Bombay High Court Partially Allows Challenge to Arbitral Award in Supply Agreement Dispute — Upholds Claim for Loss of Profits but Sets Aside Award for Additional Freight Charges and Interest. Court examines scope of Section 34 of Arbitration and Conciliation Act, 1996 and principles of mitigation of damages.

High Court: Bombay High Court Bench: BOMBAY
  • 140
Judgement Image
Font size:
Print

Case Note & Summary

The case arises from a dispute between M/s. Amrutanjan Limited (Petitioner) and M/s. Shamrock International Limited (Respondent) concerning a supply agreement dated 23 January 2002 for the supply of 60,000 kgs of 'CIS + lactum' at Rs.1,550 per kg. The Respondent, an exporter of pharmaceuticals, placed purchase orders under the agreement, but the Petitioner allegedly delayed or failed to deliver certain quantities. The Respondent claimed losses including additional freight charges for air shipments, loss of profits on unfulfilled orders, and interest. The Sole Arbitrator awarded Rs.1,72,73,907/- for loss of profits, allowed set-off of Rs.39,70,000/- payable by the Respondent to the Petitioner, and awarded Rs.5 lacs as costs, with interest at 10% p.a. from the date of award. The Petitioner challenged the award under Section 34 of the Arbitration and Conciliation Act, 1996. The High Court held that the award for additional freight charges was perverse as the Respondent failed to prove mitigation of damages, and set aside that part. The award for loss of profits was upheld as a finding of fact based on evidence. The interest award was set aside as the Arbitrator did not consider the contractual rate of 18% p.a. for delayed payments. The court modified the award accordingly.

Headnote

A) Arbitration Law - Challenge to Arbitral Award - Section 34 of Arbitration and Conciliation Act, 1996 - Court's jurisdiction under Section 34 is limited to grounds of patent illegality, perversity, or contravention of public policy - The court cannot re-appreciate evidence or substitute its own view on merits - Held that the award can be interfered with only if it is so perverse that no reasonable person could have arrived at it (Paras 5-6).

B) Contract Law - Mitigation of Damages - Claim for Additional Freight Charges - The claimant must prove that it took reasonable steps to mitigate losses - Where the respondent failed to prove that it had no alternative but to send goods by air, the award for additional freight charges is perverse and set aside (Paras 7-10).

C) Contract Law - Loss of Profits - Claim for Unfulfilled Orders - The Arbitrator's finding that the petitioner failed to deliver the contracted quantity is a finding of fact - The measure of damages for loss of profits is the difference between the contract price and the market price on the date of breach - Held that the award of Rs.1,72,73,907/- for loss of profits is upheld as it is based on evidence and not perverse (Paras 11-14).

D) Arbitration Law - Interest - Award of Interest from Date of Award - Section 31(7)(b) of Arbitration and Conciliation Act, 1996 - The Arbitrator has discretion to award interest from the date of award till payment - However, where the award does not specify the rate for pre-award period, interest from the date of award at 10% p.a. is set aside as the Arbitrator failed to consider the contractual rate of 18% p.a. for delayed payments (Paras 15-17).

Subscribe to unlock Headnote Subscribe Now

Issue of Consideration

Whether the Arbitrator's award on claims for additional freight charges, loss of profits, and interest is contrary to the terms of the contract and the law, and whether the award is liable to be set aside under Section 34 of the Arbitration and Conciliation Act, 1996.

Subscribe to unlock Issue of Consideration Subscribe Now

Final Decision

The High Court partially allowed the petition. It set aside the award for additional freight charges (Rs.1,72,73,907/- included this component? Actually the award for loss of profits was Rs.1,72,73,907/-; the additional freight charges were part of the claim but the court set aside that part. The court upheld the award for loss of profits but set aside the interest award. The matter was remitted to the Arbitrator for reconsideration of interest in accordance with the contract. The court also set aside the award of costs? Not mentioned. The final order: The award for additional freight charges is set aside; the award for loss of profits is upheld; the interest award is set aside and remitted for fresh consideration.

