Case Note & Summary
The Petitioners comprised Om Vishwashanti CHS (Proposed), through its Chief Promoter, and Okhawala Shelter, Builders & Developers, which was appointed as developer for redevelopment of slum structures situated on land bearing CTS No. 558/B and related CTS numbers at Malad East.The land was owned by BMC and was affected by reservations for a Municipal Ward Office, Disaster Management Facilities and Municipal Chowky, apart from setback requirements. The developer obtained a BMC NOC dated 31 December 2021 and subsequently an SRA LOI dated 11 November 2022.The developer submitted plans for the proposed BMC office, but BMC found the proposal inadequate and required substantial modifications, including a larger floor plate, appropriate access, two staircases, proper open spaces and a building suitable for public administration.A show-cause notice was thereafter issued proposing cancellation of the NOC. After hearing the developer, the Additional Municipal Commissioner cancelled the NOC on 10 January 2024.The present writ petition challenged that cancellation.Initially, the Bombay High Court dismissed the petition on 20 June 2025 on the ground that the dispute involved private/contractual issues and that an alternative remedy was available.The Petitioners approached the Supreme Court in SLP (C) No. 31485 of 2025. The Supreme Court modified the High Court's order and directed the High Court to examine the legality and validity of the order dated 10 January 2024. Upon rehearing the matter, the Division Bench examined the NOC, LOI, plans, correspondence and proceedings and ultimately upheld cancellation of the NOC.
Headnote
Slum Rehabilitation Scheme – Municipal land – Conditional NOC – Cancellation of NOC – Developer’s contractual rights – Preferential rights of landowner – Compliance with LOI conditions – Judicial review – Article 226 of the Constitution of India.
The Bombay High Court dismissed a writ petition challenging the Additional Municipal Commissioner’s order dated 10 January 2024 cancelling the NOC dated 31 December 2021 issued in favour of the developer for a Slum Rehabilitation Scheme. The Court held that the BMC, being the owner of the subject land, had preferential rights in relation to development and was entitled to issue an NOC subject to conditions and to revoke the same upon non-compliance.
The Court found that the developer had failed to comply with specific conditions of the NOC and Letter of Intent dated 11 November 2022, including obtaining necessary permissions and concurrence for the proposed Municipal Ward Office, Disaster Management Facility, Cyclone Shelter Centre and Municipal Chowky. The developer had also failed to submit a feasible plan satisfying BMC's requirements for almost a year after issuance of the LOI.
The Court further held that the developer had no independent right in the BMC's land. Its rights were contractual rights arising from its arrangement with the proposed society. Since the NOC was conditional and did not create an irrevocable right in the land, cancellation of the NOC on account of non-compliance did not warrant interference under Article 226.
Accordingly, the Court found no legal infirmity in the impugned order dated 10 January 2024 and dismissed the writ petition without costs.
Issue of Consideration
The Issue of consideration was whether the High Court should entertain the writ petition challenging the cancellation of NOC by Municipal Corporation despite availability of alternate remedy, and whether the cancellation order dated 10.1.2024 was legally valid
Final Decision
Writ Petition dismissed. No costs.
The Division Bench comprising Justice G. S. Kulkarni and Justice Aarti Sathe held that:
the BMC was the owner of the subject land;
the NOC was conditional;
the developer failed to comply with conditions of the NOC and LOI;
the developer failed to submit a feasible plan meeting BMC's requirements;
the BMC was entitled to revoke the conditional NOC;
the impugned order dated 10 January 2024 was properly reasoned and supported by the record; and
there was no legal infirmity warranting interference under Article 226.
The Court therefore dismissed the petition.
