Case Note & Summary
The petitioner, Illiyas Mangroo Shaikh, a businessman carrying on business at Kasam Compound, Dharavi, Mumbai, filed a writ petition under Article 226 of the Constitution of India before the Bombay High Court challenging the provisional assessment made by the Assessing Officer of the Bombay Electricity Supply and Transport Undertaking (BEST) for alleged theft of electricity. The petitioner also challenged the subsequent disconnection of electricity supply. The petitioner contended that the assessment was arbitrary and that he was not given a proper opportunity of hearing. The respondents, BEST and its officers, argued that the petitioner was issued a show cause notice and given an opportunity to file objections, but he failed to do so. The court examined the provisions of Sections 126 and 135 of the Electricity Act, 2003, and found that the procedure for provisional assessment was correctly followed. The court noted that the petitioner had an alternative remedy of appeal under Section 127 of the Act, which he did not avail. The appellate authority had rejected the appeal as time-barred, and the court held that the appellate authority had no power to condone delay beyond the statutory period. The court dismissed the petition, upholding the assessment and disconnection, and directed the petitioner to pay the assessed amount or approach the appropriate forum for relief.
Headnote
A) Electricity Law - Theft of Electricity - Provisional Assessment under Section 126 - The court examined the validity of a provisional assessment made by the Assessing Officer for alleged theft of electricity, where the petitioner was given a show cause notice and an opportunity to file objections. The court held that the procedure under Section 126 was followed and the assessment was not arbitrary. (Paras 5-10) B) Electricity Law - Appellate Authority - Limitation under Section 127 - The court considered the petitioner's failure to file an appeal within the prescribed period under Section 127 of the Electricity Act, 2003. The court held that the appellate authority has no power to condone delay beyond the statutory period, and the petition challenging the assessment without exhausting the appellate remedy was not maintainable. (Paras 11-15) C) Electricity Law - Disconnection of Supply - Validity - The court upheld the disconnection of electricity supply for non-payment of assessed dues, noting that the petitioner had not challenged the assessment before the appellate authority and had not paid the amount. The court held that the disconnection was lawful under the Electricity Act, 2003. (Paras 16-18)
Issue of Consideration
Whether the provisional assessment under Section 126 of the Electricity Act, 2003 was valid and whether the petitioner was afforded adequate opportunity of hearing before the final assessment and disconnection.
Final Decision
The Bombay High Court dismissed the writ petition, upholding the provisional assessment and disconnection of electricity supply. The court held that the procedure under Section 126 was followed and the petitioner had an alternative remedy under Section 127 which he did not avail. The court directed the petitioner to pay the assessed amount or approach the appropriate forum.
Law Points
- Electricity theft
- provisional assessment
- show cause notice
- natural justice
- Section 126 Electricity Act 2003
- Section 135 Electricity Act 2003
- Section 127 Electricity Act 2003
- appellate authority
- limitation period
- condonation of delay




