Bombay High Court Dismisses Appeal Against Arbitral Award in Contract Dispute Over Shipment Date. Minor Deviation from Contract Date Does Not Render Award Perverse Under Section 34 of Arbitration and Conciliation Act, 1996.

High Court: Bombay High Court Bench: BOMBAY
  • 93
Judgement Image
Font size:
Print

Case Note & Summary

The appeal arose from a judgment of a Learned Single Judge dismissing a petition under Section 34 of the Arbitration and Conciliation Act, 1996, challenging an arbitral award dated 1 July 2011. The dispute involved a contract dated 27 December 2010 between M/s. Chemipex (Appellant) and M/s. Shlok Chemicals (Respondent) for supply of 210 Metric Tons of Hydrogen Peroxide originating in China, with shipment to be effected before 20 January 2011. The Appellant contended that shipment was effected on 20 January 2011, and thus it was not bound to take delivery. The dispute was referred to arbitration by the Chemical and Alkali Merchants' Association. The Arbitral Tribunal, by a majority, held that the deviation in shipment date was minor considering general market practice, and directed the Appellant to pay compensation of Rs.4 lacs if it did not take delivery. The Learned Single Judge rejected the challenge, holding that the Tribunal consisted of merchants aware of trade practice and the view was not perverse. In appeal, the Appellant argued that the Tribunal failed to consider Section 55 of the Contract Act, 1872, making the contract voidable, and that no evidence supported the damages. The Respondent argued that the Tribunal's decision was based on trade practice and the Appellant had not produced evidence of repudiation by its buyer. The Division Bench held that the scope under Section 34 is limited, and the Tribunal's view was a possible view on facts. The appeal was dismissed, upholding the award and the Single Judge's order.

Headnote

A) Arbitration - Challenge to Arbitral Award - Section 34 of Arbitration and Conciliation Act, 1996 - Scope of Interference - The court held that the view taken by the Arbitral Tribunal, consisting of trade experts, that the deviation in shipment date was minor based on general market practice, was a possible view and not perverse. Hence, no interference under Section 34 is warranted (Paras 4-8).

B) Contract Act - Time of Essence - Section 55 of Contract Act, 1872 - Minor Deviation - The Arbitral Tribunal considered the general practice in the market and held that the deviation regarding the date of shipment was minor. The court upheld this finding, noting that the Tribunal was aware of trade practices (Paras 3-5).

C) Arbitration - Damages - Award of Compensation - The Arbitral Tribunal awarded Rs.4 lacs as compensation. The court found that the award was based on the Tribunal's appreciation of facts and trade practice, and the Appellant failed to produce evidence of repudiation by its buyer. Hence, the award was not without foundation (Paras 5-6).

Subscribe to unlock Headnote Subscribe Now

Issue of Consideration

Whether the arbitral award holding that a deviation in shipment date was minor and awarding compensation is liable to be set aside under Section 34 of the Arbitration and Conciliation Act, 1996.

Subscribe to unlock Issue of Consideration Subscribe Now

Final Decision

The appeal is dismissed. The order of the Learned Single Judge dated 9 April 2012 dismissing the Arbitration Petition under Section 34 of the Arbitration and Conciliation Act, 1996 is upheld. The arbitral award dated 1 July 2011 is sustained.

Law Points

  • Arbitration
  • Contract Act
  • Section 55
  • Section 34
  • Minor Deviation
  • Trade Practice
  • Perversity
Subscribe to unlock Law Points Subscribe Now

Case Details

2013 LawText (BOM) (01) 46

Appeal No.397 of 2012 in Arbitration Petition No.832 of 2011

2013-01-21

Dr. D.Y. Chandrachud, A.A. Sayed

Mr. Suraj Almeida i/b Mr. Gul Madnani for the Appellant, Mr. Prakash L. Mahadik for the Respondent

M/s. Chemipex

M/s. Shlok Chemicals

Subscribe to unlock Case Details (Citation, Judge, Date & more) Subscribe Now

Nature of Litigation

Appeal against dismissal of petition under Section 34 of Arbitration and Conciliation Act, 1996 challenging an arbitral award.

Remedy Sought

Appellant sought to set aside the arbitral award and the order of the Learned Single Judge dismissing the petition.

Filing Reason

Appellant challenged the arbitral award on grounds that the Tribunal failed to consider Section 55 of Contract Act and awarded damages without evidence.

Previous Decisions

Arbitral Tribunal dated 1 July 2011 directed Appellant to pay Rs.4 lacs compensation; Learned Single Judge dismissed the petition under Section 34 on 9 April 2012.

Issues

Whether the Arbitral Tribunal erred in not applying Section 55 of the Contract Act, 1872, making the contract voidable due to delay in shipment? Whether the award of Rs.4 lacs compensation was without any evidence and thus perverse?

Submissions/Arguments

Appellant argued that shipment was on 20 January 2011, after the stipulated date, so contract was voidable under Section 55 of Contract Act; also, no evidence supported the damages. Respondent argued that the Tribunal consisted of trade experts who found the deviation minor based on market practice, and the Appellant failed to produce evidence of repudiation by its buyer.

Ratio Decidendi

The scope of challenge under Section 34 of the Arbitration and Conciliation Act, 1996 is limited. The Arbitral Tribunal, consisting of trade experts, took a possible view based on general market practice that the deviation in shipment date was minor. Such a view is not perverse and does not warrant interference. The award of compensation was based on the Tribunal's appreciation of facts and trade practice.

Judgment Excerpts

The Tribunal however held that the deviation in the present case regarding the date of shipment was a minor deviation and had regard to the general practice followed in the market. The Learned Single Judge held that the view taken by the Arbitral Tribunal was based on a general practice followed in the market and being a possible view of the facts was certainly not a perverse view.

Procedural History

Contract dated 27 December 2010; dispute referred to arbitration; Arbitral Tribunal (Chemical and Alkali Merchants' Association) passed award on 1 July 2011; Appellant filed Arbitration Petition No.832 of 2011 under Section 34; Learned Single Judge dismissed petition on 9 April 2012; Appellant filed Appeal No.397 of 2012; Division Bench heard and dismissed appeal on 21 January 2013.

Acts & Sections

  • Arbitration and Conciliation Act, 1996: Section 28(1)(a), Section 28(2), Section 34
  • Contract Act, 1872: Section 55
Subscribe to unlock full Legal Analysis Subscribe Now
Related Judgement
High Court Bombay High Court Quashes Condition to Absorb Surplus Staff in Educational Institution Staffing Case. Condition Imposed by Deputy Director of Education Held Unlawful as Per Canossa Society Precedent.
Related Judgement
High Court Bombay High Court Upholds Civil Court Jurisdiction in M.R.T.P. Act Notice Challenge — Notice Void Ab Initio for Non-Compliance with Minimum 30-Day Period. The court held that a notice under Section 53(1) of the Maharashtra Regional and Town Plannin...