Case Note & Summary
The case arises from a dispute between M/s. Amrutanjan Limited (Petitioner) and M/s. Shamrock International Limited (Respondent) concerning a supply agreement dated 23 January 2002 for the supply of 60,000 kgs of 'CIS + lactum' at Rs.1,550 per kg. The Respondent, an exporter of pharmaceuticals, placed purchase orders under the agreement, but the Petitioner allegedly delayed or failed to deliver certain quantities. The Respondent claimed losses including additional freight charges for air shipments, loss of profits on unfulfilled orders, and interest. The Sole Arbitrator awarded Rs.1,72,73,907/- for loss of profits, allowed set-off of Rs.39,70,000/- payable by the Respondent to the Petitioner, and awarded Rs.5 lacs as costs, with interest at 10% p.a. from the date of award. The Petitioner challenged the award under Section 34 of the Arbitration and Conciliation Act, 1996. The High Court held that the award for additional freight charges was perverse as the Respondent failed to prove mitigation of damages, and set aside that part. The award for loss of profits was upheld as a finding of fact based on evidence. The interest award was set aside as the Arbitrator did not consider the contractual rate of 18% p.a. for delayed payments. The court modified the award accordingly.
Headnote
A) Arbitration Law - Challenge to Arbitral Award - Section 34 of Arbitration and Conciliation Act, 1996 - Court's jurisdiction under Section 34 is limited to grounds of patent illegality, perversity, or contravention of public policy - The court cannot re-appreciate evidence or substitute its own view on merits - Held that the award can be interfered with only if it is so perverse that no reasonable person could have arrived at it (Paras 5-6). B) Contract Law - Mitigation of Damages - Claim for Additional Freight Charges - The claimant must prove that it took reasonable steps to mitigate losses - Where the respondent failed to prove that it had no alternative but to send goods by air, the award for additional freight charges is perverse and set aside (Paras 7-10). C) Contract Law - Loss of Profits - Claim for Unfulfilled Orders - The Arbitrator's finding that the petitioner failed to deliver the contracted quantity is a finding of fact - The measure of damages for loss of profits is the difference between the contract price and the market price on the date of breach - Held that the award of Rs.1,72,73,907/- for loss of profits is upheld as it is based on evidence and not perverse (Paras 11-14). D) Arbitration Law - Interest - Award of Interest from Date of Award - Section 31(7)(b) of Arbitration and Conciliation Act, 1996 - The Arbitrator has discretion to award interest from the date of award till payment - However, where the award does not specify the rate for pre-award period, interest from the date of award at 10% p.a. is set aside as the Arbitrator failed to consider the contractual rate of 18% p.a. for delayed payments (Paras 15-17).
Issue of Consideration
Whether the Arbitrator's award on claims for additional freight charges, loss of profits, and interest is contrary to the terms of the contract and the law, and whether the award is liable to be set aside under Section 34 of the Arbitration and Conciliation Act, 1996.
Final Decision
The High Court partially allowed the petition. It set aside the award for additional freight charges (Rs.1,72,73,907/- included this component? Actually the award for loss of profits was Rs.1,72,73,907/-; the additional freight charges were part of the claim but the court set aside that part. The court upheld the award for loss of profits but set aside the interest award. The matter was remitted to the Arbitrator for reconsideration of interest in accordance with the contract. The court also set aside the award of costs? Not mentioned. The final order: The award for additional freight charges is set aside; the award for loss of profits is upheld; the interest award is set aside and remitted for fresh consideration.
Law Points
- Scope of Section 34 of Arbitration and Conciliation Act
- 1996
- Mitigation of damages
- Award of interest
- Burden of proof for additional expenses
- Loss of profits for unfulfilled orders





