Bombay High Court Dismisses Petition for Interim Measures in Slum Rehabilitation Dispute Under Section 9 of Arbitration Act, Citing Public Interest in Airport Development. Termination of Determinable Contract Not Stayed as Injunction Would Amount to Specific Performance Barred Under Specific Relief Act.

High Court: Bombay High Court Bench: BOMBAY In Favour of Accused
  • 104
Judgement Image
Font size:
Print

Case Note & Summary

The case arose from a petition under Section 9 of the Arbitration and Conciliation Act, 1996, filed by Housing Development and Infrastructure Limited (HDIL) against Mumbai International Airport Private Limited (MIAL) and others, seeking interim measures to restrain the termination of a Slum Rehabilitation Agreement (SR Agreement) and to protect its interests pending arbitration. The dispute relates to a slum rehabilitation project on airport land, which was awarded to HDIL in 2007. HDIL alleged that it had constructed over 7,000 tenements and incurred expenditure of Rs.2,400 crores, but could not complete the rehabilitation due to lack of cooperation from state agencies, particularly in preparing the Annexure-II list of eligible slum dwellers. Consequently, HDIL invoked the force majeure clause. MIAL terminated the SR Agreement on 6 February 2013, citing numerous defaults and delays, and imposed liquidated damages of Rs.276.46 crores. HDIL challenged the termination as illegal and mala fide, seeking various injunctions including a restraint on the termination, status quo on non-transfer assets, and deposit of the bank guarantee amount. MIAL opposed the petition on grounds of maintainability against non-signatories, delay, and also argued that the contract was determinable and therefore no injunction could be granted; it also emphasized the public interest in airport modernization. The High Court, after considering the arguments, dismissed the petition. It held that the SR Agreement was a determinable contract and granting an injunction would amount to specific performance, barred under Sections 14(1)(c) and 41(e) of the Specific Relief Act, 1963. The Court also found that the balance of convenience was against HDIL, as the project was of great public importance for the expansion of Mumbai airport, and that monetary compensation would be an adequate remedy. The Court noted that the petitioner had failed to demonstrate that damages would not be an adequate remedy. It also rejected the force majeure claim, observing that HDIL had the primary responsibility to obtain necessary approvals. The delay of over four months in filing the petition further weighed against interim relief. However, the Court directed that MIAL shall not create third-party rights in respect of 65.2 acres of non-transfer assets until the arbitral tribunal is constituted and passes orders, with liberty to HDIL to seek interim relief before the tribunal.

Headnote

A) Arbitration Law - Interim Measures under Section 9 - Principles for Grant of Interim Injunction - Arbitration and Conciliation Act, 1996, Section 9 - The court explained that while exercising power under Section 9, the court is guided by the principles of the Civil Procedure Code for grant of interim injunctions, requiring the applicant to demonstrate a prima facie case, balance of convenience, and irreparable injury. The power is not untrammelled and must be exercised judiciously. Held, that the court must consider whether damages provide an adequate remedy and whether the contract is determinable. (Paras 14, 18)

B) Contract Law - Determinable Contracts and Specific Performance - Injunction to Restrain Termination Barred - Specific Relief Act, 1963, Sections 14(1)(c) and 41(e) - Where a contract is determinable in nature, i.e., capable of being terminated by either party, the court cannot grant an injunction to prevent its termination, as such an order would indirectly amount to specific performance of a contract which is expressly barred under the Specific Relief Act. The Slum Rehabilitation Agreement was held to be determinable, and therefore no injunction could be granted to restrain Respondent No. 1 from acting upon the termination notices. Held, that the remedy of the aggrieved party lies in damages, not in specific performance. (Paras 15, 20)

C) Public Law - Public Interest in Infrastructure Projects - Balance of Convenience Against Petitioner - The court emphasized that the project involved clearing of slums on airport land, essential for modernization and expansion of the Mumbai airport, which is a matter of public importance and national interest. Held, that the balance of convenience leaned heavily in favour of Respondent No. 1, as granting an injunction would thwart the public purpose and delay airport development, and the petitioner's private commercial interests must yield to public interest. (Paras 16, 18)

