirements, that no time limit was stipulated for the additional construction, and therefore the demand was arbitrary and discriminatory.

Judgment Excerpts

Demand Notice dated 12th September 2017 (Exhibit 'P') issued by Respondent No.1–Mumbai Metropolitan Region Development Authority ... demanding payment of additional premium, together with interest, on account of alleged delay in completion of the construction. Article 2(e) lays down that in the event of failure to complete the construction within the stipulated period, the Metropolitan Commissioner may grant extension of time upon payment of additional premium at the prescribed rates. The Petitioner ... contends that such demand pertaining to the construction of the basic built-up area of 18,600 sq. mtrs. in the building known as 'Sofitel Hotel' ... is contrary to the terms and conditions of the Lease Deed ... and therefore, is arbitrary, illegal, discriminatory and also is in violation of the fundamental rights guaranteed to the Petitioner under Article 14 of the Constitution of India.

Procedural History

MMRDA floated tender on 8 February 2005; bid of petitioner's parent company accepted on 3 February 2006; lease deed executed on 9 June 2006; assignment to petitioner on 1 August 2006; various statutory approvals obtained including EIA clearance on 2 March 2007, excavation permission on 8 March 2007, commencement certificates between October 2007 and July 2010; construction completed on 14 June 2011 and certified on 17 June 2011; conditional occupation certificate issued on 11 October 2011; demand for additional premium of Rs.25.42 crores made on 12 October 2011; petitioner's representation rejected on 3 January 2012 and part payment made under protest; further demands in 2014 and 2015; impugned demand notice dated 12 September 2017; writ petition filed challenging said demand.

Acts & Sections

  • Mumbai Metropolitan Region Development Authority Act, 1974:
  • Companies Act, 1956:
  • Constitution of India: Article 14
  • Mumbai Metropolitan Region Development Authority (Disposal of Land) Regulations, 1977:
Subscribe to unlock full Legal Analysis Subscribe Now
Related Judgement
High Court Bombay High Court Adjudicates Writ Petition Against MMRDA's Demand for Additional Premium on Alleged Construction Delay. Court Examines Whether Demand is Arbitrary and Violative of Article 14 Given Delays Attributed to the Authority.
Related Judgement
High Court Bombay High Court Quashes Preventive Detention Order Under MPDA Act for Non-Application of Mind and Failure to Consider Less Drastic Remedies. Detenu's bail in all three predicate offences and lack of credible material to show disturbance of public o...