Case Note & Summary
The case arose from a petition under Section 9 of the Arbitration and Conciliation Act, 1996, filed by Housing Development and Infrastructure Limited (HDIL) against Mumbai International Airport Private Limited (MIAL) and others, seeking interim measures to restrain the termination of a Slum Rehabilitation Agreement (SR Agreement) and to protect its interests pending arbitration. The dispute relates to a slum rehabilitation project on airport land, which was awarded to HDIL in 2007. HDIL alleged that it had constructed over 7,000 tenements and incurred expenditure of Rs.2,400 crores, but could not complete the rehabilitation due to lack of cooperation from state agencies, particularly in preparing the Annexure-II list of eligible slum dwellers. Consequently, HDIL invoked the force majeure clause. MIAL terminated the SR Agreement on 6 February 2013, citing numerous defaults and delays, and imposed liquidated damages of Rs.276.46 crores. HDIL challenged the termination as illegal and mala fide, seeking various injunctions including a restraint on the termination, status quo on non-transfer assets, and deposit of the bank guarantee amount. MIAL opposed the petition on grounds of maintainability against non-signatories, delay, and also argued that the contract was determinable and therefore no injunction could be granted; it also emphasized the public interest in airport modernization. The High Court, after considering the arguments, dismissed the petition. It held that the SR Agreement was a determinable contract and granting an injunction would amount to specific performance, barred under Sections 14(1)(c) and 41(e) of the Specific Relief Act, 1963. The Court also found that the balance of convenience was against HDIL, as the project was of great public importance for the expansion of Mumbai airport, and that monetary compensation would be an adequate remedy. The Court noted that the petitioner had failed to demonstrate that damages would not be an adequate remedy. It also rejected the force majeure claim, observing that HDIL had the primary responsibility to obtain necessary approvals. The delay of over four months in filing the petition further weighed against interim relief. However, the Court directed that MIAL shall not create third-party rights in respect of 65.2 acres of non-transfer assets until the arbitral tribunal is constituted and passes orders, with liberty to HDIL to seek interim relief before the tribunal.
Headnote
A) Arbitration Law - Interim Measures under Section 9 - Principles for Grant of Interim Injunction - Arbitration and Conciliation Act, 1996, Section 9 - The court explained that while exercising power under Section 9, the court is guided by the principles of the Civil Procedure Code for grant of interim injunctions, requiring the applicant to demonstrate a prima facie case, balance of convenience, and irreparable injury. The power is not untrammelled and must be exercised judiciously. Held, that the court must consider whether damages provide an adequate remedy and whether the contract is determinable. (Paras 14, 18) B) Contract Law - Determinable Contracts and Specific Performance - Injunction to Restrain Termination Barred - Specific Relief Act, 1963, Sections 14(1)(c) and 41(e) - Where a contract is determinable in nature, i.e., capable of being terminated by either party, the court cannot grant an injunction to prevent its termination, as such an order would indirectly amount to specific performance of a contract which is expressly barred under the Specific Relief Act. The Slum Rehabilitation Agreement was held to be determinable, and therefore no injunction could be granted to restrain Respondent No. 1 from acting upon the termination notices. Held, that the remedy of the aggrieved party lies in damages, not in specific performance. (Paras 15, 20) C) Public Law - Public Interest in Infrastructure Projects - Balance of Convenience Against Petitioner - The court emphasized that the project involved clearing of slums on airport land, essential for modernization and expansion of the Mumbai airport, which is a matter of public importance and national interest. Held, that the balance of convenience leaned heavily in favour of Respondent No. 1, as granting an injunction would thwart the public purpose and delay airport development, and the petitioner's private commercial interests must yield to public interest. (Paras 16, 18) D) Arbitration Law - Interim Relief Against Non-Signatories - Maintainability of Section 9 Petition Against Non-Parties to Arbitration Agreement - Arbitration and Conciliation Act, 1996, Section 9 - The court observed that although some respondents were not parties to the arbitration agreement, under Section 9, the court may grant interim measures against them if necessary to protect the subject matter of arbitration. However, in view of the dismissal on merits, this issue did not require a final determination. (Para 13) E) Contract Law - Liquidated Damages and Clause 6.4 - Interpretation of Contractual Penalty - Indian Contract Act, 1872, Section 73 - The petitioner contended that the liquidated damages of Rs.276.46 crores was a penalty and void. The court held that for the purpose of interim injunction, it was not necessary to decide the validity of the clause, and the petitioner could challenge it in arbitration. Held, that the existence of such a clause did not alter the determinable nature of the contract. (Paras 21, 30) F) Limitation - Delay in Filing Petition - Effect of Laches on Grant of Interim Relief - The court noted that the termination occurred on 6 February 2013 and the petition was filed on 26 June 2013, after more than four months. Held, that the delay indicated the absence of urgency and that the petitioner slept over its rights, which militated against grant of interim relief. (Para 25) G) Force Majeure - Clause 26 of SR Agreement - Non-Cooperation of State Agencies as Force Majeure - The petitioner claimed force majeure due to non-preparation of Annexure-II by the Competent Authority, preventing rehabilitation of slum dwellers. The court found that the force majeure clause did not cover this situation as the petitioner had undertaken the obligation to obtain all approvals, and the non-availability of the Annexure was not an event beyond the petitioner's control. Held, that mere non-cooperation of authorities cannot constitute force majeure when the petitioner bore primary responsibility. (Paras 33-35)
Issue of Consideration
Whether the court under Section 9 of the Arbitration and Conciliation Act, 1996 can grant interim injunction restraining termination of a determinable contract; whether balance of convenience and public interest warrant such injunction.
Final Decision
Petition dismissed. Court refused to grant interim relief as prayed. Held that the contract was determinable and no injunction could be granted to prevent its termination; balance of convenience was against petitioner; public interest in airport modernization outweighed private interest. However, Respondent No.1 was directed not to create third party rights in respect of 65.2 acres of non-transfer assets until the arbitral tribunal is constituted and passes orders; petitioner given liberty to apply to arbitral tribunal for interim relief.
Law Points
- Section 9 Arbitration and Conciliation Act 1996
- interim measures
- balance of convenience
- public interest
- determinable contract
- specific performance
- injunction barred
- Specific Relief Act 1963 Section 14(1)(c) and 41(e)
- Indian Contract Act 1872 Section 73
- force majeure
- delay
- prima facie case
- irreparable injury



