Bombay High Court Upholds BEST's Right to Recover Electricity Dues for Under-Recording Due to Loose Connections — Consumer Liable for Unrecorded Consumption Despite Absence of Malice. The court held that a consumer must pay for electricity actually consumed even if the meter under-recorded due to a technical defect, as the consumer had the benefit of the supply and the defect was not disputed.

High Court: Bombay High Court In Favour of Prosecution
  • 169
Judgement Image
Font size:
Print

Case Note & Summary

The case involves a dispute between the Municipal Corporation for Greater Bombay (BEST Undertaking) and Sharda Dyeing & Printing Works, a consumer of electricity. The consumer had three meters; one meter (0442967) showed a sudden drop in consumption from May 3, 1994. Upon inspection on December 7, 1995, it was found that the meter was under-recording consumption by 65.76% due to the secondary circuit of the current transformer being open on the red and yellow phases and a loose potential connection. The consumer did not dispute the fact of under-recording but argued that the defect was not due to any fault on its part and that it was not liable to pay for the unrecorded consumption. The BEST Undertaking issued a supplementary bill for the period from May 1994 to December 1995, which the consumer challenged. The court held that the consumer is liable to pay for the electricity actually consumed, even if the under-recording was due to a technical defect not attributable to the consumer. The court reasoned that the consumer had the benefit of the electricity and that the defect was discovered during a routine check. The court directed the consumer to pay the arrears in installments, with interest, and restrained the BEST from disconnecting supply subject to payment. The judgment emphasizes that the liability to pay for electricity consumed is not dependent on the correctness of the meter alone, and that the supplier is entitled to recover dues for unrecorded consumption where the fact of under-recording is admitted or proved.

Headnote

A) Electricity Law - Liability for Unrecorded Consumption - Loose Connection in Current Transformer - The court considered whether a consumer is liable to pay for electricity actually consumed but not recorded due to a technical defect (loose connection) in the metering equipment, absent any fraud. Held that the consumer is liable to pay for the actual consumption, as the defect was not attributable to the consumer and the electricity was admittedly used. The court directed the consumer to pay the arrears based on the estimated consumption for the period of under-recording. (Paras 1-10)

B) Electricity Law - Section 26 of the Electricity Act, 1910 - Dispute as to Correctness of Meter - The court examined the scope of Section 26, which provides for testing of meters and determination of disputes. Held that the provision does not bar the supplier from recovering dues for unrecorded consumption where the meter is found to be under-recording due to a technical defect, and the consumer does not dispute the fact of under-recording. (Paras 5-8)

C) Electricity Law - Burden of Proof - Consumer's Knowledge of Defect - The court noted that the consumer did not dispute the under-recording and had the benefit of the electricity. Held that the burden is on the consumer to show that the defect was not due to his fault, and in the absence of any evidence of tampering, the consumer must pay for the actual consumption. (Paras 6-9)

Subscribe to unlock Headnote Subscribe Now

Issue of Consideration

Whether a consumer is liable to pay for electricity consumed but not recorded due to a loose connection in the secondary circuit of the current transformer, even in the absence of any fraud or malpractice on the part of the consumer.

Subscribe to unlock Issue of Consideration Subscribe Now

Final Decision

The court allowed the writ petition in part, directing the consumer to pay the arrears for the unrecorded consumption in installments with interest, and restrained BEST from disconnecting supply subject to compliance with the payment schedule.

Law Points

  • Electricity supply
  • under-recording of consumption
  • loose connection
  • current transformer
  • potential connection
  • liability of consumer
  • absence of fraud
  • Section 26 of the Electricity Act
  • 1910
  • Section 24 of the Indian Electricity Act
  • Bombay Municipal Corporation Act
  • 1888
Subscribe to unlock Law Points Subscribe Now

Case Details

2005 LawText (BOM) (02) 335

WRIT PETITION NO. 646 OF 2001

2005-02-04

Dr. D.Y. Chandrachud, J.

Mr. H. Toor i/b. Cr.Bayley & Co. for the Petitioner, Mr. Tejas Vora i/b. Ms. Neeta Parikh for Respondent No.1

Municipal Corporation for Greater Bombay

Sharda Dyeing & Printing Works & Ors.

Subscribe to unlock Case Details (Citation, Judge, Date & more) Subscribe Now

Nature of Litigation

Writ petition challenging the demand for payment of electricity dues for unrecorded consumption due to a technical defect in the meter.

Remedy Sought

The petitioner (BEST) sought to recover arrears for electricity consumed but not recorded due to a loose connection; the respondent consumer sought to avoid payment.

Filing Reason

The consumer disputed the supplementary bill raised by BEST for the period of under-recording, claiming no liability as the defect was not due to its fault.

Issues

Whether the consumer is liable to pay for electricity consumed but not recorded due to a technical defect in the metering equipment, absent any fraud or malpractice. Whether Section 26 of the Electricity Act, 1910 bars the supplier from recovering dues for unrecorded consumption when the meter is found to be under-recording.

Submissions/Arguments

Petitioner (BEST): The meter was under-recording due to a loose connection in the current transformer secondary circuit; the consumer had the benefit of the electricity and must pay for actual consumption. Respondent (Consumer): The defect was not due to any fault of the consumer; the meter was not tampered with; the consumer should not be liable for the unrecorded consumption.

Ratio Decidendi

A consumer of electricity is liable to pay for the electricity actually consumed, even if the meter under-records due to a technical defect not attributable to the consumer, as long as the fact of under-recording is admitted or proved. The supplier is entitled to recover the dues for the unrecorded consumption based on estimated actual usage.

Judgment Excerpts

The First Respondent is a consumer of the Bombay Electric Supply and Transport Undertaking and carries on the business of dyeing and printing. On being checked, it was found that the meter was under recording the consumption of electricity by 65.76% due to the Secondary Circuit of the Current Transformer being open on the red and yellow phases and because of a loose potential connection on the red and yellow phases. Thus even though the supply was being used by the 1st Respondent as usual, due to the above disconnection in wiring, the consumption recorded on the meter was only one third of the actual.

Procedural History

The BEST Undertaking filed a writ petition in the Bombay High Court challenging the consumer's refusal to pay the supplementary bill for unrecorded consumption. The matter was heard by a single judge, Dr. D.Y. Chandrachud, J., who delivered the judgment on February 4, 2005.

Acts & Sections

  • Electricity Act, 1910: Section 26
  • Indian Electricity Act, 1910: Section 24
  • Bombay Municipal Corporation Act, 1888:
Subscribe to unlock full Legal Analysis Subscribe Now
Related Judgement
High Court High Court of Karnataka Acquits Accused in Murder Case Due to Unreliable Identification and Lack of Corroboration. Conviction under Sections 143, 147, 148, 447, 302 read with 149 IPC set aside as sole eyewitness testimony was inconsistent and not sup...
Related Judgement
Supreme Court Supreme Court Allows Appeal by Defendant in Punjab Customary Law Succession Dispute; Adopted Son's Claim to Natural Grandfather's Estate Rejected. Customary Law Among Brahmins and Khatris of Amritsar District Bars Adopted Son from Inheriting Natural ...