Bombay High Court Dismisses Appeal Against Rejection of Section 9 Interim Relief in Arbitration Dispute Over Development Agreement Termination. Court Holds That Termination of Development Agreement by Cooperative Housing Society Was Valid and Appellant Failed to Make Out a Prima Facie Case for Interim Protection Under Section 9 of the Arbitration and Conciliation Act, 1996.

High Court: Bombay High Court Bench: BOMBAY
  • 187
Judgement Image
Font size:
Print

Case Note & Summary

The appellant, M/s. Amisha Buildcon Pvt. Ltd., filed an appeal under Section 37 of the Arbitration and Conciliation Act, 1996, challenging the order dated 7th April, 2015 passed by the learned Principal District Judge, Thane, dismissing its application under Section 9 of the Act. The appellant had entered into a development agreement with the respondent no.1, Jidnyasa Co-operative Housing Society, for construction of a housing project. The agreement was terminated by the society through a resolution dated 14th September, 2014, citing delays and non-compliance with terms. The appellant sought interim relief to stay the termination and prevent the society from appointing another developer. The District Judge rejected the application, holding that the appellant failed to make out a prima facie case. On appeal, the High Court examined the terms of the agreement and the conduct of the parties. The court noted that the appellant had not completed the construction within the stipulated time and had not obtained necessary approvals. The court also considered that the society had valid reasons for termination. The High Court upheld the District Judge's order, finding no error in the exercise of discretion. The court held that the appellant did not have a strong prima facie case, the balance of convenience was against granting interim relief, and the alleged loss could be compensated by damages. The appeal was dismissed, and the civil application was disposed of.

Headnote

A) Arbitration - Interim Measures under Section 9 - Prima Facie Case - The appellant sought stay of termination of a development agreement by a cooperative housing society. The court held that the appellant failed to establish a prima facie case as the termination was based on valid grounds including non-completion of construction and failure to obtain necessary approvals. (Paras 1-10)

B) Arbitration - Interim Measures under Section 9 - Balance of Convenience - The court found that the balance of convenience was in favor of the respondent society as the project was stalled and the society needed to proceed with development. Granting stay would cause greater hardship to the society. (Paras 11-20)

C) Arbitration - Interim Measures under Section 9 - Irreparable Loss - The appellant claimed irreparable loss, but the court held that the loss could be compensated in damages and the appellant had an alternative remedy of arbitration. (Paras 21-30)

Subscribe to unlock Headnote Subscribe Now

Issue of Consideration

Whether the appellant was entitled to interim relief under Section 9 of the Arbitration and Conciliation Act, 1996, seeking stay of the resolution dated 14th September, 2014 passed by the respondent society terminating the development agreement.

Subscribe to unlock Issue of Consideration Subscribe Now

Final Decision

The High Court dismissed the appeal, upholding the order of the Principal District Judge, Thane. The court found no merit in the appeal and held that the appellant failed to establish a prima facie case, balance of convenience, or irreparable loss. Civil Application No. 19 of 2015 was also disposed of.

Law Points

  • Section 9 of the Arbitration and Conciliation Act
  • 1996
  • Prima facie case
  • Balance of convenience
  • Irreparable loss
  • Interim measures
  • Termination of contract
  • Development agreement
  • Cooperative housing society
Subscribe to unlock Law Points Subscribe Now

Case Details

2016 LawText (BOM) (08) 113

Arbitration Appeal No. 17 of 2015 along with Civil Application No. 19 of 2015

2016-08-09

R.D. Dhanuka, J.

Mr. A. Kumbhakoni, Senior Advocate, a/w. Mr. Shardul Singh, i/b. Mr. Vaibhav Gaikwad for the Appellant. Mr. R.P. Mudholkar for Respondent no.1. Mr. Nishant Tripathi, a/w. Mr. Vaibhav Bagour, i/b. M. Tripathi & Co. for Respondent no.2.

M/s. Amisha Buildcon Pvt. Ltd.

1. Jidnyasa Co-operative Housing Society, 2. M/s. Rajkamal Constructions Pvt. Ltd., 3. Umesh Ramesh Ved, 4. Chandrakant Phatkare, 5. Ramesh Ved, 6. Baban Ratnu Ambekar

Subscribe to unlock Case Details (Citation, Judge, Date & more) Subscribe Now

Nature of Litigation

Appeal under Section 37 of the Arbitration and Conciliation Act, 1996 against dismissal of application under Section 9 for interim relief.

Remedy Sought

Appellant sought stay of operation and implementation of resolution dated 14th September, 2014 terminating the development agreement.

Filing Reason

Appellant challenged the order of the Principal District Judge, Thane dismissing its Section 9 application.

Previous Decisions

The learned Principal District Judge, Thane dismissed Civil Misc. Application No. 359 of 2014 on 7th April, 2015.

Issues

Whether the appellant made out a prima facie case for grant of interim relief under Section 9 of the Arbitration and Conciliation Act, 1996? Whether the balance of convenience was in favor of the appellant? Whether the appellant would suffer irreparable loss if interim relief was not granted?

Submissions/Arguments

Appellant argued that the termination was illegal and arbitrary, and that it had a strong prima facie case. Respondent society contended that the appellant failed to complete construction and obtain approvals, justifying termination. Appellant claimed irreparable loss, while respondents argued that loss could be compensated by damages.

Ratio Decidendi

For grant of interim relief under Section 9 of the Arbitration and Conciliation Act, 1996, the applicant must establish a prima facie case, balance of convenience in its favor, and irreparable loss. In this case, the appellant failed to satisfy these conditions as the termination was valid and the loss could be compensated by damages.

Judgment Excerpts

By this appeal filed under section 37 of the Arbitration and Conciliation Act, 1996, the appellant has impugned the judgment dated 7th April, 2015 passed by the learned Principal District Judge, Thane in Civil Misc. Application No.359 of 2014 dismissing the said application filed by the appellant herein under section 9 of the Arbitration Act.

Procedural History

The appellant filed Civil Misc. Application No. 359 of 2014 under Section 9 of the Arbitration and Conciliation Act, 1996 before the Principal District Judge, Thane, which was dismissed on 7th April, 2015. The appellant then filed the present appeal under Section 37 of the Act before the Bombay High Court.

Acts & Sections

  • Arbitration and Conciliation Act, 1996: Section 9, Section 37
Subscribe to unlock full Legal Analysis Subscribe Now
Related Judgement
Supreme Court Supreme Court Dismisses Union of India's Appeal in Land Acquisition Case, Upholds High Court Decision Based on Binding Precedent. Section 4 Notification Declared Null and Void for Non-Compliance with Mandatory Publication Requirements Under Land Acqu...
Related Judgement
Supreme Court Supreme Court Dismisses Appeal for Declaration of Adoption and Partition – Failure to Prove Ceremony of Giving and Taking Under Hindu Adoptions and Maintenance Act, 1956. The court held that evidence of being treated as a daughter, without proof of...