Law Points
- Writ jurisdiction under Article 226 of Constitution of India is exercisable when statutory authorities act arbitrarily or without jurisdiction
- Principles of natural justice require fair hearing before cancelling No Objection Certificate (NOC)
- Availability of alternate remedy is not an absolute bar to writ jurisdiction if order is prima facie amenable to judicial review
- Municipal authorities must act within their statutory powers and not arbitrarily cancel permissions
Case Details
2026 LawText (BOM) (02) 62
Writ Petition No. 1612 of 2024
G. S. Kulkarni J. , Aarti Sathye J.
Mr. Girish Godbole, Senior Advocate i/b. Ramsingh & Ajar Ahmed Ansari for Petitioner, Mr. Joel Carlos aw Pushpa Yadav for Respondent No.1 BMC, Mr. Jagdish Aradwad (Reddy) for Respondent No.3-SRA
Om Vishwashanti CHS (Proposed) Through Chief Promoter Sadhashiv Nanekar, Okhawala Shelter, Builders & Developers
Mumbai Municipal Corporation Through Municipal Commissioner, Executive Engineer (D.P.), P & R Ward, Slum Rehabilitation Authority, Additional Municipal Commissioner, BMC Western Suburbs, Assistant Municipal Commissioner, P/North Ward & Competent Authority
Subscribe to unlock Case Details (Citation, Judge, Date & more)
Subscribe Now
Nature of Litigation
Writ Petition under Article 226 of Constitution of India challenging administrative order.
Remedy Sought
Petitioners sought quashing of order dated 10.1.2024 cancelling NOC and direction to sanction building proposal.
Filing Reason
Cancellation of NOC dated 31.12.2021 prevented commencement of slum redevelopment construction
Previous Decisions
A. Order dated 8 November 2023 — WP (L) No. 26148 of 2023
The earlier writ petition concerned the proposed withdrawal/revocation of the developer's rights.
BMC stated before the High Court that the earlier order dated 6 September 2023 would be withdrawn and that a fresh show-cause notice would be issued, followed by a hearing.
The Court kept open the Petitioners' contention concerning the Municipal Commissioner's authority to issue such notice.
B. Order dated 10 January 2024
After issuance of the show-cause notice and hearing, the Additional Municipal Commissioner:
cancelled the NOC dated 31 December 2021;
directed SRA to record the proposed rehabilitation scheme;
directed BMC to undertake construction of the Municipal Ward Office and rehabilitation of eligible structures; and
directed refund of premium charges paid by the developer.
C. Bombay High Court Order dated 20 June 2025
The High Court initially dismissed WP No. 1612 of 2024.
It held, inter alia, that the dispute involved disputed questions concerning planning and design and that the Petitioners did not demonstrate an appropriate constitutional right justifying Article 226 jurisdiction.
It also held that the dispute was essentially private/contractual and that the appropriate remedy was a civil suit.
D. Supreme Court Order dated 28 November 2025
The Petitioners challenged the 20 June 2025 order through SLP (C) No. 31485 of 2025.
The Supreme Court modified the High Court's order to the extent that the High Court was directed to hear the challenge to the 10 January 2024 order in accordance with law.
The Supreme Court expressly clarified that it had not examined the merits of the dispute.
E. SRA Order dated 4 March 2025
During the present proceedings, SRA placed on record an order dated 4 March 2025 cancelling the LOI dated 11 November 2022, subject to the final outcome of the writ petition.
Issues
Issue 1
Whether the BMC was legally entitled to cancel the NOC dated 31 December 2021 issued to the Petitioners?
Issue 2
Whether the developer had complied with the conditions imposed under the NOC and LOI dated 11 November 2022?
Issue 3
Whether the developer had an enforceable or independent right to continue development of the BMC-owned land?
Issue 4
Whether the Additional Municipal Commissioner’s order dated 10 January 2024 suffered from any legal infirmity warranting interference under Article 226?
Issue 5
Whether the Petitioners could rely upon the NOC and LOI despite their failure to obtain the required approvals and submit a feasible plan satisfying BMC's requirements?
Submissions/Arguments
Arguments of the Petitioners
The Petitioners argued that:
the NOC dated 31 December 2021 had been issued after following the required procedure and obtaining legal opinion;
the LOI dated 11 November 2022 was issued on the basis of the NOC;
they had complied with the conditions imposed upon them;
a building plan showing the BMC office area had been submitted on 6 January 2023;
BMC failed to respond to that application;
the cancellation of the NOC was prompted by a complaint by a local MLA/busybody;
they had a legitimate expectation that the NOC would continue;
they had arranged their business affairs and incurred financial consequences relying upon the NOC; and
cancellation of the NOC caused substantial financial loss.
They therefore sought quashing of the impugned order and continuation of the redevelopment project.
