Case Note & Summary
The dispute arose between Ajay Singh, an actor, and Suneel Darshan, a film producer, regarding the production of a film. In 2007, the parties entered into consent terms before an arbitrator, agreeing that the actor would provide 40 shooting dates for the producer's film, subject to mutual agreement on the script. The producer forwarded a script, but the actor sought narration and dialogues, leading to delays and allegations of non-cooperation. The producer claimed he had signed an agreement with Gemini Industries, received an advance of Rs.3 crores, and stood to lose Rs.33 crores if the film was not made. After Gemini terminated its agreement, the producer claimed Rs.20 crores in damages from the actor. The dispute was referred to arbitration. The arbitrator found that the actor had breached the consent terms by varying demands, but rejected the damages claim because the producer failed to prove the Gemini agreement—no witness from Gemini testified, and the connection between Gemini and an entity called Asian Capital Consolidated Fund was unexplained. The agreement seemed to have lapsed earlier. The arbitrator dismissed both the claim and the counterclaim, but awarded Rs.12 lakhs as costs to the producer. Both parties challenged the award: the producer against rejection of damages, and the actor against the findings of breach and the costs. The High Court heard arguments on whether the award was perverse or patently illegal. The court examined the arbitrator's findings on jurisdiction, breach, proof of damages, and costs. The judgment analyzed submissions and the evidence to determine if intervention under Section 34 was warranted.
Headnote
A) Arbitration - Jurisdiction - Consent Terms - Sections 2(1)(b), 16, 34, Arbitration and Conciliation Act, 1996 - The arbitrator held that the arbitral tribunal had jurisdiction to decide disputes arising out of consent terms, including whether the parties had orally agreed on the number of subjects to be offered to the respondent and whether 40 shooting dates were to be allotted consecutively. (Para 13) B) Contract - Breach - Film Production Agreement - The arbitrator found that the respondent had committed breach of the consent terms by keeping on varying his demands on how the subject was to be agreed upon, thereby causing delay in the venture. (Para 14) C) Damages - Proof - Claim of Rs.20 Crores - The arbitrator rejected the claim for damages because the claimant failed to prove the existence and terms of the agreement with M/s. Gemini Industries, no witness from Gemini was examined, no connection between Gemini and Asian Capital Consolidated Fund was established, and the agreement appeared to have ended in November 2007 when a cheque was dishonoured. Held, that no damages could be awarded due to lack of credible evidence of loss. (Para 14) D) Evidence - Documentary Evidence - Stamp Duty - The arbitrator noted that the writing with Gemini, if an assignment, required stamp duty and was not duly proved, though the claimant argued it was merely an agreement to assign. The High Court considered submissions that this finding was perverse. (Paras 16-17) E) Costs - Arbitration Costs - Sections 31(8), 34, Arbitration and Conciliation Act, 1996 - The arbitrator awarded Rs.12 lakhs as costs in favour of the claimant despite dismissing the damages claim, reasoning that the respondent had committed breaches and the claimant was ready and willing. The respondent challenged this award of costs. (Paras 10-12)
Issue of Consideration
Whether the arbitral award rejecting the claimant's damages claim is perverse and liable to be set aside; whether the award of costs of Rs.12 lakhs against the respondent is legal and justified.
Law Points
- Section 34 of Arbitration and Conciliation Act
- 1996
- scope of interference
- patent illegality
- award of costs
- burden of proof
- assignment agreement
- stamp duty


