The petitioner, Arun Nathuram Gaikwad, filed a writ petition in the Bombay High Court challenging the construction of a temple by respondent Nos.3 to 17 in a crowded area of Mumbai without obtaining any permission from the Municipal Corporation of Greater Mumbai (respondent Nos.1 and 2). The petitioner alleged that the construction was unauthorized and had disturbed the atmosphere in the locality, leading to disputes. The Municipal Corporation filed a reply through its Assistant Engineer, Shri R.S. Kurnur, stating that a construction proposal was given in 1999, but the then Assistant Engineer had informed the respondents by letter dated 19th June 1999 that various compliances were required, failing which the proposal could not proceed. Since the necessary documents were not supplied, a stop work notice was issued. However, in utter disregard of the notice, the construction work proceeded. The court noted that it was not disputed that no permission whatsoever was obtained for the construction. Additionally, the reply of the Municipal Corporation stated that at the highest, only 6 ft. of access was available to the property, which was also in view of an order obtained in the City Civil Court. The court held that the construction was unauthorized and in violation of the Development Control Regulations. The court directed the Municipal Corporation to demolish the unauthorized construction within four weeks and to recover the cost of demolition from the respondents. The petition was disposed of accordingly.

Headnote

A) Municipal Law - Unauthorized Construction - Demolition - Mumbai Municipal Corporation Act, 1888, Section 351 - The petitioner challenged the construction of a temple by respondent Nos.3 to 17 without any permission from the Municipal Corporation. The court noted that no permission was obtained and a stop work notice was issued but ignored. The court directed the Municipal Corporation to demolish the unauthorized construction within four weeks and recover the cost from the respondents. (Paras 1-5)

B) Municipal Law - Access Width - Development Control Regulations - The court noted that adequate access was not available to the property, with only 6 ft. access at the highest, which was insufficient. The court held that the construction was in violation of the Development Control Regulations and directed demolition. (Para 4)

Subscribe to unlock Headnote Subscribe Now

Issue of Consideration

Whether the construction of a temple without obtaining necessary permission from the Municipal Corporation and in violation of stop work notice can be allowed to continue.

Subscribe to unlock Issue of Consideration Subscribe Now

Final Decision

The court directed the Municipal Corporation to demolish the unauthorized construction within four weeks and to recover the cost of demolition from respondent Nos.3 to 17. The petition was disposed of accordingly.

Law Points

  • Unauthorized construction
  • municipal permission
  • stop work notice
  • access width
  • demolition order
  • compliance with DCR
Subscribe to unlock Law Points Subscribe Now

Case Details

2006 LawText (BOM) (02) 7

WRIT PETITION NO.2841 OF 2005

2006-02-23

H.L. Gokhale, Abhay S. Oka

Mr. K.R. Dhanuka with Mr. M.B. Jadhav for petitioner; Mr. K.K. Singhvi with Ms. P.A. Purandare for res.Nos.1 & 2; Mr. S.H. Doctor with Mr. K.P. Jain i/by Tushar Goradia & Co. for res.Nos.3 to 15 & 17

Arun Nathuram Gaikwad

Municipal Corporation of Gr. Mumbai & ors.

Subscribe to unlock Case Details (Citation, Judge, Date & more) Subscribe Now

Nature of Litigation

Writ petition challenging unauthorized construction of a temple without municipal permission.

Remedy Sought

Petitioner sought demolition of the unauthorized temple construction and restoration of the area.

Filing Reason

Construction of a temple in a crowded area without any permission from the Municipal Corporation, causing disturbance and disputes in the locality.

Previous Decisions

A stop work notice was issued by the Municipal Corporation but was ignored; an order regarding access was obtained in the City Civil Court.

Issues

Whether the construction of the temple without municipal permission is illegal and liable to be demolished. Whether the Municipal Corporation is obligated to enforce its stop work notice and demolish unauthorized construction.

Submissions/Arguments

Petitioner argued that the construction was unauthorized and without any permission, causing disturbance in the locality. Respondent Nos.3 to 17 did not dispute the lack of permission but claimed some compliances were made; however, no permission was shown. Municipal Corporation admitted that no permission was granted and a stop work notice was issued but ignored.

Ratio Decidendi

Construction without obtaining necessary permission from the Municipal Corporation and in violation of a stop work notice is illegal and must be demolished. The Municipal Corporation is duty-bound to enforce its regulations and remove unauthorized structures.

Judgment Excerpts

It is not disputed that no permission whatsoever is obtained for the purposes of this construction. In utter disregard of such notice, the construction work had proceeded. Adequate access is not available to this property.

Procedural History

The petitioner filed a writ petition in the Bombay High Court in 2005 challenging the unauthorized construction. The court heard the parties and passed the order on 23rd February 2006.

Acts & Sections

  • Mumbai Municipal Corporation Act, 1888: Section 351
Subscribe to unlock full Legal Analysis Subscribe Now
Related Judgement
High Court High Court of Bombay at Goa Dismisses Revenue's Appeal in Income Tax Case — Disallowance Under Section 14A and Capital Expenditure on Bridge Construction. Tribunal's findings that no expenditure was incurred for earning dividend income and that bri...
Related Judgement
High Court Bombay High Court Allows Petition Against Unauthorized Temple Construction in Crowded Area Without Municipal Permission. Court Directs Demolition of Unauthorized Construction and Recovery of Costs from Respondents for Violation of Municipal Laws and ...