Case Note & Summary
The case involves a dispute between the State of Maharashtra (plaintiff/respondent) and M/s M.R. Mutha, Engineers and Contractors (defendant/appellant) over the jurisdiction of an arbitrator appointed by the contractor. The State had allotted a construction work to the contractor, which was completed on 7 November 1986, and the final bill was paid on 15 July 1988. The contractor, however, accepted the final bill under protest and informed the State by letter dated 19 July 1988 that it had additional claims for extra items. Despite subsequent correspondence, the State did not decide on these claims until December 1993, when it informed the contractor that the claims were rejected. On 21 February 1994, the contractor appointed an arbitrator under Clause 55 of the contract. The State then filed a suit seeking a declaration that the arbitrator had no jurisdiction and an injunction to restrain the arbitration. The trial court held that the arbitrator had no jurisdiction, and the first appellate court affirmed this decision. The contractor appealed to the High Court. The High Court framed the issue of whether the arbitrator had jurisdiction. The court noted that under Clause 54 and 55 of the contract, claims had to be settled within 30 days after the defect liability period, but the contractor had raised claims within that period and kept them alive through correspondence. The court held that the cause of action arose only in December 1993 when the claims were rejected, and the appointment of the arbitrator in February 1994 was within time. The court also observed that the payment of the final bill did not extinguish the contractor's right to arbitration, as the bill was accepted under protest. Consequently, the High Court allowed the appeal, set aside the judgments of the lower courts, and held that the arbitrator had jurisdiction to adjudicate the dispute.
Headnote
A) Arbitration - Jurisdiction of Arbitrator - Appointment under Contract - Dispute arose only after rejection of claims in December 1993, not on payment of final bill in 1988 - Appointment of arbitrator in 1994 was within time as per contract clause 55 - Held that the arbitrator had jurisdiction (Paras 1-10). B) Limitation - Cause of Action - Contractual Claims - Final bill paid under protest, subsequent correspondence kept claims alive - Rejection of claims in December 1993 gave fresh cause of action - Appointment of arbitrator in 1994 not barred by limitation (Paras 3-10). C) Contract - Interpretation - Clause 54 and 55 - Time for raising claims - Claims raised within defect liability period and pursued thereafter - No waiver or estoppel against contractor - Held that contractor did not lose right to arbitration (Paras 2-10).
Issue of Consideration
Whether the arbitrator appointed by the contractor had jurisdiction to adjudicate the dispute, given the time limits in the contract and the payment of the final bill.
Final Decision
The High Court allowed the appeal, set aside the judgments of the trial court and first appellate court, and held that the arbitrator appointed by the contractor had jurisdiction to adjudicate the dispute.
Law Points
- Arbitration
- Limitation
- Contract Interpretation
- Jurisdiction of Arbitrator
- Cause of Action



