The matter concerned a contempt petition filed by Ranchhoddas Karsondas Rangwala and Prakash Ranchhoddas Rangwalla (original defendants) alleging that the respondents, including Nalinchandra Gordhandas Soparkar and Shah Developers (original plaintiffs), had willfully disobeyed an order of the High Court dated 19th October 1995. The order was passed in Appeal from Order No.1140 of 1995, arising from a declaratory suit where the plaintiffs claimed ownership of plot CTS No.4B and had obtained an injunction restraining the defendants from interfering with development work. The contempt petition was initially disposed of on 20th August 1996 but the Supreme Court, on appeal, remanded it on 21st July 1997 for fresh examination based on all relevant materials. On remand, the High Court considered the report of the Court Commissioner appointed to survey the properties. The Commissioner visited the site on 18th March 1995 and detailed the physical situation: a nallah between plots 25 and 33, compound walls, heaps of earth reducing the nallah's width, water flow varying from 1 to 6 feet, iron rods embedded to mark boundaries as per parties, a broken sanitary tank with a dug-up portion, and a W.C. The report recorded distances between the plaintiffs' galas and the rods ranging from 26 feet 9 inches to 29 feet 6 inches, while the defendants' boundary wall foundation was found covered by earth. Conflicting boundary claims were noted. The High Court, in its oral judgment, narrated these facts extensively but did not reach a final decision on contempt within the available excerpt. Thus, the outcome of the contempt petition remains unrecorded in this text, with the court focusing on factual assessment rather than delivering an operative order.

Headnote

A) Contempt of Court - Willful Disobedience - Not mentioned - The contempt petition alleged willful disobedience of the High Court order dated 19.10.1995 restraining petitioners from interfering with development work. Matter remanded by Supreme Court for fresh examination on merits. Court considered the Court Commissioner's report to ascertain compliance. No final decision recorded in this excerpt. (Paras 1-11)

Subscribe to unlock Headnote Subscribe Now

Issue of Consideration

Whether the respondents are guilty of willfully disobeying the High Court order dated 19th October 1995?

Subscribe to unlock Issue of Consideration Subscribe Now

Case Details

2006 LawText (BOM) (08) 32

Contempt Petition No.100 of 1996 in Appeal from Order No.1140 of 1995 in Declaratory Suit No.1576 of 1995

2006-08-04

A.M. Khanwilkar

2006 BHC-AS 15030

I.M. Khairadi (amicus curiae for Petitioners), Petitioner No.2 in-person, J. Reis, Denzil D'Mello (for Respondents 1 to 7)

Ranchhoddas Karsondas Rangwala, Prakash Ranchhoddas Rangwalla

Nalinchandra Gordhandas Soparkar, Vijay Bhavanji Sethia, Vinaychand D. Jain, Shah Developers, Jayesh Bhawanji Sethia, Gitabai Ganeshlal Paliwal, Gajraj Sohanlal Jain, Jayantilal Virchand Shah, Ramesh Hazari Shah, Shankerrao Pawar

Subscribe to unlock Case Details (Citation, Judge, Date & more) Subscribe Now

Nature of Litigation

Contempt petition alleging willful disobedience of an interim injunction order in a property development dispute.

Remedy Sought

Petitioners seek to hold Respondents guilty for willfully disobeying the High Court order dated 19th October 1995.

Filing Reason

Respondents allegedly interfered with development work despite injunction.

Previous Decisions

City Civil Court granted temporary injunction on 19.10.1995; Contempt Petition disposed on 20.08.1996; Supreme Court remanded on 21.07.1997.

Issues

Whether the respondents are guilty of willfully disobeying the High Court order dated 19th October 1995?

Submissions/Arguments

Petitioners assert that the respondents have wilfully disobeyed the High Court order dated 19th October 1995 by interfering with development work.

Judgment Excerpts

This Contempt Petition was disposed of on August 20, 1996. Against the said decision, Petitioners carried the matter in Appeal before the Supreme Court. The Supreme Court by order dated July 21, 1997 has relegated the parties before this Court with direction to examine the issues afresh on the basis of all relevant materials on record. The Commissioner undertook detailed investigation as recorded in his report dated 18th March 1995.

Procedural History

The contempt petition was initially disposed of by the High Court on 20.08.1996. The Supreme Court, on appeal, remanded the matter on 21.07.1997 for fresh examination. The High Court then considered the Court Commissioner's report dated 18.03.1995.

Subscribe to unlock full Legal Analysis Subscribe Now
Related Judgement
High Court Bombay High Court Re-examines Contempt Petition in Property Dispute After Supreme Court Remand. Allegation of Willful Disobedience of Interim Injunction Order in Development Conflict to be Assessed on Basis of Court Commissioner's Survey Report.
Related Judgement
Supreme Court Supreme Court Dismisses Bail Appeals of Former Deputy Chief Minister in Delhi Excise Policy Case — Trial Delay Attributable to Appellant's Own Conduct of Filing Frivolous Applications Under Section 207 Cr.P.C. The Court held that the appellant fail...