D) Arbitration Law - Interim Relief Against Non-Signatories - Maintainability of Section 9 Petition Against Non-Parties to Arbitration Agreement - Arbitration and Conciliation Act, 1996, Section 9 - The court observed that although some respondents were not parties to the arbitration agreement, under Section 9, the court may grant interim measures against them if necessary to protect the subject matter of arbitration. However, in view of the dismissal on merits, this issue did not require a final determination. (Para 13)

E) Contract Law - Liquidated Damages and Clause 6.4 - Interpretation of Contractual Penalty - Indian Contract Act, 1872, Section 73 - The petitioner contended that the liquidated damages of Rs.276.46 crores was a penalty and void. The court held that for the purpose of interim injunction, it was not necessary to decide the validity of the clause, and the petitioner could challenge it in arbitration. Held, that the existence of such a clause did not alter the determinable nature of the contract. (Paras 21, 30)

F) Limitation - Delay in Filing Petition - Effect of Laches on Grant of Interim Relief - The court noted that the termination occurred on 6 February 2013 and the petition was filed on 26 June 2013, after more than four months. Held, that the delay indicated the absence of urgency and that the petitioner slept over its rights, which militated against grant of interim relief. (Para 25)

G) Force Majeure - Clause 26 of SR Agreement - Non-Cooperation of State Agencies as Force Majeure - The petitioner claimed force majeure due to non-preparation of Annexure-II by the Competent Authority, preventing rehabilitation of slum dwellers. The court found that the force majeure clause did not cover this situation as the petitioner had undertaken the obligation to obtain all approvals, and the non-availability of the Annexure was not an event beyond the petitioner's control. Held, that mere non-cooperation of authorities cannot constitute force majeure when the petitioner bore primary responsibility. (Paras 33-35)

Subscribe to unlock Headnote Subscribe Now

Issue of Consideration

Whether the court under Section 9 of the Arbitration and Conciliation Act, 1996 can grant interim injunction restraining termination of a determinable contract; whether balance of convenience and public interest warrant such injunction.

Subscribe to unlock Issue of Consideration Subscribe Now

Final Decision

Petition dismissed. Court refused to grant interim relief as prayed. Held that the contract was determinable and no injunction could be granted to prevent its termination; balance of convenience was against petitioner; public interest in airport modernization outweighed private interest. However, Respondent No.1 was directed not to create third party rights in respect of 65.2 acres of non-transfer assets until the arbitral tribunal is constituted and passes orders; petitioner given liberty to apply to arbitral tribunal for interim relief.

Law Points

  • Section 9 Arbitration and Conciliation Act 1996
  • interim measures
  • balance of convenience
  • public interest
  • determinable contract
  • specific performance
  • injunction barred
  • Specific Relief Act 1963 Section 14(1)(c) and 41(e)
  • Indian Contract Act 1872 Section 73
  • force majeure
  • delay
  • prima facie case
  • irreparable injury
Subscribe to unlock Law Points Subscribe Now

Case Details

2013 LawText (BOM) (08) 70

Arbitration Petition (Ld.) No. 902 of 2013

2013-08-23

Ranjit More, J.

2013:BHC-OS:8487

Mukul Rohatgi, Ravi Kadam, T. N. Subramaniam, Arif Bookwala, P. K. Dhakephalkar, Rajesh Shah, Gaurav Joshi, Mahesh Agarwal, Satyen Vora, Piyush Raheja, Chetan Yadav, Sahil Gandhi for Petitioner; Janak Dwarkadas, Virag Tulzapurkar, Dr. Birendra Saraf, Farid Karachiwala, Shoma Maitra for Respondent No. 1; Satish Upadhay for Respondent No. 2; U. S. Upadhay for Respondent Nos. 3 and 4; Kiran Bagalia for Respondent No. 5; Shailesh Shah, G. Utangale for Respondent No. 6.

Housing Development and Infrastructure Limited

Mumbai International Airport Private Limited & Others

Subscribe to unlock Case Details (Citation, Judge, Date & more) Subscribe Now

Nature of Litigation

Petition under Section 9 of Arbitration and Conciliation Act, 1996 seeking interim measures to restrain termination of Slum Rehabilitation Agreement and to protect rights pending arbitration.

