Case Note & Summary
The petitioner, M/s. R.M. Cylinders Private Limited, challenged an arbitral award dated 30 August 2010 passed by a sole arbitrator under Section 34 of the Arbitration and Conciliation Act, 1996. The dispute arose from a purchase order dated 7 June 2004 and a tender dated 25 April 2003 for supply of LPG cylinders. The respondent, Hindustan Petroleum Corporation Limited, imposed liquidated damages of Rs.24,06,885 for undelivered quantity and Rs.1,25,361 for delayed supply, totaling Rs.25,32,246. The arbitrator upheld the imposition and recovery of these damages, and also directed the petitioner to deposit a balance of Rs.24,995 and the respondent to refund a deposit of Rs.5 lakhs. The petitioner contended that the award was contrary to public policy and that the arbitrator had misconstrued the contractual clauses. The court, after hearing arguments, held that the arbitrator's interpretation was plausible and within the terms of the contract. The court noted that the scope of interference under Section 34 is limited and does not permit reappreciation of evidence. The court found no patent illegality or perversity in the award and dismissed the petition, upholding the award.
Headnote
A) Arbitration - Section 34 Challenge - Liquidated Damages - Arbitration and Conciliation Act, 1996, Section 34 - The petitioner challenged an arbitral award that upheld the respondent's imposition of liquidated damages for delayed and undelivered LPG cylinders. The court held that the award was not contrary to public policy and did not suffer from patent illegality, as the arbitrator had interpreted the contractual clauses and given a plausible view. (Paras 1-16) B) Contract - Liquidated Damages - Interpretation of Clauses - The dispute involved clauses 8, 9, 10 of the purchase order and tender which provided for liquidated damages for delayed supply and undelivered quantity. The court found that the arbitrator's interpretation was reasonable and within the terms of the contract, and thus not open to interference under Section 34. (Paras 2-10) C) Arbitration - Section 34 - Scope of Interference - The court reiterated that the scope of interference under Section 34 is narrow and does not permit reappreciation of evidence or substitution of the arbitrator's view. The award was upheld as it was not perverse or irrational. (Paras 11-16)
Issue of Consideration
Whether the arbitral award upholding the imposition of liquidated damages for delayed and undelivered LPG cylinders is liable to be set aside under Section 34 of the Arbitration and Conciliation Act, 1996.
Final Decision
The High Court dismissed the arbitration petition, upholding the arbitral award dated 30 August 2010.
Law Points
- Liquidated damages
- Contractual interpretation
- Section 34 Arbitration and Conciliation Act
- 1996
- Public policy
- Reasonable opportunity




