Case Note & Summary
The Bombay High Court considered three appeals under Section 37 of the Arbitration and Conciliation Act, 1996 arising from a construction contract dispute. The appellant, Rajasthan State Co-op Oil Seed Growers Federation Ltd. (Tilam Sangh), a principal employer, engaged National Heavy Engineering Co-operative Ltd. (NHEC) as its Project Management Consultant. NHEC in turn contracted with B.G. Shirke Construction Technology Pvt. Ltd. (Shirke) for the construction of seed processing silos. Shirke completed the work and claimed payment, leading to a civil suit. NHEC applied under Section 8 of the Act to refer the dispute to arbitration, which was allowed. The arbitral tribunal passed an award jointly against Tilam Sangh and NHEC. Tilam Sangh challenged the award under Section 34, arguing lack of jurisdiction due to no privity of contract with Shirke and that the arbitral award was without jurisdiction. The District Court dismissed Tilam Sangh’s petition but allowed NHEC’s petition, holding NHEC was merely an agent and Tilam Sangh was solely liable. Tilam Sangh then filed the present Section 37 appeals. The legal issues were whether a non-signatory to an arbitration agreement can be bound by it, and whether partial setting aside of an award against one party while retaining liability against another constitutes impermissible modification. Tilam Sangh contended that as it was not a party to the agreement containing the arbitration clause, the award was per se without jurisdiction. It also argued that the District Court modified the award by deleting NHEC’s liability. Shirke and NHEC contended that Tilam Sangh was the real principal employer, had actively participated in the project and arbitration, and thus impliedly consented to the arbitration. They relied on the Supreme Court decision in Cox and Kings Ltd. v. SAP India Pvt. Ltd., which held that non-signatories could be bound by an arbitration agreement if there was a common intention and implied consent. The High Court agreed with the respondents, finding that Tilam Sangh was the designated purchasing principal under the contract, that it had participated in the selection of the contractor, in meetings, and even filed a counter-claim in arbitration before withdrawing it. The court held that such conduct indicated implied consent and active participation, making the arbitration agreement binding on Tilam Sangh. On the second issue, the court held that the District Court's order was a partial setting aside, not a modification, as the severable portion of the award against NHEC was set aside without affecting the remainder. The appeals were dismissed, and the arbitral award against Tilam Sangh was upheld. The decision affirms that non-signatories may be compelled to arbitrate based on their conduct and the commercial understanding between the parties.
Headnote
A) Arbitration Law - Non-Signatory to Arbitration Agreement - Binding Effect - Arbitration and Conciliation Act, 1996, Sections 8, 34 - The appellant, a project owner who was not a signatory to the construction contract containing the arbitration clause, challenged the arbitral award on jurisdictional grounds. The court, relying on Cox and Kings Ltd. v. SAP India Pvt. Ltd., held that a non-signatory may be bound by the arbitration agreement if the commercial arrangement demonstrates common intention, implied consent, and active participation. The appellant’s involvement in selecting the contractor, participating in meetings, and filing a counter-claim established its consent to be bound by the arbitration agreement. Held that the arbitral award was not without jurisdiction and the appellant was liable under it. (Paras 13-14) B) Arbitration Law - Partial Setting Aside of Arbitral Award - Modification - Arbitration and Conciliation Act, 1996, Section 34 - The appellant argued that the District Court’s order allowing the agent’s Section 34 petition and deleting its liability while maintaining the award against the appellant constituted impermissible modification. The court held that partial setting aside of an arbitral award is permissible when the portion set aside is severable and does not affect the remaining part. The deletion of the agent’s liability did not alter the appellant’s obligation and was not a modification of the award. Held that the District Court’s action was within the permissible scope of Section 34 and did not amount to modification. (Paras 7, 11)
Issue of Consideration
Whether a non-signatory can be compelled to arbitrate and be held liable under an arbitral award on the basis of implied consent and common intention, and whether the partial setting aside of an arbitral award against a co-obligor constitutes impermissible modification
Final Decision
Appeals dismissed. The High Court upheld the District Court’s order, finding that Tilam Sangh was bound by the arbitration agreement despite being a non-signatory, based on its active participation, common intention, and implied consent. The Arbitral Award was not modified but partially set aside within permissible limits.
Law Points
- Non-signatory to an arbitration agreement may be bound if there is a common intention to arbitrate
- implied consent
- and active participation in the contract
- partial setting aside of an arbitral award does not amount to impermissible modification if the portion set aside is severable



