Case Note & Summary
The dispute arises from a series of hotel management agreements concerning a hotel at Lonavala owned by petitioner Laguna Resorts Pvt. Ltd. (formerly Hasina Resorts). In 1999, petitioner entered into a Hotel Management Agreement with Concept Hospitality Pvt. Ltd. for construction, management, and operation of the hotel for five years, extendable by another five years. During the extended term, Evergreen Hospitality Pvt. Ltd. showed interest, leading to a Tripartite Assignment Agreement dated 1 April 2009 between petitioner, Concept, and Evergreen, under which Concept assigned its rights to Evergreen for the period 1 April 2009 to 13 March 2011. Subsequently, a separate Hotel Management Agreement dated 11 March 2011 was executed between petitioner and Evergreen. Disputes arose; Evergreen invoked arbitration under the 2011 Agreement for claims from 1 April 2009 to 11 March 2016. Separately, Concept invoked arbitration under the 1999 Agreement for claims from July 2006 to March 2009. Concept and Evergreen merged on 24 December 2013, forming CHPL. The Concept arbitration resulted in an award dated 13 September 2016 which was complied with. The Evergreen arbitration resulted in an award dated 22 December 2015 allowing claims for the entire period. Petitioner challenged that award under Section 34; the High Court on 12 March 2019 partially set aside the award, holding that the period 1 April 2009 to 11 March 2011 was governed by the 1999 Concept Agreement, not the 2011 Evergreen Agreement. Thereafter, CHPL invoked arbitration under the 1999 Concept Agreement for the period 1 April 2009 to 11 March 2011. The arbitrator dismissed petitioner’s Section 16 jurisdictional objections (order dated 8 July 2021) and passed the impugned award on 28 November 2022, directing petitioner to pay Rs. 78,09,220/- with interest, costs of Rs. 21,28,809/-, and post-award interest. In the Section 34 petition, petitioner contended that the arbitrator lacked jurisdiction as there was no arbitration agreement between petitioner and CHPL for that period; the assignment did not incorporate the arbitration clause; time spent in Evergreen arbitration could not be excluded under Section 43(4) because the parties and dispute were not identical; and the claim was barred by limitation, res judicata, and constructive res judicata. Petitioner relied on M.R. Engineers and NBCC (India) Ltd. v. Zillion Infraprojects to argue against incorporation of arbitration clause by general reference. The court’s analysis and decision are not provided in the excerpt, which ends with petitioner’s submissions.
Headnote
A) Arbitration – Jurisdiction – Section 16, 43(4) Arbitration and Conciliation Act, 1996 – Exclusion of time spent in prior arbitration – Claimant must demonstrate that new arbitration is with respect to the same dispute and between the same parties – Mere severance of part of earlier Award does not automatically warrant fresh arbitration under a different agreement – Held that Arbitrator dismissed jurisdiction challenge, but petitioner contends that earlier arbitration under Evergreen Agreement cannot be basis for exclusion for claims under Concept Agreement (Paras 8-9). B) Arbitration – Existence of Arbitration Agreement – Sections 7, 16 Arbitration and Conciliation Act, 1996 – Incorporation by reference – General reference to another contract does not incorporate arbitration clause; specific reference required – Tripartite Assignment Agreement dated 1 April 2009 only assigned limited rights; arbitration clause from Concept Agreement not automatically assigned to Evergreen – Held that no arbitration agreement existed between petitioner and Evergreen for period 1 April 2009 to 11 March 2011 (Paras 10-11). C) Civil Procedure – Res Judicata and Constructive Res Judicata – Code of Civil Procedure, 1908 (Order II Rule 2) – Bar of subsequent claims – Claims not raised in earlier arbitration despite being available may be barred – Petitioner argued that CHPL’s claim was barred as it could have been raised in prior arbitration between different entities – Held not addressed in provided excerpt (Paras 7-8). D) Limitation – Exclusion of time – Section 43(4) Arbitration and Conciliation Act, 1996; Section 14 Limitation Act, 1963 – Period spent in good faith in prior arbitration excluded – Condition of identity of parties and dispute – Petitioner contended that time spent in Evergreen arbitration cannot be excluded for Concept Agreement arbitration as parties and agreement differ – Held not addressed in provided excerpt (Paras 8-9).
Issue of Consideration
Whether the Arbitral Tribunal had jurisdiction to entertain CHPL's claims for the period 1 April 2009 to 11 March 2011 under the Concept Agreement of 1999, considering the earlier partial setting aside and the requirements under Section 43(4) of the Arbitration Act; and whether the claim was barred by limitation, res judicata, or constructive res judicata.
Law Points
- arbitration agreement must exist between the parties
- exclusion of time under Section 43(4) of Arbitration Act requires same dispute and same parties
- general reference to a contract does not incorporate its arbitration clause unless specifically referenced
- assignment of rights does not automatically assign arbitration agreement
- res judicata and constructive res judicata under Order II Rule 2 CPC can bar subsequent claims