BMC contended that:
BMC was the owner of the land and therefore had the primary right concerning its development and utilisation;
the NOC and LOI expressly required compliance with conditions concerning the Municipal Ward Office, Disaster Management Facility and Municipal Chowky;
the developer had failed to construct or provide the required amenities;
the developer had also failed to obtain the necessary permissions and approvals;
LOI Conditions 33 and 53 specifically required various NOCs and concurrence from BMC authorities;
the developer failed to produce a feasible plan meeting the requirements of the user department;
the developer's proposed building was inadequate in terms of floor area, accessibility, fire safety, staircases, open spaces, parking and other requirements; and
cancellation was therefore justified.
The SRA supported BMC's position and relied upon its order dated 4 March 2025, which cancelled the LOI dated 11 November 2022 subject to the outcome of the present writ petition.
SRA contended that the developer had failed to provide a feasible plan for more than a year after issuance of the LOI and had therefore failed to comply with its obligations.
Ratio Decidendi
A developer appointed for a Slum Rehabilitation Scheme does not acquire an independent right in land owned by the BMC merely because a conditional NOC and LOI have been issued. Where the developer fails to comply with the express conditions of the NOC/LOI and fails to submit a feasible development plan satisfying the landowner's requirements, the BMC, as owner of the land, is entitled to revoke the conditional NOC. Such a reasoned decision will not ordinarily warrant interference under Article 226.
Judgment Excerpts
On the developer's contractual rights
“The developer appointed by Petitioner No.1-Society cannot have any independent rights.”
The Court treated the developer's rights as contractual rights arising from its arrangement with the society.
On BMC's ownership
“MCGM/ BMC being the owner of the subject land will have preferential ownership…”
The Court held that BMC's ownership was of particular significance because the land was being developed under an SR scheme.
On non-compliance
“Petitioner no.2-developer had miserably failed to comply with the conditions of the NOC and the Letter of Intent (LOI).”
The Court found the cancellation order supported by the record and declined to interfere.
On the conditions of the LOI
The Court specifically relied upon Conditions 33 and 53, requiring necessary BMC NOCs and concurrence for the proposed Municipal Office Building, Disaster Management Facility, Cyclone Shelter Centre and Municipal Chowky.
Procedural History
2016
Petitioner No. 2 was appointed as developer pursuant to the General Body Resolution dated 27 February 2016.
16 September 2017
Deputy Collector, SRA requested issuance of Annexure II.
30 October 2018
Draft Annexure II was issued.
4 February 2019
Request was made to BMC's Estate Department for NOC for certification of final Annexure II.
31 December 2021
BMC Estate Department issued the NOC for issuance of Annexure II, subject to conditions.
9 February 2022
Final Annexure II was certified and forwarded to SRA.
11 November 2022
SRA issued LOI in favour of the developer, subject to conditions including obtaining necessary DP remarks and BMC approvals.
6 January 2023
Developer submitted plans showing the BMC office BUA to the Executive Engineer (DP).
28 July 2023
Developer issued legal notice seeking sanction of the DP proposal.
12 September 2023
BMC responded to the legal notice.
2023 — WP (L) No. 26148 of 2023
Developer approached the Bombay High Court concerning the failure to sanction the plans and the proposed revocation of the LOI.
8 November 2023
BMC withdrew the earlier order dated 6 September 2023 and agreed to issue a fresh show-cause notice and provide a hearing.
29 December 2023
Fresh show-cause notice issued proposing cancellation of the NOC.
2 January 2024
Hearing was conducted.
10 January 2024
Additional Municipal Commissioner passed the impugned order cancelling the NOC.
2024 — WP No. 1612 of 2024
Petitioners challenged the cancellation before the Bombay High Court.
20 June 2025
High Court dismissed the writ petition on maintainability/alternative-remedy grounds.
2025 — SLP (C) No. 31485 of 2025
Petitioners approached the Supreme Court.
28 November 2025
Supreme Court modified the High Court order and directed examination of the legality and validity of the 10 January 2024 order.
20 January 2026
Matter reserved by the Bombay High Court.
11 February 2026
Division Bench pronounced judgment and dismissed WP No. 1612 of 2024.
Acts & Sections
- Constitution of India: Article 226