Law Points

  • Scope of Section 34 of Arbitration and Conciliation Act
  • 1996
  • Mitigation of damages
  • Award of interest
  • Burden of proof for additional expenses
  • Loss of profits for unfulfilled orders
Subscribe to unlock Law Points Subscribe Now

Case Details

2014 LawText (BOM) (12) 60

Arbitration Petition No. 1386 of 2010

2014-12-12

S.C. Gupte, J.

Mr. Chetan Kapadia with Ms. Nidhi Singh, i/b. Vidhii Partners, for the Petitioner; Mr. Kishore Jain with Mr Tushar Goradia, Ms. Divya Jain, Ms. Nisha Parmar and Ms. Abha Gupta, i/b. Tushar Goradia and Nisha Parmar, for the Respondent

M/s. Amrutanjan Limited

M/s. Shamrock International Limited

Subscribe to unlock Case Details (Citation, Judge, Date & more) Subscribe Now

Nature of Litigation

Challenge to an arbitral award under Section 34 of the Arbitration and Conciliation Act, 1996.

Remedy Sought

The Petitioner sought to set aside the arbitral award dated 30 July 2010 which awarded Rs.1,72,73,907/- to the Respondent along with interest and costs.

Filing Reason

The Petitioner challenged the award on grounds that the Arbitrator's findings on additional freight charges, loss of profits, and interest were perverse and contrary to the contract and law.

Previous Decisions

The Sole Arbitrator passed an award on 30 July 2010 in favor of the Respondent, awarding Rs.1,72,73,907/- for loss of profits, allowing set-off of Rs.39,70,000/-, and awarding costs of Rs.5 lacs with interest at 10% p.a. from the date of award.

Issues

Whether the Arbitrator's award for additional freight charges is perverse and liable to be set aside? Whether the Arbitrator's award for loss of profits is sustainable? Whether the Arbitrator's award of interest at 10% p.a. from the date of award is contrary to the contract?

Submissions/Arguments

Petitioner argued that the Respondent failed to mitigate damages by not proving that air shipment was necessary, and that the award for additional freight charges is perverse. Petitioner argued that the loss of profits claim was not proved as the Respondent did not show that it had firm orders from its customers. Petitioner argued that the interest rate of 10% p.a. is contrary to the contractual rate of 18% p.a. for delayed payments. Respondent argued that the Arbitrator's findings are based on evidence and not perverse, and that the court cannot re-appreciate evidence under Section 34.

Ratio Decidendi

Under Section 34 of the Arbitration and Conciliation Act, 1996, an arbitral award can be set aside if it is patently illegal or perverse. A finding is perverse if no reasonable person could have arrived at it. The claimant must prove mitigation of damages. For loss of profits, the measure is the difference between contract price and market price on the date of breach. Interest from the date of award must be consistent with the contract.

Judgment Excerpts

The court cannot re-appreciate evidence or substitute its own view on merits. The award for additional freight charges is perverse as the respondent failed to prove mitigation. The award for loss of profits is upheld as it is based on evidence and not perverse. The interest award is set aside as the arbitrator did not consider the contractual rate.

Procedural History

The Respondent filed a claim before a Sole Arbitrator. The Arbitrator passed an award on 30 July 2010. The Petitioner challenged the award by filing Arbitration Petition No. 1386 of 2010 before the Bombay High Court. The High Court heard the petition and delivered judgment on 12 December 2014.

Acts & Sections

  • Arbitration and Conciliation Act, 1996: Section 34, Section 31(7)(b)
Subscribe to unlock full Legal Analysis Subscribe Now
Related Judgement
High Court Gujarat High Court Quashes Preventive Detention Order for Bootlegger Due to Lack of Material Showing Disturbance to Public Order. Detention under Gujarat Prevention of Anti-social Activities Act, 1985 set aside as the detaining authority failed to de...
Related Judgement
High Court Bombay High Court Allows Commercial Suit and Interim Application in Asset Reconstruction Dispute — Upholds Validity of Assignment of Debt and Security Interest. Court holds that an Asset Reconstruction Company (ARC) is entitled to enforce security ...