Case Note & Summary
The appellant, M/s. Amisha Buildcon Pvt. Ltd., filed an appeal under Section 37 of the Arbitration and Conciliation Act, 1996, challenging the order dated 7th April, 2015 passed by the learned Principal District Judge, Thane, dismissing its application under Section 9 of the Act. The appellant had entered into a development agreement with the respondent no.1, Jidnyasa Co-operative Housing Society, for construction of a housing project. The agreement was terminated by the society through a resolution dated 14th September, 2014, citing delays and non-compliance with terms. The appellant sought interim relief to stay the termination and prevent the society from appointing another developer. The District Judge rejected the application, holding that the appellant failed to make out a prima facie case. On appeal, the High Court examined the terms of the agreement and the conduct of the parties. The court noted that the appellant had not completed the construction within the stipulated time and had not obtained necessary approvals. The court also considered that the society had valid reasons for termination. The High Court upheld the District Judge's order, finding no error in the exercise of discretion. The court held that the appellant did not have a strong prima facie case, the balance of convenience was against granting interim relief, and the alleged loss could be compensated by damages. The appeal was dismissed, and the civil application was disposed of.
Headnote
A) Arbitration - Interim Measures under Section 9 - Prima Facie Case - The appellant sought stay of termination of a development agreement by a cooperative housing society. The court held that the appellant failed to establish a prima facie case as the termination was based on valid grounds including non-completion of construction and failure to obtain necessary approvals. (Paras 1-10) B) Arbitration - Interim Measures under Section 9 - Balance of Convenience - The court found that the balance of convenience was in favor of the respondent society as the project was stalled and the society needed to proceed with development. Granting stay would cause greater hardship to the society. (Paras 11-20) C) Arbitration - Interim Measures under Section 9 - Irreparable Loss - The appellant claimed irreparable loss, but the court held that the loss could be compensated in damages and the appellant had an alternative remedy of arbitration. (Paras 21-30)
Issue of Consideration
Whether the appellant was entitled to interim relief under Section 9 of the Arbitration and Conciliation Act, 1996, seeking stay of the resolution dated 14th September, 2014 passed by the respondent society terminating the development agreement.
Final Decision
The High Court dismissed the appeal, upholding the order of the Principal District Judge, Thane. The court found no merit in the appeal and held that the appellant failed to establish a prima facie case, balance of convenience, or irreparable loss. Civil Application No. 19 of 2015 was also disposed of.
Law Points
- Section 9 of the Arbitration and Conciliation Act
- 1996
- Prima facie case
- Balance of convenience
- Irreparable loss
- Interim measures
- Termination of contract
- Development agreement
- Cooperative housing society


