Bombay High Court Adjudicates Commercial Arbitration Petition Challenging Majority Arbitral Award on Royalty Liability for Earthwork. Liability for Royalty on Ordinary Earth Used in Embankment Held by Arbitral Tribunal to be Borne by Employer, Section 34 Petition Filed Challenging Interpretation of Contract Clauses.

High Court: Bombay High Court Bench: BOMBAY
  • 2
Judgement Image
Font size:
Print

Case Note & Summary

The matter involved a challenge under Section 34 of the Arbitration and Conciliation Act, 1996 to a majority arbitral award dated 22nd May 2020 arising from a construction contract. The National Thermal Power Corporation had proposed a Super Thermal Power Plant and engaged Konkan Railway Corporation Ltd. (the petitioner) as Project Management Consultant. The petitioner in turn issued a tender for coal transportation system works. The respondent, M/s. SRCC Company Infra Private Ltd., emerged as the L1 bidder and was issued a Letter of Acceptance on 16th May 2017 for the work valued at Rs. 122,32,98,483/-, with a contract agreement executed on 5th December 2017. During execution, the Collector’s office, Madhya Pradesh, demanded royalty charges at Rs. 100/- per cubic meter for earth used in embankment, aggregating approximately Rs. 22 crore. The respondent invoked arbitration, and a three-member arbitral tribunal was constituted. The majority award held the petitioner liable to pay the royalty and directed the petitioner to modify the contract under Section 26 of the Specific Relief Act, 1963 and Section 20 of the Indian Contract Act, 1872 to reflect the correct consensus ad idem. The dissenting presiding arbitrator directed the respondent to pay the royalty. The petitioner challenged the award on the ground that the tribunal, being a creature of the contract, exceeded its jurisdiction by ignoring clear contractual terms that imposed royalty liability on the contractor as per Clauses 14.2, 37, 57 of the tender conditions and the Schedule of Items. The petitioner relied upon the Supreme Court decision in Union of India v. Bharat Enterprise and contended that the direction to amend the contract was without authority. The respondent supported the award, though its specific submissions are not captured in the extracted portion. The court heard extensive arguments from senior counsel on both sides and reserved judgment on 12th June 2025, pronouncing it on 14th November 2025. The judgment addressed the core issue of whether the majority award suffered from patent illegality or was otherwise liable to be set aside under the narrow scope of Section 34 of the Act.

Headnote

A) Arbitration – Section 34 Challenge – Liability for Royalty – Arbitration and Conciliation Act, 1996, Section 34 – The majority arbitral award held the petitioner liable for royalty on ordinary earth used in embankment and directed payment; the dissenting arbitrator held the respondent liable. The petitioner contended that the contractual terms (Clauses 14.2, 37, 57 of the tender conditions, etc.) place royalty liability on the contractor, and the tribunal exceeded its contractually circumscribed jurisdiction. The High Court examined the contract terms and the scope of interference under Section 34. (Paras 1-4)

B) Contract Law – Modification of Contract by Arbitral Tribunal – Powers under Specific Relief Act, 1963, Section 26 and Indian Contract Act, 1872, Section 20 – The arbitral majority directed the petitioner to modify the contract to reflect the true consensus ad idem, invoking specific relief and contract law provisions. The petitioner argued this was beyond the tribunal’s authority. The High Court assessed whether such direction was permissible in law. (Paras 3-4, 11)

Subscribe to unlock Headnote Subscribe Now

Issue of Consideration

Whether the majority arbitral award holding the petitioner liable to pay royalty on ordinary earth used in the subject work and directing modification of the contract is liable to be set aside under Section 34 of the Arbitration and Conciliation Act, 1996

Subscribe to unlock Issue of Consideration Subscribe Now

Law Points

  • Arbitral tribunal is a creature of contract and cannot traverse beyond its terms
  • strict construction of contract under Arbitration and Conciliation Act
  • 1996
  • interpretation of royalty liability clauses in construction contracts
  • Specific Relief Act
  • 1963 Section 26 and Indian Contract Act
  • 1872 Section 20 invoked for contract modification
Subscribe to unlock Law Points Subscribe Now

Case Details

2025 LawText (BOM) (11) 105

Commercial Arbitration Petition No. 646 of 2021 along with Interim Application (L) No. 4926 of 2020, and Commercial Arbitration Petition No. 641 of 2021 with Interim Application (L) No. 4949 of 2020

2025-11-14

R.I. Chagla J.