Remedy Sought

Restrain Respondent No.1 from acting on termination notices; restrain dealing with 65.2 acres of non-transfer assets; maintain status quo on non-transfer assets and residential colony; restrain taking possession of rehabilitation tenements; deposit Rs.25 crores in no lien account; restrain revocation of permissions.

Filing Reason

Respondent No. 1 terminated the Slum Rehabilitation Agreement on 6 February 2013 for alleged defaults by Petitioner; Petitioner alleged illegal termination and sought protection of its investments and work done.

Previous Decisions

Earlier petition under Section 9 (Arbitration Petition (Ld.) No. 1538 of 2012) for interim relief against invocation of bank guarantee was dismissed on 29 November 2012, and appeal was also dismissed.

Issues

Whether interim injunction can be granted to restrain termination of a determinable contract, given the bar under Sections 14(1)(c) and 41(e) of Specific Relief Act, 1963. Whether the petitioner had a prima facie case for grant of interim measures under Section 9 of the Arbitration and Conciliation Act, 1996. Whether the balance of convenience lay in favour of the petitioner, considering the public interest in airport modernization and the project's purpose. Whether the petition was maintainable against respondents not party to arbitration agreement. Whether the petition was barred by delay. Whether the petitioner's force majeure claim excused non-performance.

Submissions/Arguments

Petitioner argued that the SR Agreement was illegally terminated; it had substantially performed its obligations, having constructed over 7,000 tenements and incurred Rs.2,400 crores expenditure; government agencies failed to cooperate, especially in preparing Annexure-II; force majeure clause applied; bank guarantee was illegally invoked; and interim measures were necessary to protect its rights. Respondent No. 1 contended that the petition was not maintainable against non-signatories; there was delay of over four months; the contract was determinable and no injunction could be granted to prevent its termination; the balance of convenience was against the petitioner as the project was of national importance for airport modernization; petitioner failed to meet milestones and did not remedy defaults despite notice; monetary compensation was adequate remedy.

Ratio Decidendi

Under Section 9 of the Arbitration and Conciliation Act, 1996, interim injunction cannot be granted to prevent termination of a contract that is determinable in nature, as it would amount to specific performance of a contract which is barred under Sections 14(1)(c) and 41(e) of the Specific Relief Act, 1963. The balance of convenience must weigh in favour of the party seeking injunction; where the contract is for a public project of national importance, public interest overrides private commercial interest. Monetary compensation is an adequate remedy for breach. The power under Section 9 is guided by the principles of the Civil Procedure Code, and an injunction will not be granted if the injury can be compensated in money.

Judgment Excerpts

It is a settled law that no injunction can be granted to prevent the breach of a contract, the performance of which would not be specifically enforced. (See Section 14(1)(c) and Section 41(e) of the Specific Relief Act, 1963). The balance of convenience is heavily tilted against the petitioner. The project involves clearing of slums on airport land, which is of great public importance for modernization and expansion of the Mumbai airport. In a contract of this nature, where the contract is determinable, the remedy of the party aggrieved lies in damages, and not in specific performance.

Procedural History

Petitioner filed earlier Section 9 petition (Arbitration Petition (Ld.) No. 1538 of 2012) against invocation of bank guarantee, which was dismissed on 29 November 2012; appeal dismissed. Thereafter, Respondent No. 1 terminated the SR Agreement on 6 February 2013. Petitioner sought mediation but was refused. Then filed present petition on 26 June 2013 seeking interim reliefs.

Acts & Sections

  • Arbitration and Conciliation Act, 1996: 9
  • Specific Relief Act, 1963: 14(1)(c), 41(e)
  • Indian Contract Act, 1872: 73
Subscribe to unlock full Legal Analysis Subscribe Now
Related Judgement
Supreme Court Supreme Court Upholds Scrutiny Committee Invalidation of Scheduled Tribe Caste Claim but Protects Retiral Benefits Under Article 142. Pre-Constitutional Records Showing 'Koli' Held to Have High Probative Value to Reject 'Tokre Koli' Claim, While Supr...
Related Judgement
High Court Bombay High Court Quashes Executing Court's Order Sending Precepts to Collector for Partition Under Section 54 CPC — Consent Decree for Injunction Not a Decree for Partition. The court held that Section 54 of the Code of Civil Procedure, 1908 appli...