Case Note & Summary
The case involves two appeals under Section 37 of the Arbitration and Conciliation Act, 1996, arising from a judgment of a learned Single Judge of the Bombay High Court dated 16 November 2005, which partly set aside an arbitral award dated 4 July 2003. The appellant in Appeal No. 26 of 2006 is Larsen and Toubro Limited (L&T), the original claimant, and the appellant in Appeal No. 14 of 2006 is Hindustan Petroleum Corporation Ltd. (HPCL), the original respondent. The dispute relates to a construction contract between L&T and HPCL for the construction of a lube oil blending plant. The arbitrator had awarded various claims in favor of L&T, including claims for extra work, escalation, refund of liquidated damages, idle labour and machinery, loss of profit, financing charges, and interest. The learned Single Judge set aside the award in respect of Claim Nos. 1, 2, 4, 9, 15, 16, 21(i), 21(iii), and 21(iv), and maintained the award in respect of other claims. Both parties appealed. The Division Bench examined each claim and the grounds for setting aside under Section 34. The court held that the Single Judge's interference was justified for claims that were patently illegal or contrary to public policy, such as claims for extra work not supported by written orders, idle labour and machinery without evidence, loss of profit being speculative, and financing charges not within the contract. However, the court restored the award for refund of liquidated damages, escalation, and interest at 18% per annum, as the arbitrator's findings were plausible and not perverse. The court emphasized that the scope of interference under Section 34 is limited and that the arbitrator's interpretation of contract terms should be respected unless it is so unreasonable that no fair-minded person would accept it. The appeals were disposed of accordingly, with the award being partly restored and partly set aside.
Headnote
A) Arbitration Act, 1996 - Section 34 - Public Policy - Setting Aside of Award - The court examined whether the arbitral award was contrary to the public policy of India and patently illegal. The learned Single Judge had set aside several claims awarded by the arbitrator. The Division Bench held that the Single Judge's interference was justified in respect of claims that were based on no evidence or contrary to the contract terms, but restored certain claims where the arbitrator's findings were plausible. (Paras 1-56) B) Arbitration Act, 1996 - Section 37 - Appeal against Order under Section 34 - Scope - The court considered the scope of appeal under Section 37 against an order setting aside or modifying an arbitral award. It held that the appellate court can re-examine the grounds under Section 34 and can either uphold or reverse the Single Judge's decision. (Paras 1-56) C) Contract Law - Liquidated Damages - Refund of Liquidated Damages - The arbitrator awarded refund of liquidated damages deducted by HPCL. The Single Judge set aside this award. The Division Bench restored the award, holding that the arbitrator's finding that HPCL failed to prove actual loss was not perverse. (Paras 20-25) D) Contract Law - Escalation Clause - Claim for Escalation - The arbitrator awarded escalation under Clause 70C. The Single Judge set aside the award. The Division Bench restored it, noting that the arbitrator's interpretation of the escalation clause was plausible and not contrary to the contract. (Paras 26-30) E) Contract Law - Extra Work - Claim for Extra Work - The arbitrator awarded amounts for extra work. The Single Judge set aside the award. The Division Bench upheld the setting aside, as the claims were not supported by written orders as required by the contract. (Paras 31-35) F) Arbitration Act, 1996 - Interest - Award of Interest - The arbitrator awarded interest at 18% per annum. The Single Judge reduced it to 9% per annum. The Division Bench restored the arbitrator's rate, holding that the arbitrator's discretion on interest is not ordinarily interfered with under Section 34. (Paras 36-40) G) Arbitration Act, 1996 - Claim for Idle Labour and Machinery - The arbitrator awarded compensation for idle labour and machinery. The Single Judge set aside the award. The Division Bench upheld the setting aside, as the claim was not supported by evidence and was contrary to the contract. (Paras 41-45) H) Arbitration Act, 1996 - Claim for Loss of Profit - The arbitrator awarded loss of profit. The Single Judge set aside the award. The Division Bench upheld the setting aside, as the claim was speculative and not proved. (Paras 46-50) I) Arbitration Act, 1996 - Claim for Financing Charges - The arbitrator awarded financing charges. The Single Judge set aside the award. The Division Bench upheld the setting aside, as the claim was not within the scope of the contract. (Paras 51-55)
Issue of Consideration
Whether the learned Single Judge was correct in setting aside the arbitral award in part under Section 34 of the Arbitration and Conciliation Act, 1996, on the ground that the award was contrary to the public policy of India and patently illegal, and whether the cross-appeals against the maintained portions are sustainable.
Final Decision
The Division Bench partly allowed both appeals. It restored the award in respect of Claim No. 1 (refund of liquidated damages), Claim No. 2 (escalation), and Claim No. 21(i) (interest at 18% per annum). It upheld the setting aside of the award in respect of Claim No. 4 (extra work), Claim No. 9 (idle labour and machinery), Claim No. 15 (loss of profit), Claim No. 16 (financing charges), Claim No. 21(iii) and 21(iv) (other claims). The appeals were disposed of accordingly.
Law Points
- Arbitration Act
- 1996
- Section 34
- Section 37
- Public Policy
- Interest Award
- Liquidated Damages
- Escalation Clause
- Extra Work
- Claim for Idle Labour and Machinery
- Claim for Loss of Profit
- Claim for Financing Charges
- Claim for Interest under Interest Act
- 1978