Simil Purohit, Subit Chakrabarti, Srushti Thorat, Aashka Vora, Anil Anturkar, Kunal Kumbhat, Karthik Pillai, Kashish N. Chelani, Atharva Date, Harshvardhan Suravanshi

Konkan Railway Corporation Ltd.

M/s. SRCC Company Infra Private Ltd.

Subscribe to unlock Case Details (Citation, Judge, Date & more) Subscribe Now

Nature of Litigation

Commercial arbitration petition under Section 34 of the Arbitration and Conciliation Act, 1996 challenging a majority arbitral award

Remedy Sought

Petitioner seeks setting aside of the majority award dated 22 May 2020 which held it liable to pay royalty and directed modification of contract

Filing Reason

The arbitral tribunal held the petitioner liable for royalty on ordinary earth used in embankment for the construction work, contrary to contractual terms as contended by petitioner

Previous Decisions

Majority arbitral award dated 22 May 2020 directing petitioner to pay royalty and modify contract; Dissent Note directing respondent to pay royalty

Issues

Whether the majority arbitral award is contrary to the contractual terms regarding liability for royalty on earth used in embankment Whether the arbitral tribunal exceeded its jurisdiction by directing modification of the contract under Section 26 of the Specific Relief Act and Section 20 of the Indian Contract Act

Submissions/Arguments

The arbitral tribunal is a creature of contract and cannot traverse beyond its terms; it must strictly interpret and apply the contract clauses The contract clauses (including Clauses 14.2, 37, 57 of the tender conditions and Schedule B Item 1) clearly indicate that royalty on earthwork is to be borne by the contractor The direction to modify/amend the contract using Section 26 of the Specific Relief Act and Section 20 of the Indian Contract Act is beyond the tribunal's jurisdiction and contrary to the principle that the tribunal cannot rewrite the contract

Judgment Excerpts

By the said Award, the Arbitral Tribunal held that the liability to pay royalty on ordinary earth used in the subject work lies with the Petitioner-Respondent and directed the Petitioner-Respondent to make payment of the same. Further, the Arbitral Tribunal directed the Petitioner-Respondent to modify / amend the Contract with the Respondent-Claimant to that extent by invoking Section 26 of the Specific Relief Act, 1963 and Section 20 of the Indian Contract Act, 1872 so as to purportedly correctly reflect the consensus ad idem (between the parties).

Procedural History

NTPC proposed a Super Thermal Power Plant and engaged KRCL as Project Management Consultant; KRCL invited tenders on 23 November 2016; technical bids opened 26 December 2016; financial bids opened 31 March 2017; respondent found L1; Letter of Acceptance issued 16 May 2017; contract agreement executed 5 December 2017; demand for royalty by Collector on 27 December 2018; respondent invoked arbitration on 13 June 2019; arbitral tribunal constituted 20 August 2019; majority award passed 22 May 2020 with dissenting note; petitioner filed Section 34 petition before Bombay High Court.

Acts & Sections

  • Arbitration and Conciliation Act, 1996: Section 34
  • Specific Relief Act, 1963: Section 26
  • Indian Contract Act, 1872: Section 20
Subscribe to unlock full Legal Analysis Subscribe Now
Related Judgement
Supreme Court Supreme Court Examines Jurisdiction of Internal Complaints Committee Under POSH Act in Cross-Departmental Complaint. Court Considers Whether ICC at Aggrieved Woman's Workplace Can Proceed Against Respondent Employed Elsewhere, Focusing on Statutory D...
Related Judgement
High Court Bombay High Court Considers Challenge to Separate Seniority Lists for Graduate and Diploma Engineers in Nagpur Municipal Corporation. Petitioners Claim Seniority Should Be Based on Date of Joining Junior Engineer Post, Not Educational Qualification.