Case Note & Summary
The case involves an appeal by M/s. Bombay Railways Engineering Co. against the General Manager, Central Railway, arising from a challenge to an arbitral award under Section 34 of the Arbitration and Conciliation Act, 1996. The appellant was awarded a contract for Shallow Screening of Track on 10 April 2000 at a total cost of Rs.37.80 lakhs, with a completion period of six months from January 2000. The work was completed on 13 March 2002, and the appellant was paid Rs.42 lakhs. The appellant challenged the arbitral award insofar as it declined claims 1, 10, and 11, which were for under-utilisation of labour force, overhead charges, and loss of profits due to an extension of the contract. The key issue was whether Clause 17(iii) of the General Conditions of Contract, which prohibits the contractor from claiming damages or compensation for delays caused by the Railway, barred these claims. The Division Bench, following the Supreme Court's decision in Ramnath International Construction Private Limited v. Union of India, AIR 2007 SC 509, and its own decision in Union of India v. M/s. Shyam Constructions, held that Clause 17(iii) is prohibitory in nature and clearly bars any claim for compensation arising from extensions granted. The court found no merit in the appeal and dismissed it, upholding the Single Judge's order. The decision reinforces the principle that express contractual terms prohibiting compensation for delays must be given effect, and arbitral awards that respect such terms are not liable to be set aside under Section 34 of the Arbitration and Conciliation Act, 1996.
Headnote
A) Arbitration - Challenge to Arbitral Award - Section 34 of Arbitration and Conciliation Act, 1996 - The appellant challenged an arbitral award under Section 34 of the Arbitration and Conciliation Act, 1996, which was dismissed by the learned Single Judge. The appeal was against the dismissal of the petition. The Division Bench upheld the Single Judge's order, finding no merit in the appeal. (Paras 1-5) B) Contract Law - Interpretation of Clause 17(iii) - Compensation for Delay - Clause 17(iii) of General Conditions of Contract - The clause expressly prohibits the contractor from claiming damages or compensation for any delay caused by the Railway, including failure to hand over possession or provide drawings. The court held that the clause is prohibitory in nature and bars claims for compensation arising from extensions granted. (Paras 3-4) C) Precedent - Binding Effect of Supreme Court Decision - Ramnath International Construction Private Limited v. Union of India, AIR 2007 SC 509 - The Division Bench followed the Supreme Court's interpretation of a similar clause, which held that in view of clear contractual terms, no compensation is payable for delays. The court applied this principle to the present case. (Para 4)
Issue of Consideration
Whether the appellant is entitled to claims for under-utilisation of labour force, overhead charges, and loss of profits arising from an extension of the contract, in light of Clause 17(iii) of the General Conditions which prohibits compensation for delays caused by the Railway.
Final Decision
The appeal is dismissed. The Division Bench upheld the order of the learned Single Judge dismissing the petition under Section 34 of the Arbitration and Conciliation Act, 1996. No order as to costs.
Law Points
- Arbitration
- Contract Law
- Interpretation of Contractual Clauses
- Compensation for Delay
- Clause 17(iii) of General Conditions of Contract


